Questions and Answers AZ BL COLO 7582(1) Burro Creek Road 11 10 26.pdf

PDF 98 KB Posted

Attached to
AZ BL COLO 7528(1) Burro Creek Road
Solicitation number
6982AF27B000002
Issued by

About this file

This is a Question and Answer document for federal contract 6982AF27B000002, an Arizona Bureau of Land Management road construction project at Burro Creek Road. The Q&A addresses 47 questions from contractors submitted between October 26 and November 10, 2026, clarifying contract requirements and specifications.

The project involves Schedule A work and an Option X component covering pavement removal, full-depth reclamation, culvert installation, seeding, erosion control, and related roadway improvements. Key clarifications include: the bid schedule quantities govern for bidding (7.2 acres seeding Schedule A, 0.1 acre Option X; 170 boulders; 5.3 miles striping Schedule A, 0.2 miles Option X), with plan quantities differing due to allowances for multiple applications; alternate seed vendors may be submitted to the Contracting Officer for approval, provided they meet requirements; contractors must bid plans as shown for rolled erosion control materials; boulders paid under Option X are deleted if Option X is not awarded; removed asphalt may be reused if it meets contract requirements; and scaled rock may be reused subject to compliance with Sections 107, 108, 156, and 262. The document clarifies staffing requirements including that a Quality Control Manager must have no responsibilities other than managing QC; a single qualified individual may perform both QC inspection and testing; and one person may perform multiple stormwater roles if qualified. Construction water must be sourced independently by the contractor, with no government-furnished supply available. Culvert lengths and locations are approximate and subject to field verification and Contracting Officer approval before pipe ordering. The document references the Standard Contract Requirements (SCR), FP-24 specifications, and various contract sections for detailed requirements.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6982AF27B000002

AZ BL COLO 7528(1) BURRO CREEK ROAD

QUESTION & ANSWER

October 26, 2026

Question Answer

1. Can you confirm if the site is open to the public? One of our subcontractors would like to visit and review the existing conditions.

The site is open to the public.

November 5, 2026

2. Will contractors be able to draft water out of the creek for construction water?

Refer to Sections 105 and 158 regarding construction water sources.

3. Regarding the seeding, the bid schedule, and the plan quantities don't line up...

Bid schedule calls for 7.2 acres for Schedule A, and 0.1 acre for Option X while the plans call for 3.4 acres with a 0.1 acre allowance for Schedule A and 0.1 acre for Option X. Which Quantity is correct?

The Bid schedule quantity is correct. The Plan quantity for Schedule A was doubled to account for two applications if necessary.

Refer to sheets B2 and B7 in the Plans for Seeding quantity information.

4. Do you have a specified rate or specific call out for fertilizer, tackifier or any other amendments?

Refer to Section 625 and 625 items in the bid schedule for turf establishment requirements.

There is no requirement in the contract for fertilizer.

5. The seed vendor that we utilize is not listed on the approved vendors list, but they are approved by ADOT, will we be able submit them and have the Government consider approving them as vendor? OR it is strictly limited to the vendors on the approved list?

Alternate seed sources may be submitted to the CO for approval.

6. In regards to the Rolled Erosion Control, we have a TRM that exceeds the requirements of the 5B that is called out. Will the Government consider approval of this product as an approved equal?

Please bid the Plans as shown.

7. Are there any existing CAD files? Refer to SCR Subsections 102.02A and

152.04 for physical data provided in the contract.

8. Can one person fulfill the role of superintendent, QC manager and site safety health officer? Or must those roles be filled by individual people?

Per Section 153.04 of the FP-24, provide a QCM with no responsibilities for managing or superintending the project or performing operations other than managing the QC.

9. Can the bid due date be extended to Friday 11/20?

No, bids are due on the original date of 11/17.

Received November 9, 2026

10. There is an object marker at Sta 06+33 Lt with no type or size listed. What should we bid there?

(Sheet B8)

Please refer to Amendment 001.

11. The bid schedule has 170 boulders, but the callouts on Sheets C2 and C3 add up to 158.

Which is correct? (Item X0240, Sheets C2-C3)

The bid schedule is correct and includes an allowance.

12. The boulders are paid under Option X but are located in the Schedule A area (Sta 30+00 to 73+55). If Option X is not awarded, are the boulders deleted? (Item X0240)

That is correct. If Option X is not awarded, no boulders will be installed.

