This document contains bid specifications for snow removal services solicited by Salt Lake County Contracts and Procurement on behalf of Facilities Management, Aging and Adult Services, Salt Lake County Health Department, and the District Attorney's offices. The county seeks contractors to provide snow plowing, snow shoveling, application of ice melt for concrete surfaces, and sodium chloride application for parking lots and streets across multiple facility locations. Services are required at seven primary locations: Ellis R. Shipp Public Health Center, Environmental Health Administration, South Main Public Health Center, Magna-Kennecott Senior Center, South Redwood Public Health Center, Household Hazardous Waste facility, Salt Lake County District Attorney Building, and Salt Lake County West Jordan Building. Contractors must respond to snowstorms with accumulation of 2 inches or when called out, with services beginning within one hour of notification. The county may contract with multiple bidders, and all vehicles must be properly registered with current inspections and emissions certifications.
Key specifications require that all snow plowing vehicles be equipped with plows and ice melt spreaders, with ice melt containing 80 percent or greater calcium chloride for concrete areas and sodium chloride permitted only on asphalt surfaces. All de-icing materials must be approved by county Facilities Services, Aging and Adult Services, Salt Lake County Health Department, and the District Attorney's offices. No subcontracting is permitted; contractors must use their own company equipment and vehicles. Contractors are responsible for maintaining safety at all locations and must provide signed notifications or invoices during building occupancy hours and email notifications with read receipts within twelve hours of service completion. Maintenance schedules vary by location, with most facilities requiring Monday through Sunday service with clearance by 6:00 a.m., except the Magna-Kennecott Senior Center, which operates Monday through Friday with 7:00 a.m. clearance. Snow placement restrictions are specific to each facility, with requirements to protect fire hydrants, dumpsters, disabled parking spaces, building entrances, and sidewalk access.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 1 - SPECIFICATIONS
FAC112996-2 SNOW REMOVAL RFC
MAIN SPECIFICATIONS
Minimum Requirements
Meets Spec If No, Indicate
Alternative Y N
1. Crews must respond to snowstorms with accumulation of 2” during the nighttime hours; or be called out. Services to begin within one hour of being notified.
2. All snow plowing vehicles are to be equipped with plows and Ice Melt spreaders.
3. De-icing
a. For de-icing Contractor will use ice/snow melt on concrete areas. (Not Salt). Ice melt must be (80%) or greater of Calcium Chloride.
b. Sodium Chloride may be used on asphalt surfaces only.
c. Ice/snow melt must be approved by the Facilities Services, Aging & Adult Services and division of Salt Lake County Health Department and DA’s offices.
4. Contractor must be able to respond day and night, seven days per week including holidays within one hour of call or snow Depth is 2”.
5. Unless specifically indicated in these specifications, "snow plowing" shall mean "pushing" the snow, and properly placing it to allow for easy access parking for the disabled, vehicles and/or pedestrians, and minimize loss of parking spaces.
6. No subcontracting of snow plowing or de-icing services will be allowed. Contractor will utilize their own company, equipment and vehicles that are capable of plowing and spreading ice melt in a manner that effectively and efficiently provides for the safety of the occupants of the Salt Lake County’s property.
7. Snow piles must not block access to fire hydrants, trash dumpsters or other emergency and public service equipment.
8. Snow piles must not block or interfere with access to and usability of sidewalks, entrances, stairs or driving areas.
9. All driveways must be plowed, (public access from Street).
10. With each call-out the contractor assumes the responsibility for completing all contracted areas in a manner that will leave the area safe for all facility occupancy. It is the contractor’s responsibility to check all contracted areas to determine safety of all locations prior to exiting the property.
11. During hours of building occupancy contractor will have signed notification or invoices for completed work by a Salt Lake County employee located at each location.
12. Notification of services provided will be sent by e-mail with read notification to the building representative within twelve (12) hours of completion of services showing what billable services was done and time service was performed.
13. All vehicles used on Salt Lake County property shall be properly registered including inspection and emissions.
SALT LAKE COUNTY LOCATIONS
A. ELLIS R. SHIPP PUBLIC HEALTH CENTER
4535 South 5600 West
Minimum requirements
Meets Specs
IF NO, INDICATE ALTERNATIVE Y N
1. Days Maintained: Monday through Sunday.
2. Parking lots ONLY.
3. Ice melt shall be used for de-icing on concrete areas and rock salt on asphalt areas.
4. Timing
a. Evening and early morning snow/ice accumulations shall be cleared by 6:00 AM.
b. Contractors need to return to facilities by 6:00 am the day following a storm to see if de-icing is needed.
c. If snow continues to fall, contractor shall return to facilities after 2” additional accumulation of snow until the snowstorm has passed and parking lots are cleared completely of snow and ice.
d. Extra plowing and ice melt treatments shall be required and completed on an additional 2” accumulation of snow due to lake effect snow fall, high winds, and drifting snow.
e. It shall be the responsibility of the winning bidder(s) to monitor the facility through the storm to assure that the facility is plowed and de-iced as needed.
