70Z04724RPCNI0007 Rio Bayamon Phase I_RFI Log - Responses.pdf

PDF 104 KB Posted

Attached to
Design/Build Construction for San Juan Hurricane Rebuild Rio Bayamon at USCG Base San Juan, San Juan, PR (Phase 1-Reprocurement)
Solicitation number
70Z04724RPCNI0007
Issued by

About this file

This document is an RFI (Request for Information) log related to a federal Design-Build contract opportunity for the reconstruction of facilities at the U.S. Coast Guard Sector San Juan in Puerto Rico, following damage from Hurricane Maria.

The key details are:

  • The solicitation number is 70Z04724RPCNI0007 and the contract is for the Design/Build Construction for San Juan Hurricane Rebuild Rio Bayamon at USCG Base San Juan, San Juan, PR (Phase 1-Reprocurement).
  • The project scope includes new infrastructure, utilities distribution, and resiliency upgrades, including a new campus-wide generator system and water storage tank with pump.
  • Several questions and answers are provided related to the period of performance, utility coordination fees, environmental testing, insurance requirements, noise mitigation, fuel storage, and coordination with the existing Building Automation System.
  • The proposal due date was originally extended to August 9, 2024, and the performance period was increased from 389 days to 783 days.
  • The procurement is limited to contractors on the current DHS/USCG National Multiple Award Construction Contract III (NMACC III - Pool 1).

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date Posted

ID # Document Page Section Paragraph Answered Through

1 TOA PG. 3 RFP Part 1 PoP

The current period of performance of 389 calendar days will not be adequate to satisfy the Government’s design submittal requirements, manage the procurement of long lead items and perform the construction works. To mitigate this risk to the Government, and to enable the offeror to complete the design and construction in accordance with the Government requirements, will the Government please consider increasing the overall period of performance to a minimum of 831 calendar days?

The period of performace has been extended to 783 days. 6/21/24 8/7/2024

2 Contracting

Task Order

Announceme nt

Subcontractors and suppliers have notified us that preparations of quotations for this Design-Build project will take more time than projects that are already fully designed. Information obtained from the site visit last week is being analyzed and incorporated into project narratives and estimates. Please consider extending the proposal due date by two weeks to allow for development and submission of accurate and cost competitive proposals.

Original proposal due date was extended to 9 August 2024. Please monitor

SAM.gov and email for amendments to orignal solicitation.

7/16/24 7/30/2024

3 Contracting

Task Order

Announceme nt

The Contract performance period is identified as 389 calendar days.

This performance period is insufficient for a Design-Build project with significant long lead equipment such as transformers and generators.

Assuming nine months for design, 12 months for long lead equipment, and six months for contract completion beyond delivery of long lead equipment, please revise the contract performance period to 27 months / 821 calendar days.

The period of performace has been extended to 783 days. 7/16/24 8/7/2024

4 Electrical E-601

For reconnection purposes, please provide the size/description of the existing electrical feeders (Sheet Key Note #2) that runs from SU-1 &

SU-2 up to existing Pad Mounted Transformers (Housing Cluster)

Exisiting sizes will need to be investigated by the design builld contractor. A separate site visit can be arranged to confirm this information.

7/16/24 7/30/2024

5 Electrical E-606

Is the Contractor required to conduct elecrical testing on the existing primary feeders (that will be reconnected) running from SU-1 & SU-2 up to the new Pad Mounted Transformers? Please advise.

No, testing the existing cables is not part of the scope, however this was discussed with the Government during RFP document phase. "High Pot" testing may damage the existing cables. IF the DB believes cables should be tested this will require further disucssions with the government.

7/16/24 7/30/2024

6 Electrical E-003

Since it is not shown or defined on the One Line Diagram (Sheet E-

610), Please clarify the purpose of the ''electrical feeder'' running from the Gate House up to the Lift Station Pump Vault shown on the Partial

Electrical Site Plan (Sheet E-003) and also provide the description and size (conduits & wires) of this ''electrical feeder''.

Its for continuity of service to the gate house to correct the voltage issue at the gate house, as they it currently gets two different voltages from the generator and source transformer.

7/16/24 7/30/2024

7 Electrical

Section

01800 1.13

Please confirm generator's diesel tanks: 1.2MW RNH-1 (10,000 gals) &

230kW RBH-2 (936 gals) shall not be completely filled with fuel by the contractor under this task order.