13. The boulders are paid under Option X but are located in the Schedule A area (Sta 30+00 to 73+55). If Option X is not awarded, are the boulders deleted? (Item X0240)

That is correct. If Option X is not awarded, no boulders will be installed.

14. Subexcavation is to be backfilled with crushed aggregate over geotextile. Neither has a pay item in Schedule A. Are they paid under subexcavation? (SCR 204.07, Item A0340)

Refer to Subsections 204.16, 204.17, and Section 109 for measurement and payment information.

15. Subexcavation is to be backfilled with crushed aggregate over geotextile. Neither has a pay item in Schedule A. Are they paid under subexcavation? (SCR 204.07, Item A0340)

See response to question 14.

16. Sheet B8 shows about 5.05 miles of striping for Schedule A and 0.04 miles for Option X. The bid schedule shows 5.3 and 0.2 miles. Please confirm. (Sheet B8, Items A1140 and X0740)

The bid schedule is correct and includes an allowance.

17. We can't order pipe until field lengths are approved. How long will that review take, and will pipe lead time be considered in contract time?

(Sheet B5, Note 1)

Please refer to Sections 155 and 108 regarding the Contractor’s schedule and the completion date requirements.

18. Is there an approved water source near the project we can use? (Section 158)

No government-furnished water source is provided. Refer to Sections 105 and 158.

19. Can the removed asphalt be reused on the project (in the FDR or on shoulders), or does it all need to be hauled off? (Items A0300 and A0320)

Removed asphalt may be reused provided it meets all contract requirements.

20. Can scaled rock stay on site, or does it have to be hauled off? Can a machine be used on areas reachable from the road? (Section 262, Item A0440)

Scaled rock may be reused provided it meets all contract requirements. Scaling methods and equipment must comply with all contract requirements, including, but not limited to Sections 107, 108, 156, and 262.

21. Field office allocation Bid items A1180 and X0780 each list one field office. For pricing Option X, may the same compliant field office furnished for Schedule A remain in service for the extended option period, with X0780 covering incremental duration and services, or is a second separate office required?

Reference: bid schedule and SCR Section 637.

A second separate field office is not required. The same compliant field office provided under Schedule A may remain in service for the duration of Option X. Refer to SCR Section 637.

22. Biological services beyond initial surveys Please clarify whether the biological-services lump sums require ongoing construction monitoring beyond the surveys, reporting and protective measures expressly described in SCR 107.10(e). If ongoing monitoring is required, identify the activities requiring attendance and the anticipated coverage. If surveys must be repeated solely because Government-directed phasing or protective buffers delay access, identify the applicable payment provision. Reference: A0980, X0640, SCR 107.10(e) and 623.03.

Refer to Sections 107 and 623 for biological services requirements and qualifications.

23. Cultural training and additional attendance Beyond initial and new-personnel Tribal Cultural Sensitivity Training under SCR 107.10(e)(2), are routine archaeological monitoring or Tribal representative attendance required during planned ground disturbance, including Option X bridge-approach excavation? If so, please identify the required coverage and whether it is included in A1000/X0660 or furnished separately by the Government. Reference: SCR 107.10(e) and 623.03.

Refer to Sections 107 and 623 for archaeological services requirements and qualifications.

Received November 10, 2026

24. Pavement Removal and Reclamation Limits The bid schedule identifies 1.3 miles of full-depth reclamation at a 4-inch depth and 1,965 square yards of asphalt pavement removal. Please clarify whether the removal quantity represents discrete areas outside the reclamation limits or whether the two operations overlap, and identify the controlling plan stations for each treatment.

The two operations do not overlap. Asphalt pavement removal applies to discrete existing pavement sections outside the Full-depth reclamation areas. Full-depth reclamation covers the roadway traveled way as detailed on the Typical Sections. Refer to Sheets A2 through A7, B6 and C1 for additional information.

25. Reclaimed Material Suitability If existing pulverized pavement material fails to meet specified suitability or gradation requirements despite proper processing, please identify the required corrective action and the applicable measurement and payment provisions

Refer to Section 304 for Full-depth reclamation requirements. Changes to the contract will be administered through applicable Contract Specifications and FAR clauses.

for additional processing, disposal, or imported aggregate.