5. Parking Lots
a. East- Push snow to the south side of the lot.
b. West- Push snow to the north side of the lot.
6. No snow shall be piled in front of dumpster.
7. Snow piles shall not block access to fire hydrants.
8. Snow shall not be piled on sidewalks or block access to sidewalks or at entrances.
9. All driveways must be plowed, (public access from street).
B. ENVIRONMENTAL HEALTH ADMINISTRATION
788 E. Woodoak Lane
MINIMUM REQUIREMENT
Specs
IF NO, INDICATE ALTERNATIVE Y N
1. Days Maintained: Monday Through Sunday.
2. Parking lots ONLY.
b. If snow continues to fall contractor shall return to facilities after 2” additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice.
5. Snow shall not be piled in front of dumpster enclosure located in southwest parking lot.
6. Snow shall be completely removed from North and South I/M bay (overhead) doors.
7. Parking Lot
a. West- Push snow towards the grassy area south side of the lot
b. East- Push snow to the south side of the lot.
8. Snow piles shall not block access to fire hydrants.
9. Snow shall not be piled on sidewalks or block
10. All driveways must be plowed, (public access
C. SOUTH MAIN PUBLIC HEALTH CENTER
3690 South Main Street
Specs
IF NO, INDICATE ALTERNATIVE Y N
1. Days Maintained: Monday through Sunday
2. Parking lots ONLY are maintained. Walkways and sidewalks are responsibility of Health Department.
a. Snow must be cleared by 6:00 a.m. for arriving employees.
b. If snow continues to fall contractor shall return to facilities after 2” additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice.
c. Contractors need to return to facilities by 6:00 am the day following a storm to see if de-icing is needed.
5. Snow shall not be piled in front of storage shed.
6. DO NOT pile snow in the 4 parking stalls east of storage shed marked, “Facilities Vehicles Only.”
7. Most or all of the snow should be pushed to the south side of the parking lot. Snow piles shall not interfere with parking or snow removal at Harmony Park.
8. Contractors shall not push or pile snow in disabled parking stalls. (Doing so prevents disabled persons from parking in designated stalls.)
9. Snow shall not be piled on sidewalks or block
10. All driveways must be plowed, (public access
D. Magna- Kennecott Senior Center 9228 W 2700 South
Specs IF NO, INDICATE
ALTERNATIVE Y N
1. Days Maintained: Monday Through Friday.
2. Parking lots ONLY are maintained. Walkways and sidewalks are responsibility of Aging & Adult Services
3. Ice melt shall be used for de-icing on concrete areas and rock salt on asphalt areas.
4. Timing
a. Evening and early morning snow/ice accumulations shall be cleared by 7:00 AM.
b. If snow continues to fall contractor shall return to facilities after 2” additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice.
d. Extra plowing and ice melt treatments shall be required and completed on an as needed basis due to lake effect snow fall, high winds, and drifting snow.
e. It shall be the responsibility of the winning bidder(s) to monitor the facility through the snowstorm to assure that the facility is plowed and de-iced as required.
f. Contractors need to return to facilities by 7:00 am the day following a storm to see if de-icing is needed.
5. Parking Lots
a. South Parking- Push snow to the south side of the lot.
b. North Parking- Push snow to the West side of the lot. Do not push snow over the north edges into the drainage areas.
c. East Entrance- Push snow to the North or South side of lot, ensuring that the melt off does not freeze on the driveway.
d. The gated areas on the Northwest corner of the building must be kept clear for trash removal and van access.
6. No snow shall be piled in front of dumpster.
7. Snow shall not be piled in front of storage shed.
8. Snow shall not be piled on sidewalks or block access to sidewalks or at entrances.
9. Winning bidder shall not push snow in disabled parking stalls.
E. South Redwood Public Health Center 7971 South 1825 West
MINIMUM REQUIREMENT Meets
Specs IF NO, INDICATE
ALTERNATIVE Y N
1. Days Maintained: Monday through Sunday sidewalks are responsibility of Health Department.
3. Ice melt shall be used for de-icing on concrete areas and rock salt on asphalt areas.
employees
b. If snow continues to fall contractor shall return to facilities after 2” additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice.
5. Snow shall not be piled in front of storage shed.
7. Most or all of the snow should be pushed to the south side of the parking lot. Show piles shall not interfere with parking or snow removal at Harmony Park.
parking stalls. (Doing so prevents disabled persons from parking in designated stalls.)