Confirmed 7/16/24 7/30/2024

Fire

Protection/Life

Safety

01800 Para

1.4; 1.10;

1.11

As the water storage tank will serve fire water demand as well as domestic water demand, please confirm whether it needs to be fully compliant with NFPA, including number of manways

Yes, it needs to be fully compliant with NFPA including number of manways. 7/16/24 7/30/2024

Electrical 01800 Para

1.13

To ensure the competing D/B contractors are consistently accounting for utility coordination fees, please provide an allowance for PREPA fees for disconnection of existing transformers and connection of primary to new transformers

The contractor is responsible to account for possible utility fees, coordinate with local utility companies and include the cost in the proposal 7/16/24 7/30/2024

Environmental Please confirm no lead paint is present at any areas to be affected by this project LBP surveying was excluded from RBH during design. 7/16/24 7/30/2024

Environmental Please confirm no PCBs are present at any areas to be affected by this project PCB surveying was excluded from RBH during design. 7/16/24 7/30/2024

General Please confirm that there is no DBA waiver, and that the cost of DBA insurance must be included in addition to any locally required workmen's compensation programs

There is no DBA waiver. 7/16/24 8/7/2024

13 7 1800 1.3.1.1

The RFP states that the project shall require compliance with the

Guiding Principles and verification of documentation demonstrating compliance with the Guiding Principles shall be provided by the Green

Building Initiative's (GBI) Guiding Principles Compliance Assessment

Program. Further it states that the Contractor shall register and pay all fees associated with third-party review and certification. Due to the scope of the project and limited building square footage, please confirm that third-party building certification is not required for the project.

Third party building certification is not required for this project. 7/16/24 7/30/2024

RFI Log - 70Z04724RPCNI0007: Design/Build San Juan Hurricane Rebuild Rio Bayamon at

Base San Juan, San Juan, PR (Phase 1-Reprocurement)

Discipline Date

Submitted

Question Gov't Response

Include the following email addresses on all correspondence: Yolanda.l.davis@uscg.mil, sharan.a.lind@uscg.mil

RFP Reference

Section

01800/01900

1.3.1

Reference to

Attachment

C Page 2 &

Attachment

C page 10 2-

4.2.2 Noise

Mitigation

Table 2-1 Generator Noise Level Regulation

a) Would the Noise Zone for this Project be considered Residential for both Generators to be installed; or will the Generator located at the

Pump House be classified differently? The site is mainly residential, however the Government may clasify it differently to allow for greater dB levels. Final decision by the Government.

7/16/24 7/30/2024

Section

01800

1.3.1

Reference to

Attachment

C Page 2 &

Attachment

C page 10 2-

4.2.2 Noise

Mitigation

Table 2-1 Generator Noise Level-

The max Dba for any noise zone is 72 Dba. All Major manufacturers we have contacted state the best Dba they can achieve will be 72.

a) Will this meet the requirement of the project?

b) If not, will Table 2-1 be the only basis considered?

Utilize sound attenuating enclosure providing the best practical attenuation.

Notify the Government that 72 Dba is the max achievable attenuation. The

Government will need to evaluate table 2-1 vs. other site dBA requirements.

7/16/24 7/30/2024

Section

01800

1.13 Page 5

& 1.13.15.1

Table 2 Fuel Utilization Requires the 230KW RBH-2 to have a Subbase

Tank sized for 58.6 hrs assuming 100% use for 58.6 Hrs. Section

1.13.15.1 calls for a subbase tank for RBH-2 to support 48 hrs at 100% as a minimum. What is the required level of fuel storage required?

48hrs minimum is required. Closest nominal tank size provides above 48hrs depending on manufacturer.

7/16/24 7/30/2024

Section

01800 1.8

Specs

1.8.2.5.3

Design Load

Criteria

Please confirm Under Occupancy (Risk) Category - Utility Foundations and structures IV and All other Foundations and Structures are II for seismic requirements. Does this apply to all exterior mounted Electrical

Switchgear and Generator enclosures?

All other foundations and structures are Category II for seismic requirements. 7/16/24 7/30/2024

18 N/A N/A N/A In order to provide competitive and accurate pricing, we are requesting minimum 2-week extension to the bid date after all PPIs have been responded to and sent to the contractor.

refer to RFI no. 2 7/16/24 7/30/2024

19 24 1.13.16 1.13.16.1

Will the Government please provide a technician to integrate

Advanced Metering Infrastructure data points from the new installed meters to the existing DAS Obvious Model A8812? The RFP calls for the provision of MODBUS current transformers / meters compatible with the existing (AMI) but does not specify who is responsible for integrating the new data points (metering data) with the existing system.

The contractor is responsible for installation of equipment. USCG and this contractor will need to coordinate with "Obvious" for a technicion to integrate the new componenents into the existing system.

7/16/24 7/30/2024