26. Unstable Subgrade and Additional Subexcavation The bid schedule identifies 200 cubic yards of subexcavation. If unsuitable subgrade is discovered beyond the planned limits or quantities, please clarify the Government approval, measurement, and payment procedures for additional excavation, geotextile, replacement aggregate, and restoration of the pavement section.

Refer Sections 204 for subexcavation requirements. Changes to the contract will be administered through applicable Contract Specifications and FAR clauses.

27. Differing Subsurface Conditions Please confirm whether additional subsurface investigation data will be furnished before bid opening and identify the procedures for documenting and obtaining direction on materially differing conditions encountered during roadway and drainage excavation.

Refer to Subsection 102.02A for physical data provided, including all available reports and information. Changes to the contract will be administered through applicable Contract Specifications and FAR clauses.

28. Notice to Proceed and Work Restrictions Please confirm the anticipated notice-to-proceed timeframe and whether seasonal, environmental, weather-related, or other work restrictions apply beyond those already shown in the contract documents.

Refer to the IFB, Item 11 for information regarding the Notice to Proceed timeframe.

29. Traffic Closures During Reclamation and Paving May the contractor implement temporary full roadway closures during reclamation, culvert installation, and asphalt paving? If so, please identify the approval procedure, permissible closure windows, and any required advance public notifications.

Refer to Section 156 for temporary traffic control requirements.

30. Utility Verification and Conflicts Existing utility information includes water and overhead electrical facilities. Please clarify the required pre-excavation verification procedures and the contractual process for resolving unforeseen utility conflicts or Government-directed adjustments.

Refer to Section 107 for utility locating requirements.

31. Culvert Adjustments and Compensation Where field conditions necessitate Government-directed changes to culvert alignment, length, elevation, or associated drainage improvements beyond the plan quantities, please identify the applicable measurement and payment procedures.

Culvert lengths, locations, and skews shown on the plans are approximate and subject to field verification and CO approval before ordering pipe per Plan Sheet B5 and Section 602. Approved changes in culvert lengths and associated drainage structures will be measured and paid at the established contract unit prices under the Section 601 and 602 bid items per Sections 602 and 109.

32. QCM Performing QC Inspection May the designated Quality Control Manager also perform QC inspection duties, provided the individual meets the qualifications for both functions and maintains the required on-site

Per Subsection 153.04, provide a QCM with no responsibilities for managing or superintending the project or performing operations other than managing QC.

presence?

33. QCM Performing QC Testing May the designated Quality Control Manager also perform material sampling and testing when appropriately certified or otherwise qualified, while complying with the prohibition on non-QC management duties?

See the response to Question 32.

34. QC Inspector and QC Tester Combination May one qualified individual perform both QC inspection and material sampling/testing functions when the individual meets the qualifications for each?

A single qualified individual may perform both QC inspection and testing duties provided they meet the qualifications. Refer to Section 153 for qualifications and additional requirements.

35. Alternate QCM Site Presence Is the designated Alternate QCM required to remain continuously assigned to and present at the site, or may the Alternate QCM perform another qualified QC function until needed to assume the QCM duties?

Per Section 153, the Alternate QCM must meet all QCM qualifications when acting as the QCM on the project. Per Subsection 153.04, do not use an alternate QCM for more than 3 consecutive days unless approved.

36. Alternate QCM Dual-Hatting May the designated Alternate QCM serve as QC Inspector and/or QC Tester, provided all applicable qualifications are met and the individual can assume QCM responsibilities when required?

When acting as the QCM, the Alternate QCM must meet all QCM requirements in the Contract.

See responses to Questions 32 and 35 above.

37. Subcontracted QC Testing May QC sampling and materials testing be performed by a qualified subcontracted testing firm or laboratory, provided the work and responsible personnel are identified in the approved Quality Control Plan?

Refer to SCR Subsection 153.03(b). Refer to Sections 153 and 154 for Contractor Quality Control and Sampling and Testing Requirements.

38. Dedicated Project Manager Requirement Does the contract require a separately designated Project Manager, or may project management responsibilities be performed by the Project Superintendent or another qualified management team member?

The contract does not require a separately designated or standalone Project Manager.