9. Contractors need to return to facilities by 6:00 am the day following a storm to see if de-icing is needed.
10. Snow shall not be piled on sidewalks or block access to sidewalks or at entrances.
11. All driveways must be plowed, (public access from street).
F. Household Hazardous Waste 8805 South 700 West
MINIMUM REQUIREMENT
Meets Specs IF NO, INDICATE
ALTERNATIVE Y N
1. Days Maintained: Monday through Sunday sidewalks are responsibility of the Health Department.
3. Ice melt shall be used for de-icing on concrete areas and rock salt on asphalt areas.
employees facilities after 1” additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice.
c. Contractors need to return to facilities by 6:00 am the day following a storm to see if de-icing is needed.
5. Snow SHALL NOT be piled in front of storage shed.
7 Parking Lot
a. South Parking- Push snow to South side of lot.
b. West Parking- Push snow to West side of lot.
parking stalls.
9. Snow piles shall not block access to fire hydrants.
10. Contractors need to return to facilities by 6:00 am the day following a storm to see if deicing is needed.
11. Snow shall not be piled on sidewalks or block access to sidewalks or at entrances.
12. All driveways must be plowed, (public access from street).
G. Salt Lake County District Attorney Building 35 E 500 South Salt Lake City
Meet Specs IF NO, INDICATE
ALTERNATIVE Y N
1. Days Maintained: Monday through Sunday.
2. All parking lots and sidewalks must be cleared (parking garage to be completed by request only).
3. Ice melt shall be used for de-icing on concrete areas.
a. Evening and early morning snow/ice accumulations shall be cleared by 6:00 AM.
facilities after 2” additional accumulation of snow until the storm has passed and lots are cleared completely of snow/ice.
c. Contractor needs to return to facilities by 6:00 am the day following a storm to see if de-icing is needed.
5. Parking Garage:
a. To be completed by request only
b. Top deck of parking garage snow must be piled in specified areas.
c. Work in parking garage to be completed with poly blade.
6. Snow piles shall not block any walkways access points, garage doors or garbage cans.
H. Salt Lake County West Jordan Building 8090 S 1825 W West Jordan Utah
MINIMUM REQUIREMENT
Meets Specs IF NO, INDICATE
ALTERNATIVE Y N
1. Days Maintained: Monday through Sunday.
2. All parking lots and sidewalks must be cleared.
3. Ice melt shall be used for de-icing on concrete areas.
4. Timing facilities after 2” additional accumulation of snow until the storm has passed and lots are cleared completely of snow/ice.
c. Contractor needs to return to facilities by 6:00 am the day following a storm to see if de-icing is needed.
5. Snow piles shall not block any walkways, access points or garbage cans.
MAIN SPECIFICATIONS
| Y1 Crews must respond to snowstorms with accumulation of 2 during the nighttime hours or be called out Services to begin within one hour of being notified: |
| N1 Crews must respond to snowstorms with accumulation of 2 during the nighttime hours or be called out Services to begin within one hour of being notified: |
| If No Indicate Alternative1 Crews must respond to snowstorms with accumulation of 2 during the nighttime hours or be called out Services to begin within one hour of being notified: |
| 2 All snow plowing vehicles are to be equipped with plows and Ice Melt: |
| If No Indicate Alternative2 All snow plowing vehicles are to be equipped with plows and Ice Melt spreaders: |
| Y3 Deicing a For deicing Contractor will use icesnow melt on concrete areas Not Salt Ice melt must be 80 or greater of Calcium Chloride: |
| N3 Deicing a For deicing Contractor will use icesnow melt on concrete areas Not Salt Ice melt must be 80 or greater of Calcium Chloride: |
| If No Indicate Alternative3 Deicing a For deicing Contractor will use icesnow melt on concrete areas Not Salt Ice melt must be 80 or greater of Calcium Chloride: |
| undefined: |
| If No Indicate Alternativeb Sodium Chloride may be used on asphalt surfaces only: |
| Yc Icesnow melt must be approved by the Facilities Services Aging Adult Services and division of Salt Lake County Health Department and DAs offices: |
| Nc Icesnow melt must be approved by the Facilities Services Aging Adult Services and division of Salt Lake County Health Department and DAs offices: |
| If No Indicate Alternativec Icesnow melt must be approved by the Facilities Services Aging Adult Services and division of Salt Lake County Health Department and DAs offices: |
| 4 Contractor must be able to respond day and night seven days per week: |
| If No Indicate Alternative4 Contractor must be able to respond day and night seven days per week including holidays within one hour of call or snow Depth is 2: |
| Y5 Unless specifically indicated in these specifications snow plowing shall mean pushing the snow and properly placing it to allow for easy access parking for the disabled vehicles andor pedestrians and minimize loss of parking spaces: |
