AZ BL COLO 7528(1) Bid Opening Summary Sched and Opt.pdf
PDF 99 KB Posted
- Attached to
- AZ BL COLO 7528(1) Burro Creek Road
- Solicitation number
- 6982AF27B000002
About this file
This is a Bid Opening Summary for the Burro Creek Road Project (AZ BL COLO 7528(1)), a Bureau of Land Management construction project. The bid opening occurred on November 17, 2026, at 2:00 p.m. MST in Lakewood, Colorado, with Eric Grosskreuz as the bid opening officer. One amendment was issued on November 12, 2026.
Ten contractors submitted bids, with bid totals ranging from $2,599,870.00 to $5,449,551.34. The low bid was submitted by Jud CO, LLC (Cedar City, UT) at $2,599,870.00, consisting of $2,276,748.00 for Schedule A and $323,122.00 for Option X. Other notable bids include Cutting Edge Contractors, Inc. (Las Vegas, NV) at $2,899,999.34 and Gunner Contracting (Taylor, AZ) at $3,315,965.18. The Engineer's Estimate was $3,074,850.00, comprised of $2,629,850.00 for Schedule A and $445,000.00 for Option X. All bids are subject to verification. The remaining bidders were Aventus NV, Inc., Black River Asphalt, Central Southern Construction, McKenzie Construction and Site Development LLC, TIMS 8A JV, TNT, and Whelcon Contractors.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid Opening Summary
Project Name: Burro Creek Road Project Number: AZ BL COLO 7528(1) Bid Opening Date: 11/17/2026 Time: 2:00 p.m. MST Bid Opening Location: Lakewood, CO Bid Opening Officer: Eric Grosskreuz
Amendments: (1)__11/12/2026__ (2) _____________
Bidder’s Name Schedule A Option X BID TOTAL
1. Aventus NV, Inc.
Boulder City, NV
$5,138,672.52
$310,878.72
$5,449,551.34
2. Black River Asphalt Goodyear, AZ
$3,355,896.93
$542,044.57
$3,897,941.50
3. Central Southern Construction Jacksonville, FL
$3,208,413.00
$739,615.44
$3,948,028.44
4. Cutting Edge Contractors, Inc.
Las Vegas, NV
$2,597,599.66
$302,399.68
$2,899,999.34
5. Gunner Contracting Taylor, AZ
$3,088,372.30
$227,592.88
$3,315,965.18
6. Jud CO, LLC Cedar City, UT
$2,276,748.00
$323,122.00
$2,599,870.00
7. Mckenzie Construction and Site Development, LLC
Washington, DC
$3,925,828.49
$1,020,032.65
$4,945,861.15
*All bids are subject to verification.
Bidder’s Name Schedule A Option X BID TOTAL
8. TIMS 8A JV
Yuma, AZ
$3,251,245.50
$222,888.45
$3,474,133.95
9. TNT
Nephi, UT
$4,186,290.46
$557,885.13
4,744,175.59
10. Whelcon Contractors Tucson, AZ
$3,095,735.95
$530,520.82
$3,626,256.77
Engineer’s Estimate
$2,629,850.00 $445,000.00 $3,074,850.00
*All bids are subject to verification.