39. RFI 016 – Superintendent Qualifications and Presence Please identify any minimum degree, certification, or years-of-highway-construction-experience requirements for the Superintendent, and clarify whether continuous on-site presence is required during all active construction or whether a qualified alternate may cover temporary absences.

The contract does not establish specific degree or certification requirements for the Superintendent.

Refer to Section 101 and FAR Clause 52.236-6 for additional information and requirements.

40. Dedicated SSHO and Combined Safety Duties Does the contract require a separately designated Site Safety and Health Officer (SSHO) or equivalent safety representative? If so, may the Superintendent or another qualified on-site employee perform those duties concurrently?

Per Subsection 156.08, do not designate the superintendent as the Traffic Control Supervisor.

41. EM 385, OSHA and Other Safety Credentials Please confirm whether EM 385-1-1 training/familiarization, OSHA 30-hour, OSHA 40-hour, or other project-specific safety credentials are contractually required for the QCM, Alternate QCM, QC Inspector, QC Tester, Superintendent, Project Manager, or safety representative, beyond expressly stated FP-24 and applicable regulatory requirements.

Refer to Sections 101 and 153 for Superintendent and QC personnel qualifications.

42. Accident Prevention Plan Responsible Individual Does the Accident Prevention Plan requirement under Section 107.08 establish any minimum credentials, training, or separate staffing requirement for the person responsible for implementing and administering the plan?

The Accident Prevention Plan must identify a competent, designated person on site with the authority to enforce safety requirements according to the Contract Specifications and FAR Clause 52.236-13.

43. Stormwater Role Combination Section 157 identifies the SWPPP Developer, Erosion Control Supervisor, and On-Site Stormwater Lead. Please confirm whether a qualified Superintendent or other project staff member may perform the On-Site Stormwater Lead function concurrently with their other duties, provided all training and presence requirements are satisfied.

Per SCR Subsection 157.03, "One person may serve in more than one role if qualified." All qualifications and staffing assignments must be submitted and approved as part of the SWPPP submittal per SCR Subsection 157.03.

44. Alternate Campground Access During Construction SCR 156.06(k) requires public access to the Burro Creek Campground from the east to be maintained at all times, and SCR 156.04 does not allow alternate route detours without approval.

The campground has a second entrance across the bridge that is currently unpaved gravel and in rough condition. Would the Government consider allowing the Contractor to grade and improve the existing gravel entrance, and use it as the public access route to the campground while the paved road is closed for full depth reclamation and paving? This would limit traffic control to a short section near the campground entrance, reduce delays to campers, and improve safety for the traveling public and work crews. If this is acceptable, please advise whether the work would be paid under existing bid items or whether it should be included at the Contractor's expense.

Bids must be submitted in accordance with the IFB. Refer to Section 156 for temporary traffic control requirements.

45. Principal Work Item Quantities The updated SAM.gov project description lists principal work item quantities that differ from the Bid Schedule: Ditch Reconditioning 2,000 LNFT (Bid Schedule A0480: 170 LNFT), 18-Inch Pipe Culvert 100 LNFT (A0680: 55 LNFT), 24-Inch Pipe Culvert 175 LNFT (A0700: 135 LNFT), and

The quantities listed in the official Bid Schedule govern for bidding purposes.

Boulder 100 EACH (X0240: 170 EACH). Please confirm that the Bid Schedule quantities govern for bidding purposes.

46. Field Office in Option X The Bid Schedule includes Field Office (63701- 0000) at 1 EACH in Schedule A (A1180) and 1 EACH in Option X (X0780). If Option X is exercised, is a second field office intended, or does X0780 cover extending the Schedule A field office through the Option X completion date?

See response to Question 21.

47. Construction Water Source The November 5 Q&A did not approve drafting construction water from Burro Creek, and the campground well (about 3 gallons per minute) serves campers only. The nearest known fill point is an ADOT site near Wikieup on US 93. Is the Government aware of any approved construction water source closer to the project, such as an ADOT or BLM fill site? If the Contractor uses the ADOT site near Wikieup, does the Government have any requirements or coordination contacts for drawing water there?

If utilizing the ADOT Wikieup fill site, the Contractor must independently coordinate with ADOT to obtain any required permits, agreements or approvals. Refer to Sections 105, 107 and 158 for additional information regarding construction water sources.

File details come from the government source that posted it. Updated .