| N5 Unless specifically indicated in these specifications snow plowing shall mean pushing the snow and properly placing it to allow for easy access parking for the disabled vehicles andor pedestrians and minimize loss of parking spaces: |
| If No Indicate Alternative5 Unless specifically indicated in these specifications snow plowing shall mean pushing the snow and properly placing it to allow for easy access parking for the disabled vehicles andor pedestrians and minimize loss of parking spaces: |
| Y6 No subcontracting of snow plowing or deicing services will be allowed Contractor will utilize their own company equipment and vehicles that are capable of plowing and spreading ice melt in a manner that effectively and efficiently provides for the safety of the occupants of the Salt Lake Countys property: |
| N6 No subcontracting of snow plowing or deicing services will be allowed Contractor will utilize their own company equipment and vehicles that are capable of plowing and spreading ice melt in a manner that effectively and efficiently provides for the safety of the occupants of the Salt Lake Countys property: |
| If No Indicate Alternative6 No subcontracting of snow plowing or deicing services will be allowed Contractor will utilize their own company equipment and vehicles that are capable of plowing and spreading ice melt in a manner that effectively and efficiently provides for the safety of the occupants of the Salt Lake Countys property: |
| 7 Snow piles must not block access to fire hydrants trash dumpsters or: |
| If No Indicate Alternative7 Snow piles must not block access to fire hydrants trash dumpsters or other emergency and public service equipment: |
| access to and usability of sidewalks entrances stairs or driving areas: |
| If No Indicate Alternative8 Snow piles must not block or interfere with access to and usability of sidewalks entrances stairs or driving areas: |
| undefined_2: |
| If No Indicate Alternative9 All driveways must be plowed public access from Street: |
| Y10 With each callout the contractor assumes the responsibility for completing all contracted areas in a manner that will leave the area safe for all facility occupancy It is the contractors responsibility to check all contracted areas to determine safety of all locations prior to exiting the property: |
| N10 With each callout the contractor assumes the responsibility for completing all contracted areas in a manner that will leave the area safe for all facility occupancy It is the contractors responsibility to check all contracted areas to determine safety of all locations prior to exiting the property: |
| If No Indicate Alternative10 With each callout the contractor assumes the responsibility for completing all contracted areas in a manner that will leave the area safe for all facility occupancy It is the contractors responsibility to check all contracted areas to determine safety of all locations prior to exiting the property: |
| Y11 During hours of building occupancy contractor will have signed notification or invoices for completed work by a Salt Lake County employee located at each location: |
| N11 During hours of building occupancy contractor will have signed notification or invoices for completed work by a Salt Lake County employee located at each location: |
| If No Indicate Alternative11 During hours of building occupancy contractor will have signed notification or invoices for completed work by a Salt Lake County employee located at each location: |
| Y12 Notification of services provided will be sent by email with read notification to the building representative within twelve 12 hours of completion of services showing what billable services was done and time service was performed: |
| N12 Notification of services provided will be sent by email with read notification to the building representative within twelve 12 hours of completion of services showing what billable services was done and time service was performed: |
| If No Indicate Alternative12 Notification of services provided will be sent by email with read notification to the building representative within twelve 12 hours of completion of services showing what billable services was done and time service was performed: |
| undefined_3: |
| If No Indicate Alternative13 All vehicles used on Salt Lake County property shall be properly registered including inspection and emissions: |
| Y1 Days Maintained Monday through Sunday: |
| N1 Days Maintained Monday through Sunday: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday through Sunday: |
| Y2 Parking lots ONLY: |
| N2 Parking lots ONLY: |
| IF NO INDICATE ALTERNATIVE2 Parking lots ONLY: |
| 3 Ice melt shall be used for deicing on concrete: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas and rock salt on asphalt areas: |
| accumulations shall be cleared by 600 AM: |
| IF NO INDICATE ALTERNATIVE4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM: |
| 600 am the day following a storm to see if de: |
| IF NO INDICATE ALTERNATIVEb Contractors need to return to facilities by 600 am the day following a storm to see if de icing is needed: |
