About this file

This is a Capital Outlay Budget Request document submitted by the City of Palm Bay, Florida Parks and Facilities Department for the construction and installation of a chemical storage shed at the Aquatic Center. The project involves the procurement and installation of a pre-fabricated storage shed under 120 square feet, with the addition of a forced ventilation system and electrical/lighting infrastructure. The chemical shed will be located at the Aquatic Center, 120 Malabar Road, Palm Bay, Florida 32907. The requestor, Josh Hudak (321-288-5884), identified this as a new capital asset request with no specified construction timeline, response dates, or bidder meetings noted in the document.

The total funding request for FY27 is $11,475.00, with all costs concentrated in the fiscal year 2027 and no anticipated expenses in subsequent years. Funding is requested from the General Fund with no additional sources identified. The justification for this capital improvement centers on OSHA compliance and safety upgrades, as chemicals are currently stored in an unsecured, open-air environment within the pump room. While OSHA inspection confirmed that current storage meets safety standards, the Facilities Department seeks to implement enhanced storage protocols. This project is categorized as an unfunded request requiring departmental approval and represents an operating asset intended to improve asset and safety health at the aquatic facility.

View the file

Other files

File Type Posted
2-01 Aquatic Center Usage Data - Revenue.pdf PDF
17-05 Original Design and Alterations - Site Plan 1001 July 2002.pdf PDF
15-05 Original Design and Alterations - Geotechnical August 2019.pdf PDF
11-04 Licences and Insurance - Swimming Pool License Fee.pdf PDF
20-06 Related Agreement - 2002-02 Pool Agreement.pdf PDF
16-05 Original Design and Alterations - Plans as-built July 2002.pdf PDF
14-05 Original Design and Alterations - Water Slide as-built March 2003.pdf PDF
13-04 Licences and Insurance - Dept of Health Requirements.pdf PDF
6-03 Current Unfunded Budget Requests - FY31 CIP Project Request Add New Pavillon.pdf PDF
10-04 Licences and Insurance - COI for FL Dept of Ag 9-29-25 Slide.pdf PDF
12-04 Licences and Insurance - AFO CERT Katherine Steward.pdf PDF
22-08 Fee Schedule.pdf PDF
1-PBAC RFS scope.pdf PDF
5-02 Condition Assessment 2026-01-29 opt r.pdf PDF
8-03 Current Unfunded Budget Requests - FY27 Operating Request Interior Repaint-Repairs.pdf PDF
19-06 Related Agreement - 2016-01 Pool Agreement Amendment.pdf PDF
4-01 Aquatics Center Usage Data - Raw Data.pdf PDF
21-07 Operating Expense - Operating Expense Report 9-22-2026.pdf PDF
3-01 Aquatics Center Usage Data.pdf PDF
9-03 Current Unfunded Budget Requests - FY27 Operating Request Pool Repairs.pdf PDF
18-06 Related Agreement - Brevard Schools Interlocal Agreement.pdf PDF
Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Master Capital Improvement Plan/CIP Capital Outlay Summary

Information Asset Description Department Facility/Park Name Division Address Budget Goal Departmental Contact Key Performance Indicator FY27 Total Funding Request FY27 Budget Priority Code Asset Costs 2027 2028 2029 2030 2031 TOTAL Asset Type Capital 11,475.00 11,475.00 Asset Category Operating - Age of Asset Total Costs 11,475.00 - - - - 11,475.00

Account New Requests for FY27 Department Approval (Y/N) 001-4526-572-6501 11,475.00 Requested Unfunded Unfunded Unfunded Unfunded

Funding Source Details 2027 2028 2029 2030 2031 TOTAL General Fund 11,475.00 11,475.00 Utilities Funds* - Building Fund* - Stormwater Fund* - Impact Fees - Grants/Awards - Total Fund Source 11,475.00 - - - - 11,475.00

* Enterprise Funds

Total 11,475.00

Accounting Breakdown Section Budget Planning Section

Asset Justification

Currently chemicals are stored in the pump room in an open air environment which is not to our Facilities departments standards. OSHA has inspected and says the chemicals are safely and appropriately stored as is. Facilities would like to have a chemical storage unit placed at the aquatic center for safer storage.

This estimate is for pre-made storage shed under 120 sq ft.. A forced ventilation system and electrical/lighting will need to be added. (lal)

$11,475 Expenditure Planning Section

New Other

NA

Parks Maintenance 420 Community College Parkway SE Infrastructure Maintenance & Improvement Josh Hudak 321-288-5884

Asset & Safety Health

Details Aquatic Center Chemical Shed Asset Location & Contact

Parks & Facilities Aquatic Center

120 Malabar Road, Palm Bay, Florida 32907

Master Capital Improvement Plan/CIP Capital Outlay Summary

Summary Impact on Operating Budget

→ Operational Costs Personnel Operating Other Total Operational Costs

Additional Notes/Comments

Asset Images

Reccuring Annual Costs

Operational Impacts - Identify How This Capital Asset Impacts Operational Needs Within Your Department

120 Malabar Road, Palm Bay, Florida 32907

Aquatic Chemical Shed