This is a Contractors Work specification document for Douglass Township in Montgomery County, Pennsylvania, detailing the requirements for the County Line Bridge Replacement Design Build project. The project encompasses the complete replacement of the existing County Line Bridge, with an anticipated Notice to Proceed date of August 31 and a 180-day completion timeframe. The contractor is responsible for furnishing all labor and materials, with construction operations confined to specified rights-of-way and easement areas. A non-mandatory pre-bid meeting is scheduled for July 22, 2026, at 10:00 A.M. on site, and sealed bids are due by 11:00 A.M. prevailing time on July 29, 2026, through the PennBid platform. Project drawings and documents are available for inspection at the Douglass Township Administration Building and online at PennBid.
Bidders must submit bids unconditionally with bid security of not less than ten percent of the bid amount via certified check or bond from Pennsylvania-licensed companies. The successful bidder will be required to furnish Performance and Labor and Material Bonds equal to 100 percent of the contract amount and a Maintenance Bond of 25 percent of the total contract price, along with a Certificate of Insurance. Bids must comply with Pennsylvania Prevailing Wage requirements included in the bidding documents. No bidder may withdraw a bid within 60 days after the scheduled closing time for receipt of bids. The contractor bears all costs including temporary power, water, telephone, testing services, road opening permits, construction permits, and licenses. The township reserves the right to waive any informality or reject any or all bids as deemed in its best interest.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01010-1
SECTION 01010
CONTRACTORS WORK
PART 1 GENERAL
1.1 RESPONSIBILITY OF CONTRACTOR
A. This project scope is the complete replacement of existing County Line
Bridge as Design Build
B. The anticipated Notice to Proceed date is August 31 with a 180 day completion time frame.
1.2 CONSTRUCTION LIMITS
A. Contractor shall confine their operations strictly within the limits of rights-of-way and easements as indicated by the plans and/or directed by the Engineers, unless written permission is obtained to occupy additional ground. Upon completion of work the Contractor shall cleanup and restore the area of their operations to a condition at least equal to original conditions. Unless specified elsewhere herein, all restoration shall be included in the Contractor's unit and/or lump sum price bid. Damage to property outside of specified construction limits shall be the responsibility of the Contractor and restoration of same shall be made at the
Contractor's expense.
1.3 MEASUREMENT OF WORK AND MATERIALS
A. The Contractor will be paid for the actual quantity of authorized work or material furnished under each item of the contract, at the prices stipulated for each item. If the quantity of any unit price item is decreased the Contractor shall have no claim for damages on the basis of loss of anticipated profits. All quantities of work and materials to be paid will be determined by the Engineers in accordance with working lines specified in the contract documents.
1.4 DELETED
1.5 CONTRACTOR'S RESPONSIBILITIES
A. The Contractor shall be responsible for all costs, including temporary power, water, telephone, testing services, road opening permits in local roads, construction permits, and licenses.
1.6 PROTECTION OF WORK AND PROPERTY
01010-2
A. Contractor shall protect and maintain existing structures, access to existing homes and driveways, equipment and new construction (unless otherwise specified) in an undisturbed condition during the contract period.
B. Contractor shall provide adequate protection for the public, the Township, and their employees during the contract period. Provide protective devices and equipment for protection of people and property. Protective measures shall comply with the Occupational Safety and Health Administration (OSHA) and other codes having jurisdiction.
C. The Contractor shall provide adequate protection against injury or loss arising in connection with this Contract for all their work and the property of the Township.
He shall make good any such damage, injury or loss. He shall adequately protect adjacent property as provided by law and the specifications and drawings. He shall provide facilities for protection required by public authority or local conditions as passageways, guard fences, lights, etc.
1.7 CLEAN-UP
A. Each Contractor shall periodically remove waste so that at no time shall there be undue accumulation in the work area. Upon completion of the work, the
Contractor shall remove from the project and adjacent property, all surplus and discarded materials, equipment and temporary structures and leave the premises broom clean.
B. A final cleaning inspection shall be made by the Engineer. The Contractor shall perform any additional cleaning as required by the Engineer.
1.8 TIME OF THE ESSENCE
A. Time is of the essence in the performance of the Work required by this Contract.
No extensions of time will be granted for rain days, snow days or cold weather.
1.9 COPIES OF DOCUMENTS
A. Furnished Copies: Contractor will be furnished at no cost to them a maximum of three (3) sets of full-size Contract Drawings, (in addition to as-built set) including revised drawings, and a maximum of three (3) copies of the Contract
Specifications in addition to those used in the execution of the Agreement.
B. Additional Copies: Additional copies of the above documents will be supplied with the Contractor paying for printing, handling and delivery cost upon receipt.
1.10 RELATED DOCUMENTS
01010-3
A. The Contractor shall adhere to the rules, regulations and requirements of all state, county and local permits and/or approvals issued for this project. Permitting agencies must be notified by the Contractor prior to construction per the requirements of the permits.
1.11 WORK WITHIN PRIVATE PROPERTY RIGHT-OF-WAY
A. The Contractor's construction operations, equipment, materials and any other such items shall not leave the permanent right-of-ways or easement areas without the written permission of the property Owner and Engineer.
B. The Contractor shall neither damage nor destroy any trees or shrubs not located in the permanent right-of-way. Any trees or shrubs damaged or destroyed that are located outside of the permanent right-of-way shall be replaced in kind by the
Contractor at no additional cost to the Township.
C. Contractor shall restore all disturbed areas as specified herein.
1.12 CONSTRUCTION STAKEOUT
A. The Contractor shall perform all construction stakeout required for the installation of the facilities, using the information provided on the drawings.
B. The Contractor shall provide the Engineer with one (1) copy of the cut sheets.
END OF SECTION