| Yc If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and parking lots are cleared completely of snow and ice: |
| Nc If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and parking lots are cleared completely of snow and ice: |
| IF NO INDICATE ALTERNATIVEc If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and parking lots are cleared completely of snow and ice: |
| Yd Extra plowing and ice melt treatments shall be required and completed on an additional 2 accumulation of snow due to lake effect snow fall high winds and drifting snow: |
| Nd Extra plowing and ice melt treatments shall be required and completed on an additional 2 accumulation of snow due to lake effect snow fall high winds and drifting snow: |
| IF NO INDICATE ALTERNATIVEd Extra plowing and ice melt treatments shall be required and completed on an additional 2 accumulation of snow due to lake effect snow fall high winds and drifting snow: |
| Ye It shall be the responsibility of the winning bidders to monitor the facility through the storm to assure that the facility is plowed and deiced as needed: |
| Ne It shall be the responsibility of the winning bidders to monitor the facility through the storm to assure that the facility is plowed and deiced as needed: |
| IF NO INDICATE ALTERNATIVEe It shall be the responsibility of the winning bidders to monitor the facility through the storm to assure that the facility is plowed and deiced as needed: |
| a EastPush snow to the south side of the: |
| IF NO INDICATE ALTERNATIVE5 Parking Lots a EastPush snow to the south side of the lot: |
| Yb WestPush snow to the north side of the lot: |
| Nb WestPush snow to the north side of the lot: |
| IF NO INDICATE ALTERNATIVEb WestPush snow to the north side of the lot: |
| Y6 No snow shall be piled in front of dumpster: |
| N6 No snow shall be piled in front of dumpster: |
| IF NO INDICATE ALTERNATIVE6 No snow shall be piled in front of dumpster: |
| Y7 Snow piles shall not block access to fire hydrants: |
| N7 Snow piles shall not block access to fire hydrants: |
| IF NO INDICATE ALTERNATIVE7 Snow piles shall not block access to fire hydrants: |
| 8 Snow shall not be piled on sidewalks or block: |
| IF NO INDICATE ALTERNATIVE8 Snow shall not be piled on sidewalks or block access to sidewalks or at entrances: |
| 9 All driveways must be plowed public access: |
| IF NO INDICATE ALTERNATIVE9 All driveways must be plowed public access from street: |
| Y1 Days Maintained Monday Through Sunday: |
| N1 Days Maintained Monday Through Sunday: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday Through Sunday: |
| Y2 Parking lots ONLY_2: |
| N2 Parking lots ONLY_2: |
| IF NO INDICATE ALTERNATIVE2 Parking lots ONLY_2: |
| 3 Ice melt shall be used for deicing on concrete_2: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas and rock salt on asphalt areas_2: |
| Y4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM: |
| N4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM: |
| IF NO INDICATE ALTERNATIVE4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM_2: |
| Yb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice: |
| Nb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice: |
| IF NO INDICATE ALTERNATIVEb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice: |
| 5 Snow shall not be piled in front of dumpster: |
| IF NO INDICATE ALTERNATIVE5 Snow shall not be piled in front of dumpster enclosure located in southwest parking lot: |
| 6 Snow shall be completely removed from North and: |
| IF NO INDICATE ALTERNATIVE6 Snow shall be completely removed from North and South IM bay overhead doors: |
| Y7 Parking Lot a WestPush snow towards the grassy area south side of the lot: |
| N7 Parking Lot a WestPush snow towards the grassy area south side of the lot: |
| IF NO INDICATE ALTERNATIVE7 Parking Lot a WestPush snow towards the grassy area south side of the lot: |
| Yb EastPush snow to the south side of the lot: |
| Nb EastPush snow to the south side of the lot: |
| IF NO INDICATE ALTERNATIVEb EastPush snow to the south side of the lot: |
| Y8 Snow piles shall not block access to fire hydrants: |
| N8 Snow piles shall not block access to fire hydrants: |
| IF NO INDICATE ALTERNATIVE8 Snow piles shall not block access to fire hydrants: |
| 9 Snow shall not be piled on sidewalks or block: |
| IF NO INDICATE ALTERNATIVE9 Snow shall not be piled on sidewalks or block access to sidewalks or at entrances: |
| 10 All driveways must be plowed public access: |
| IF NO INDICATE ALTERNATIVE10 All driveways must be plowed public access from street: |
| Y: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday through Sunday_2: |
| 2 Parking lots ONLY are maintained Walkways and: |
| IF NO INDICATE ALTERNATIVE2 Parking lots ONLY are maintained Walkways and sidewalks are responsibility of Health Department: |
| 3 Ice melt shall be used for deicing on concrete_3: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas and rock salt on asphalt areas_3: |
| Y4 Timing a Snow must be cleared by 600 am for arriving employees: |
| N4 Timing a Snow must be cleared by 600 am for arriving employees: |
| IF NO INDICATE ALTERNATIVE4 Timing a Snow must be cleared by 600 am for arriving employees: |
| Yb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice: |
| Nb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice: |
| IF NO INDICATE ALTERNATIVEb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice: |
| am the day following a storm to see if deicing is: |
| IF NO INDICATE ALTERNATIVEc Contractors need to return to facilities by 600 am the day following a storm to see if deicing is needed: |
| Y5 Snow shall not be piled in front of storage shed: |
| N5 Snow shall not be piled in front of storage shed: |
| IF NO INDICATE ALTERNATIVE5 Snow shall not be piled in front of storage shed: |
| 6 DO NOT pile snow in the 4 parking stalls east of: |
| IF NO INDICATE ALTERNATIVE6 DO NOT pile snow in the 4 parking stalls east of storage shed marked Facilities Vehicles Only: |
| Y7 Most or all of the snow should be pushed to the south side of the parking lot Snow piles shall not interfere with parking or snow removal at Harmony Park: |
| N7 Most or all of the snow should be pushed to the south side of the parking lot Snow piles shall not interfere with parking or snow removal at Harmony Park: |
| IF NO INDICATE ALTERNATIVE7 Most or all of the snow should be pushed to the south side of the parking lot Snow piles shall not interfere with parking or snow removal at Harmony Park: |
| Y8 Contractors shall not push or pile snow in disabled parking stalls Doing so prevents disabled persons from parking in designated stalls: |
| N8 Contractors shall not push or pile snow in disabled parking stalls Doing so prevents disabled persons from parking in designated stalls: |
| IF NO INDICATE ALTERNATIVE8 Contractors shall not push or pile snow in disabled parking stalls Doing so prevents disabled persons from parking in designated stalls: |
| 9 Snow shall not be piled on sidewalks or block_2: |
| IF NO INDICATE ALTERNATIVE9 Snow shall not be piled on sidewalks or block access to sidewalks or at entrances_2: |
| 10 All driveways must be plowed public access_2: |
| IF NO INDICATE ALTERNATIVE10 All driveways must be plowed public access from street_2: |
| Y1 Days Maintained Monday Through Friday: |
| N1 Days Maintained Monday Through Friday: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday Through Friday: |
| sidewalks are responsibility of Aging Adult Services: |
| IF NO INDICATE ALTERNATIVE2 Parking lots ONLY are maintained Walkways and sidewalks are responsibility of Aging Adult Services: |
| 3 Ice melt shall be used for deicing on concrete areas: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas and rock salt on asphalt areas_4: |
| Y4 Timing a Evening and early morning snowice accumulations shall be cleared by 700 AM: |
| N4 Timing a Evening and early morning snowice accumulations shall be cleared by 700 AM: |
| IF NO INDICATE ALTERNATIVE4 Timing a Evening and early morning snowice accumulations shall be cleared by 700 AM: |
| Yb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice_2: |
| Nb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice_2: |
| IF NO INDICATE ALTERNATIVEb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice_2: |
| Yd Extra plowing and ice melt treatments shall be required and completed on an as needed basis due to lake effect snow fall high winds and drifting snow: |
| Nd Extra plowing and ice melt treatments shall be required and completed on an as needed basis due to lake effect snow fall high winds and drifting snow: |
| IF NO INDICATE ALTERNATIVEd Extra plowing and ice melt treatments shall be required and completed on an as needed basis due to lake effect snow fall high winds and drifting snow: |
| Ye It shall be the responsibility of the winning bidders to monitor the facility through the snowstorm to assure that the facility is plowed and deiced as required: |
| Ne It shall be the responsibility of the winning bidders to monitor the facility through the snowstorm to assure that the facility is plowed and deiced as required: |
| IF NO INDICATE ALTERNATIVEe It shall be the responsibility of the winning bidders to monitor the facility through the snowstorm to assure that the facility is plowed and deiced as required: |
| the day following a storm to see if deicing is needed: |
| IF NO INDICATE ALTERNATIVEf Contractors need to return to facilities by 700 am the day following a storm to see if deicing is needed: |
| a South ParkingPush snow to the south side of the: |
| IF NO INDICATE ALTERNATIVE5 Parking Lots a South ParkingPush snow to the south side of the lot: |
| Yb North ParkingPush snow to the West side of the lot Do not push snow over the north edges into the drainage areas: |
| Nb North ParkingPush snow to the West side of the lot Do not push snow over the north edges into the drainage areas: |
| IF NO INDICATE ALTERNATIVEb North ParkingPush snow to the West side of the lot Do not push snow over the north edges into the drainage areas: |
| Yc East EntrancePush snow to the North or South side of lot ensuring that the melt off does not freeze on the driveway: |
| Nc East EntrancePush snow to the North or South side of lot ensuring that the melt off does not freeze on the driveway: |
| IF NO INDICATE ALTERNATIVEc East EntrancePush snow to the North or South side of lot ensuring that the melt off does not freeze on the driveway: |
| Yd The gated areas on the Northwest corner of the building must be kept clear for trash removal and van access: |
| Nd The gated areas on the Northwest corner of the building must be kept clear for trash removal and van access: |
| IF NO INDICATE ALTERNATIVEd The gated areas on the Northwest corner of the building must be kept clear for trash removal and van access: |
| undefined_4: |
| IF NO INDICATE ALTERNATIVE6 No snow shall be piled in front of dumpster_2: |
| 7 Snow shall not be piled in front of storage shed: |
| IF NO INDICATE ALTERNATIVE7 Snow shall not be piled in front of storage shed: |
| 8 Snow shall not be piled on sidewalks or block access: |
| IF NO INDICATE ALTERNATIVE8 Snow shall not be piled on sidewalks or block access to sidewalks or at entrances_2: |
| 9 Winning bidder shall not push snow in disabled parking: |
| IF NO INDICATE ALTERNATIVE9 Winning bidder shall not push snow in disabled parking stalls: |
| Y1 Days Maintained Monday through Sunday_2: |
| N1 Days Maintained Monday through Sunday_2: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday through Sunday_3: |
| 2 Parking lots ONLY are maintained Walkways and_2: |
| IF NO INDICATE ALTERNATIVE2 Parking lots ONLY are maintained Walkways and sidewalks are responsibility of Health Department_2: |
| 3 Ice melt shall be used for deicing on concrete areas_2: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas and rock salt on asphalt areas_5: |
| Y4 Timing a Snow must be cleared by 600 am for arriving employees_2: |
| N4 Timing a Snow must be cleared by 600 am for arriving employees_2: |
| IF NO INDICATE ALTERNATIVE4 Timing a Snow must be cleared by 600 am for arriving employees_2: |
| Yb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice_2: |
| Nb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice_2: |
| IF NO INDICATE ALTERNATIVEb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snow and ice_2: |
| 5 Snow shall not be piled in front of storage shed: |
| IF NO INDICATE ALTERNATIVE5 Snow shall not be piled in front of storage shed_2: |
| 6 DO NOT pile snow in the 4 parking stalls east of_2: |
| IF NO INDICATE ALTERNATIVE6 DO NOT pile snow in the 4 parking stalls east of storage shed marked Facilities Vehicles Only_2: |
| Y7 Most or all of the snow should be pushed to the south side of the parking lot Show piles shall not interfere with parking or snow removal at Harmony Park: |
| N7 Most or all of the snow should be pushed to the south side of the parking lot Show piles shall not interfere with parking or snow removal at Harmony Park: |
| IF NO INDICATE ALTERNATIVE7 Most or all of the snow should be pushed to the south side of the parking lot Show piles shall not interfere with parking or snow removal at Harmony Park: |
| Y8 Contractors shall not push or pile snow in disabled parking stalls Doing so prevents disabled persons from parking in designated stalls_2: |
| N8 Contractors shall not push or pile snow in disabled parking stalls Doing so prevents disabled persons from parking in designated stalls_2: |
| IF NO INDICATE ALTERNATIVE8 Contractors shall not push or pile snow in disabled parking stalls Doing so prevents disabled persons from parking in designated stalls_2: |
| 9 Contractors need to return to facilities by 600 am the: |
| IF NO INDICATE ALTERNATIVE9 Contractors need to return to facilities by 600 am the day following a storm to see if deicing is needed: |
| 10 Snow shall not be piled on sidewalks or block access: |
| IF NO INDICATE ALTERNATIVE10 Snow shall not be piled on sidewalks or block access to sidewalks or at entrances: |
| 11 All driveways must be plowed public access from: |
| IF NO INDICATE ALTERNATIVE11 All driveways must be plowed public access from street: |
| Y_2: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday through Sunday_4: |
| sidewalks are responsibility of the Health Department: |
| IF NO INDICATE ALTERNATIVE2 Parking lots ONLY are maintained Walkways and sidewalks are responsibility of the Health Department: |
| 3 Ice melt shall be used for deicing on concrete areas_3: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas and rock salt on asphalt areas_6: |
| Y4 Timing a Snow must be cleared by 600 am for arriving employees_3: |
| N4 Timing a Snow must be cleared by 600 am for arriving employees_3: |
| IF NO INDICATE ALTERNATIVE4 Timing a Snow must be cleared by 600 am for arriving employees_3: |
| Yb If snow continues to fall contractor shall return to facilities after 1 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice: |
| Nb If snow continues to fall contractor shall return to facilities after 1 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice: |
| IF NO INDICATE ALTERNATIVEb If snow continues to fall contractor shall return to facilities after 1 additional accumulation of snow until the snowstorm has passed and lots are cleared completely of snow and ice: |
| the day following a storm to see if deicing is needed_2: |
| IF NO INDICATE ALTERNATIVEc Contractors need to return to facilities by 600 am the day following a storm to see if deicing is needed_2: |
| 5 Snow SHALL NOT be piled in front of storage shed: |
| IF NO INDICATE ALTERNATIVE5 Snow SHALL NOT be piled in front of storage shed: |
| 6 DO NOT pile snow in the 4 parking stalls east of_3: |
| IF NO INDICATE ALTERNATIVE6 DO NOT pile snow in the 4 parking stalls east of storage shed marked Facilities Vehicles Only_3: |
| a South ParkingPush snow to South side of lot: |
| IF NO INDICATE ALTERNATIVE7 Parking Lot a South ParkingPush snow to South side of lot: |
| Yb West ParkingPush snow to West side of lot: |
| Nb West ParkingPush snow to West side of lot: |
| IF NO INDICATE ALTERNATIVEb West ParkingPush snow to West side of lot: |
| 8 Contractors shall not push or pile snow in disabled: |
| IF NO INDICATE ALTERNATIVE8 Contractors shall not push or pile snow in disabled parking stalls: |
| 9 Snow piles shall not block access to fire hydrants: |
| IF NO INDICATE ALTERNATIVE9 Snow piles shall not block access to fire hydrants: |
| 10 Contractors need to return to facilities by 600 am the: |
| IF NO INDICATE ALTERNATIVE10 Contractors need to return to facilities by 600 am the day following a storm to see if deicing is needed: |
| 11 Snow shall not be piled on sidewalks or block access: |
| IF NO INDICATE ALTERNATIVE11 Snow shall not be piled on sidewalks or block access to sidewalks or at entrances: |
| 12 All driveways must be plowed public access from: |
| IF NO INDICATE ALTERNATIVE12 All driveways must be plowed public access from street: |
| Y1 Days Maintained Monday through Sunday_3: |
| N1 Days Maintained Monday through Sunday_3: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday through Sunday_5: |
| 2 All parking lots and sidewalks must be cleared parking: |
| IF NO INDICATE ALTERNATIVE2 All parking lots and sidewalks must be cleared parking garage to be completed by request only: |
| 3 Ice melt shall be used for deicing on concrete areas_4: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas: |
| Y4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM_2: |
| N4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM_2: |
| IF NO INDICATE ALTERNATIVE4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM_3: |
| Yb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snowice: |
| Nb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snowice: |
| IF NO INDICATE ALTERNATIVEb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snowice: |
| the day following a storm to see if deicing is needed_3: |
| IF NO INDICATE ALTERNATIVEc Contractor needs to return to facilities by 600 am the day following a storm to see if deicing is needed: |
| undefined_5: |
| IF NO INDICATE ALTERNATIVE5 Parking Garage a To be completed by request only: |
| b Top deck of parking garage snow must be piled in: |
| IF NO INDICATE ALTERNATIVEb Top deck of parking garage snow must be piled in specified areas: |
| c Work in parking garage to be completed with poly: |
| IF NO INDICATE ALTERNATIVEc Work in parking garage to be completed with poly blade: |
| 6 Snow piles shall not block any walkways access: |
| IF NO INDICATE ALTERNATIVE6 Snow piles shall not block any walkways access points garage doors or garbage cans: |
| Y_3: |
| IF NO INDICATE ALTERNATIVE1 Days Maintained Monday through Sunday_6: |
| 2 All parking lots and sidewalks must be cleared: |
| IF NO INDICATE ALTERNATIVE2 All parking lots and sidewalks must be cleared: |
| 3 Ice melt shall be used for deicing on concrete areas_5: |
| IF NO INDICATE ALTERNATIVE3 Ice melt shall be used for deicing on concrete areas_2: |
| Y4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM_3: |
| N4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM_3: |
| IF NO INDICATE ALTERNATIVE4 Timing a Evening and early morning snowice accumulations shall be cleared by 600 AM_4: |
| Yb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snowice_2: |
| Nb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snowice_2: |
| IF NO INDICATE ALTERNATIVEb If snow continues to fall contractor shall return to facilities after 2 additional accumulation of snow until the storm has passed and lots are cleared completely of snowice_2: |
| Yc Contractor needs to return to facilities by 600 am the day following a storm to see if deicing is needed: |
| Nc Contractor needs to return to facilities by 600 am the day following a storm to see if deicing is needed: |
| IF NO INDICATE ALTERNATIVEc Contractor needs to return to facilities by 600 am the day following a storm to see if deicing is needed_2: |
| 5 Snow piles shall not block any walkways access: |
| IF NO INDICATE ALTERNATIVE5 Snow piles shall not block any walkways access points or garbage cans: |