This is Amendment One to a Request for Quote (RFQ) for the Federal Law Enforcement Training Centers (FLETC) Fence Upgrade project. The solicitation number is 70LGLY26QSSB00077, issued by the Department of Homeland Security's Federal Law Enforcement Training Centers in Glynco, Georgia, with an effective date of August 26, 2026.
The project requires contractors to upgrade and replace existing perimeter fencing at the FLETC facility in compliance with Executive Order 14111 and Interagency Security Committee (ISC) requirements for federal facility physical security. The work must adhere to ISC, DHS, and FLETC physical security requirements, with the fencing material meeting ASTM M30/P1 standards. The period of performance is 180 days, from September 30, 2026 to March 31, 2027. Amendment One corrects administrative errors from the original solicitation, including conflicting solicitation numbers, updates to dates, and clarifications on fencing quantity (referenced in Attachment 2, Appendix A). Questions from bidders are due no later than September 2, 2026. A mandatory site visit will be held on September 1, 2026 at 10:00 AM at the front gate visitor center; contractors must submit Visitor Access Request (VAR) forms by August 31, 2026. The bid guarantee is 20 percent of the bid amount or $3,000,000, whichever is less, due at time of bid submission. Performance bonds and payment bonds are due from the awardee within 10 days of award. All attachments including the scope of work, site map, site visit instructions, wage determination, typical fence drawing, and typical fence photo have been provided for reference, with no intentional preference given to specific brand names provided that fencing complies with stated requirements.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Traci A. Davis
See continuation page
DEPARTMENT OF HOMELAND SECURITY
FEDERAL LAW ENFORCEMENT TRAINING CENTERS
1131 CHAPEL CROSSING RD
GLYNCO GA 31524
DEPARTMENT OF HOMELAND SECURITY
FEDERAL LAW ENFORCEMENT TRAINING CENTERS
1131 CHAPEL CROSSING RD
PRO BLDG 681
GLYNCO GA 31524
70LGLY 70LGLY
70LGLY26QSSB00077
08/26/2026
08/26/2026
1 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
70LGLY26QSSB00077/0001
AMENDMENT ONE - CORRECTS SOME ADMINISTRATIVE
ERRORS, PROVIDES ADDITIONAL ATTACHMENTS, AND
PROVIDES ADDITONAL CLARIFICATIONS
FLETC Fence Upgrade - FLETC is required to adhere to Executive Order 14111 and the
Interagency Security Committee (ISC) requirements for the physical security of federal facilities. This project will consist of the upgrade and replacement of the existing fencing with an approved perimeter fence designed and constructed in accordance with
ISC, DHS, and FLETC physical security requirements.
Period of Performance: 09/30/2026 to
03/31/2027
ATTACHMENTS:
ATTACHMENT 1 - BID SCHEDULE
ATTACHMENT 2 - SCOPE OF WORK - 1 JULY 2026
ATTACHMENT 3 - SITE MAP
ATTACHMENT 4 - BLANK
ATTACHMENT 5 - SITE VISIT INSTRUCTIONS
ATTACHMENT 6 - VAR FORM
ATTACHMENT 7 - WAGE DETERMINATION
ATTACHMENT 8 - TYPICAL FENCE DRAWING (AMENDMENT
1)
ATTACHMENT 9 - TYPICAL FENCE PHOTO (AMENDMENT 1)
Traci Davis Highlight
Traci Davis Highlight
Amendment One:
All changes/updates to original RFQ are highlighted in blue.
• FAR 52.225-11 reference removed
• Corrections made to conflicting solicitation numbers
• Response date for question changed from 2025 to 2026
• Clarification regarding quantity of fencing – please reference Attachment 2, Appendix A
• The period of performance is updated to 180 days – SOW (Attachment 2) also updated to reflect POP of 180 days. If you as a bidding contractor feel this is not enough time then your proposal should address this issue as well as provide for the time frame that you are proposing and why.
• Questions are due no later than September 2, 2026.
• The bid sheet is meant to be a summary sheet and the back data for your quote can be attached. If not attached then it should be readily available if requested by the Contracting O icer.
• With regard to ASTM M30/P1 requirement – this applies to fencing only.
• The Bid Guarantee is 20% of bid amount or $3,000,000 – which ever is less – this is due at time of bid. The performance bond and payment bonds are due from awardee within 10 of award.
• Additional Attachments have been added – no intentional reference is made to a specific brand name – the drawings/photos are given for reference. Fence that is in compliance with requirements found in the SOW regardless of brand name will be considered.
• Site Visit – This will be held on September 1 at the front gate visitor center. VAR forms are requested to be submitted by August 31. If necessary, contractors arriving at the front visitor center with completed VAR forms and arriving in a timely manner to allow processing can be accommodated. Site visit will proceed at 10am promptly so plan accordingly – this is a very busy site – do not assume you are the only one coming in for the visit at the last minute. The Government wants to accommodate as many as possible but in order to respect everyone’s time including contractors who submitted timely VAR request forms, the site visit will proceed on time.
Traci Davis Highlight
| 70LGLY26QSSB00077-Amendment One |
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
Amendment One_
File details come from the government source that posted it. Updated .