This is a pricing template attachment for the TSA's Checked Baggage Screening Equipment Deployment Services (SEDS) solicitation (70T04026R7672N004), establishing standardized unit pricing for equipment deployment, labor, and support services across an 8-year contract period.

The template covers pricing for large screening equipment (Smiths CTX-5800, Leidos CT-80DR+, L3 3DX6700 series, Smiths CTX-9000/9400/9800 medium-speed systems), small screening equipment (ETD units including Smiths Ioscan 500DT and Leidos QS B220), and furniture, fixtures, and equipment (FF&E). Pricing is stratified by service categories including shipping (with three notice-period tiers: greater than 15 business days, 3-15 business days, and urgent), rigging, installation, de-installation, packaging/crating, temporary storage at different airport categories (CAT X/I versus CAT II/III/IV), and site design CAD services. Equipment-specific components such as pedestals, tunnels, powered conveyors, PVS/SVS viewing stations, and UPS systems are itemized with distance-based shipping ranges (0-50 miles through 2000+ miles to/from TSALC). The labor section defines 16 fully-loaded labor categories spanning Years 1-8, including Engineer Levels 1-4, various Manager roles, Program Managers I-II, Administrative and Project Specialist positions, trades personnel (Master Tradesman, Foreman, Journey Tradesman, Apprentice Tradesman) differentiated by airport category and region, and specialized roles such as Site Lead and Reimbursement Agreement Invoice Reviewer. The template includes sample task order pricing examples demonstrating deployment scenarios and a separate Program Management Task Order pricing framework covering transition periods, base year, and subsequent contract years with hourly labor rate multipliers across all staffing categories.

View the file

Other files

File Type Posted
SEDS CB RFP 70T04026R7672N004 Amendment 2 - clean.docx DOCX document
SEDS CB RFP 70T04026R7672N004 Amendment 2 - track changes.docx DOCX document
SEDS CP RFP - Amendment 2 SF30.pdf PDF
SEDS CP RFP Questions and Answers updated 4.30.2026.pdf PDF
SEDS CP RFP Questions and Answers updated.pdf PDF
SEDS CP RFP Questions and Answers.pdf PDF
SEDS CB RFP 70T04026R7672N004 Amendment 1 - track changes.docx DOCX document
SEDS CB RFP 70T04026R7672N004 Amendment 1 - clean.docx DOCX document
SEDS CP RFP - Amendment 1 SF30.pdf PDF
RFP Att03 - CB SEDS II Program Management Task Order - Amendment 1.docx DOCX document
RFP Att02 - Checked Baggage SEDS Pricing Template.xlsx XLSX spreadsheet
Contract Att04 - CDRL D001 - CB EDS Decommission Report and Checklist v4_Template_08.12.2025.xlsx XLSX spreadsheet
Contract Att03 - CDRL A003 - CB Monthly Status Report_ Template_02.03.2025.docx DOCX document
Contract Att01 - CDRL B002 - OTA Invoice Review Report_Template_08.12.2025.docx DOCX document
RFP Att04 -DHS Subcontracting Plan Review Checklist.pdf PDF
Contract Att05 - Acquisitions Requirements Order Worksheet v2.2_Template_08.12.2025.xlsx XLSX spreadsheet
Contract Att06 - CB Test Readiness Notification_Template_02.03.2025.docx DOCX document
SEDS CB RFP 70T04026R7672N004.pdf PDF
RFP Att1 - SEDS CB SF-1449.pdf PDF
RFP Att03 - CB SEDS II Program Management Task Order.docx DOCX document
Contract Att08 - ITAR_Terms-Conditions_3.31.26.docx DOCX document
Contract Att07 - DSD Acronym List 03-11-26.docx DOCX document
Questions on SEDS CB RFP.xlsx XLSX spreadsheet
Contract Att02 - CDRL A004 - CB Weekly Status Report_ Template_08.12.2025.xlsx XLSX spreadsheet
Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.A CB Pricing Template Year 1

Equipment TypeShipping (if given greater than 15 business days notice)Shipping (if given between 3 business days and 15 business days notice)Urgent Shipping (if given less than 3 business days notice)Rigging (includes equipment and labor)InstallationDe-installation (wrap & strap includes material and labor - Condition Code X)De-installation (for all except for Condition Code X)Packaging/Crating (includes materials and labor)Temporary Storage at CAT X and I AirportsTemporary Storage at CAT II, III, and IV Airports
Large Screening Equipmentper unit, shipping rangeUnit Priceper unit, shipping rangeUnit Priceper unit, shipping rangeUnit PriceFor 1-2 UnitsPriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Smiths CTX-5800
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Leidos CT-80DR+
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Reduce Size EDS Pedestal0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Tunnel0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Powered Conveyor0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
PVS/SVS0 - 50 miles0 - 50 miles0 - 50 miles1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Computer Tower
(decomissioning CCX inline system PVS/SVS computer towers only)0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
L3 3DX6700, 3DX6700-ES, 3DX6600, 3DX6000
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Smiths CTX-9000, CTX-9400, CTX-9800
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Medium Speed MUX Kit0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
Small Screening EquipmentUnit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnit (wrap & strap not applicable for ETD)Unit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
ETD
Smiths Detection Ioscan 500DT1 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
ETD
Leidos QS B2201 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
FF&E (see definitions on next tab)Unit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Lift Table1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Lightweight Parts1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Heavy Parts1 unit1 unit1 unitall parts for project, daily price1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units11+ units11+ units11+ units
Furniture1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units
UPS associated with Medium Speed EDS (small - 40 and 60 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (80 - 120 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (large - 160 and 400 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles

Site Design - CAD Hourly

The Vertex Company Proprietary &"Arial,Regular"&9TSA CB SEDS Solicitation Number: 70T04020R9AP4052&"-,Regular"&11

&"Arial,Regular"&9The Vertex Company Proprietary Vol II-Tab 4-&P

1.B CB Pricing Template Year 2

Equipment TypeShipping (if given greater than 15 business days notice)Shipping (if given between 3 business days and 15 business days notice)Urgent Shipping (if given less than 3 business days notice)Rigging (includes equipment and labor)InstallationDe-installation (wrap & strap includes material and labor - Condition Code X)De-installation (for all except for Condition Code X)Packaging/Crating (includes materials and labor)Temporary Storage at CAT X and I AirportsTemporary Storage at CAT II, III, and IV Airports
Large Screening Equipmentper unit, shipping rangeUnit Priceper unit, shipping rangeUnit Priceper unit, shipping rangeUnit PriceFor 1-2 UnitsPriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Smiths CTX-5800
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Leidos CT-80DR+
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Reduce Size EDS Pedestal0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Tunnel0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Powered Conveyor0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)$ - 0
PVS/SVS0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Computer Tower
(decomissioning CCX inline system PVS/SVS computer towers only)0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
L3 3DX6700, 3DX6700-ES, 3DX6600, 3DX6000
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Smiths CTX-9000, CTX-9400, CTX-9800
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Medium Speed MUX Kit0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
Small Screening EquipmentUnit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnit (wrap & strap not applicable for ETD)Unit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
ETD
Smiths Detection Ioscan 500DT1 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
ETD
Leidos QS B2201 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
FF&E (see definitions on next tab)Unit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Lift Table1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Lightweight Parts1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Heavy Parts1 unit1 unit1 unitall parts for project, daily price1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units11+ units11+ units11+ units
Furniture1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units
UPS associated with Medium Speed EDS (small - 40 and 60 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (80 - 120 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (large - 160 and 400 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles

Site Design - CAD Hourly

The Vertex Company Proprietary &"Arial,Regular"&9TSA CB SEDS

&"Arial,Regular"&9The Vertex Company Proprietary Vol II-Tab 4-&P

1.C CB Pricing Template Year 3

Equipment TypeShipping (if given greater than 15 business days notice)Shipping (if given between 3 business days and 15 business days notice)Urgent Shipping (if given less than 3 business days notice)Rigging (includes equipment and labor)InstallationDe-installation (wrap & strap includes material and labor - Condition Code X)De-installation (for all except for Condition Code X)Packaging/Crating (includes materials and labor)Temporary Storage at CAT X and I AirportsTemporary Storage at CAT II, III, and IV Airports
Large Screening Equipmentper unit, shipping rangeUnit Priceper unit, shipping rangeUnit Priceper unit, shipping rangeUnit PriceFor 1-2 UnitsPriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Smiths CTX-5800
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Leidos CT-80DR+
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Reduce Size EDS Pedestal0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Tunnel0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Powered Conveyor0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
PVS/SVS0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Computer Tower
(decomissioning CCX inline system PVS/SVS computer towers only)0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
L3 3DX6700, 3DX6700-ES, 3DX6600, 3DX6000
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Smiths CTX-9000, CTX-9400, CTX-9800
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Medium Speed MUX Kit0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
Small Screening EquipmentUnit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnit (wrap & strap not applicable for ETD)Unit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
ETD
Smiths Detection Ioscan 500DT1 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
ETD
Leidos QS B2201 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
FF&E (see definitions on next tab)Unit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Lift Table1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Lightweight Parts1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Heavy Parts1 unit1 unit1 unitall parts for project, daily price1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units11+ units11+ units11+ units
Furniture1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units
UPS associated with Medium Speed EDS (small - 40 and 60 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (80 - 120 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (large - 160 and 400 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles

Site Design - CAD Hourly

The Vertex Company Proprietary &"Arial,Regular"&9TSA CB SEDS

&"Arial,Regular"&9The Vertex Company Proprietary Vol II-Tab 4-&P

1.D CB Pricing Template Year 4

Equipment TypeShipping (if given greater than 15 business days notice)Shipping (if given between 3 business days and 15 business days notice)Urgent Shipping (if given less than 3 business days notice)Rigging (includes equipment and labor)InstallationDe-installation (wrap & strap includes material and labor - Condition Code X)De-installation (for all except for Condition Code X)Packaging/Crating (includes materials and labor)Temporary Storage at CAT X and I AirportsTemporary Storage at CAT II, III, and IV Airports
Large Screening Equipmentper unit, shipping rangeUnit Priceper unit, shipping rangeUnit Priceper unit, shipping rangeUnit PriceFor 1-2 UnitsPriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Smiths CTX-5800
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Leidos CT-80DR+
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Reduce Size EDS Pedestal0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Tunnel0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Powered Conveyor0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
PVS/SVS0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Computer Tower
(decomissioning CCX inline system PVS/SVS computer towers only)0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
L3 3DX6700, 3DX6700-ES, 3DX6600, 3DX6000
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Smiths CTX-9000, CTX-9400, CTX-9800
Medium Speed EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2 units2 units2 units2 units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles2000+ miles2000+ miles
Medium Speed MUX Kit0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
Small Screening EquipmentUnit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnit (wrap & strap not applicable for ETD)Unit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
ETD
Smiths Detection Ioscan 500DT1 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
ETD
Leidos QS B2201 unit1 unit1 unit1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units2 - 4 units1 unit per week (week 2 +)1 unit per week (week 2 +)
5+ units5+ units5+ units5+ units5+ units5+ units5+ units
FF&E (see definitions on next tab)Unit shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnits shipping to the same locationUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Lift Table1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Lightweight Parts1 unit1 unit1 unit
2 - 20 units2 - 20 units2 - 20 units
21 - 50 units21 - 50 units21 - 50 units
51+ units51+ units51+ units
Heavy Parts1 unit1 unit1 unitall parts for project, daily price1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units11+ units11+ units11+ units
Furniture1 unit1 unit1 unit1 unit
2 - 10 units2 - 10 units2 - 10 units2 - 10 units
11+ units11+ units11+ units11+ units
UPS associated with Medium Speed EDS (small - 40 and 60 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (80 - 120 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles
UPS associated with Medium Speed EDS (large - 160 and 400 kva)0 - 200 miles0 - 200 miles0 - 200 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
201 - 499 miles201 - 499 miles201 - 499 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles2000+ miles2000+ miles

Site Design - CAD Hourly

The Vertex Company Proprietary &"Arial,Regular"&9TSA CB SEDS

&"Arial,Regular"&9The Vertex Company Proprietary Vol II-Tab 4-&P

1.E CB Pricing Template Year 5

Equipment TypeShipping (if given greater than 15 business days notice)Shipping (if given between 3 business days and 15 business days notice)Urgent Shipping (if given less than 3 business days notice)Rigging (includes equipment and labor)InstallationDe-installation (wrap & strap includes material and labor - Condition Code X)De-installation (for all except for Condition Code X)Packaging/Crating (includes materials and labor)Temporary Storage at CAT X and I AirportsTemporary Storage at CAT II, III, and IV Airports
Large Screening Equipmentper unit, shipping rangeUnit Priceper unit, shipping rangeUnit Priceper unit, shipping rangeUnit PriceFor 1-2 UnitsPriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit PriceUnitUnit Price
Smiths CTX-5800
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Leidos CT-80DR+
Reduced Size EDS0 - 50 miles0 - 50 miles0 - 50 milesRegular Rigging - Daily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles
201 - 499 miles201 - 499 miles201 - 499 milesVariable Reach Forklift and/or Specialized Equipment - Daily (8 Hours)
500 - 1000 miles500 - 1000 miles500 - 1000 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
1000 - 2000 miles1000 - 2000 miles1000 - 2000 milesCrane - Daily (8 Hours)
2000+ miles (to or from TSALC)2000+ miles2000+ miles
Reduce Size EDS Pedestal0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles
500 - 1000 miles500 - 1000 miles500 - 1000 miles
1000 - 2000 miles1000 - 2000 miles1000 - 2000 miles
2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)2000+ miles (to or from TSALC)
Reduce Size EDS Tunnel0 - 50 miles0 - 50 miles0 - 50 milesDaily (8 Hours)1 unit1 unit1 unit1 unit1 unit per week (week 1)1 unit per week (week 1)
51 - 200 miles51 - 200 miles51 - 200 miles2+ units2+ units2+ units2+ units1 unit per week (week 2 +)1 unit per week (week 2 +)
(when shipped separate from unit)201 - 499 miles201 - 499 miles201 - 499 miles

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .