This document is a set of Questions and Answers (Q&A) related to the federal contract opportunity for the CA ERFO NP DEVA 2023-3(2) Repairs and Armoring project. The key details are:

The project is located in Death Valley National Park and involves pavement patching, roadway reconditioning, armoring, sign installation and replacement, and new gate installation on multiple routes throughout the park. Significant quantities include removal of pavement, revet mattress, roadway reconditioning, asphalt concrete pavement patch, pipe culvert, sidewalk, and concrete barrier. There is an optional scope for gabions, revet mattress, and additional pavement patching and concrete barrier on Emigrant Canyon Road. A non-mandatory pre-bid virtual meeting will be held on July 18, 2024 to orient contractors. Answers indicate that CMP pipe culverts are not allowed, a note on the plans regarding crack sealing will be removed, and the contractor is responsible for maintaining stability and safety of excavations. The estimated bid range is between $10,000,000 and $20,000,000, with an anticipated award in August 2024 and construction from August 2024 through February 2025.

View the file

Other files for this federal contract opportunity

Other files attached to CA ERFO NP DEVA 2023-3(2) Repairs and Armoring, newest first.
File Type Posted
Bid Tabs CA ERFO NP DEVA 2023-3(2).pdf PDF
Bid Opening Summary CA ERFO NP DEVA 2023-3(2).pdf PDF
QnA 8.09.24_ DEVA.pdf PDF
A005 DEVA 8.9.24.pdf PDF
A004 DEVA 8.5.24.pdf PDF
QnA 8.5.24_ DEVA.pdf PDF
A003 DEVA.pdf PDF
QnA 7.26.24 DEVA.pdf PDF
A002 DEVA.pdf PDF
QnA 7.24.24 DEVA.pdf PDF
QnA 7.18.24 Virtual Pre-Bid.pdf PDF
CA ERFO DEVA_Prebid presentation.pptx PPTX presentation
QnA 7.18.24 DEVA.pdf PDF
A001 DEVA 7.18.24.pdf PDF
Interested Vendors List 7.11.2024.pdf PDF
01.100 - Plans.pdf PDF
22.100 - Pavement Report.pdf PDF
FP-14_Eng.pdf PDF
6982AF24B000010.pdf PDF
CA ERFO NP DEVA2023-3(1)-AS-BUILT DRAWINGS_01_26_24.pdf PDF
21.100 Hydraulics Report.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

CA ERFO NP DEVA 2023 – 3(2) REPAIRS AND ARMORING

July 10, 2024

Questions Answers 1 Is there a job walk for the attached project? NON-MANDATORY PRE-BID VIRTUAL MEETING

A pre-bid virtual meeting will be conducted to solicit contractor interest and to orient contractors with the project prior to the bid opening. A Representative from the Federal Highway Administration (FHWA) will conduct a meeting on Thursday, July 18, 2024, from 2:00 – 3:00p.m. Local Mountain Time. FHWA will provide a brief project presentation and will be available to answer questions. All questions and answers will be posted to SAM.gov.

If you would like to attend the virtual meeting, please email CFLContracts@dot.gov by Wednesday, July 17, 2024, 1:00 p.m., Local Mountain Time to request a link to join the presentation. The virtual meeting will be held using Microsoft Teams.

ATTENDANCE AT THE PRE- BID VIRTUAL MEETING IS NOT REQUIRED TO BID

2 Can we use CMP in lieu of HDPE for the pipe culverts?

No

3 On plan sheet A5, note 4, it talks about cleaning prior to sealing cracks, seal according to 414 subsections. I am not finding anything on this under section 418 nor are there any bid items for this work. Can you please clarify this note and possibly add bid items for this work since there are miles of cracks and will be hard to measure as incidental, it needs to be by the linear foot?

An amendment will be forthcoming to remove this note from the sheet.

4 In some areas where gabion walls are being installed it shows to shore the excavation. Is it possible to put up temporary portable concrete barrier rail pinned to the asphalt to create one lane of traffic with the use of temporary signals in lieu of shoring the vertical excavation? If shoring is required regardless, can you send us a detail of what would be accepted in the Park?

Maintaining stability and safety of the excavation is the responsibility of the contractor. See the Special Contract Requirements (SCR) of the IFB and FP-14, Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects.