About this file

This document is a Pavement & Materials Recommendations memorandum for the CA ERFO NP DEVA 2023-3(2) Repairs and Armoring project in Death Valley National Park. The project scope includes pavement patching, roadway reconditioning, culvert replacement/placement, and roadway armoring on multiple routes throughout the park due to damage from Hurricane Hilary. Based on field investigations, the memorandum provides recommendations for pavement structural sections and materials, including 4-inch asphalt concrete pavement patches, 6-inch aggregate surface course, and 2-inch asphalt sidewalk. The recommended bid items include subexcavation, roadway aggregate, asphalt concrete pavement patches, and asphalt sidewalk. The related federal contract opportunity (Solicitation Number 6982AF24B000010) has an estimated bid range between $10,000,000 and $20,000,000, with construction anticipated from August 2024 through February 2025.

View the file

Other files for this federal contract opportunity

Other files attached to CA ERFO NP DEVA 2023-3(2) Repairs and Armoring, newest first.
File Type Posted
Bid Tabs CA ERFO NP DEVA 2023-3(2).pdf PDF
Bid Opening Summary CA ERFO NP DEVA 2023-3(2).pdf PDF
A005 DEVA 8.9.24.pdf PDF
QnA 8.09.24_ DEVA.pdf PDF
A004 DEVA 8.5.24.pdf PDF
QnA 8.5.24_ DEVA.pdf PDF
A003 DEVA.pdf PDF
QnA 7.26.24 DEVA.pdf PDF
A002 DEVA.pdf PDF
QnA 7.24.24 DEVA.pdf PDF
QnA 7.18.24 Virtual Pre-Bid.pdf PDF
CA ERFO DEVA_Prebid presentation.pptx PPTX presentation
QnA 7.18.24 DEVA.pdf PDF
A001 DEVA 7.18.24.pdf PDF
Interested Vendors List 7.11.2024.pdf PDF
CA ERFO NP DEVA 2023-3(2)_QnA-07_10_2024.pdf PDF
01.100 - Plans.pdf PDF
6982AF24B000010.pdf PDF
CA ERFO NP DEVA2023-3(1)-AS-BUILT DRAWINGS_01_26_24.pdf PDF
FP-14_Eng.pdf PDF
21.100 Hydraulics Report.pdf PDF
Show all 21

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Subject: Pavement & Materials Recommendations (P1) CA ERFO NP DEVA 2023-3(2) Repairs and Armoring

From: Darin Lockhart Pavement & Materials Engineer, CFLHD

Through: Mike Voth Pavement & Materials Team Lead, CFLHD

To: Toni Pankau, Project Manager, CFLHD Greg Relyea, Design Engineer, CFLHD

INTRODUCTION

This memorandum provides pavement and material recommendations for the Death Valley National Park CA ERFO NP DEVA 2023-3(2) Repairs and Armoring project.

The scope of this project is to finish emergency repairs from Hurricane Hillary including roadway reconditioning on select routes and pavement patching on all routes. Armoring both ERFO and non-ERFO eligible on all applicable routes scoped on October 2023. New and replacement gates in several different locations. Rehabilitation and emergency repairs on Harmony Borax trail including paving, repair of fencing, and paved shoulder for drainage.

FIELD INVESTIGATION

The Central Federal Lands Highway Division (CFLHD) in cooperation with Death Valley National Park plan to repair roads damaged by Hurricane Hilary and add roadway armoring at select locations to provide resiliency against future storm events.

Routes are included in this project:

• Beatty Cutoff Road

• Daylight Pass Road / Mud Canyon Road

• North Highway

• Emigrant Canyon Road

• Badwater Road, Route 15

• Old Stovepipe Wells Road

• Ubehebe Crater Road

• Dante's View Road

Memorandum

Date: February 15, 2024

• West Side Road

• Natural Bridge Road

• Keane Wonder Mine Road (Aggregate Surface Course) This route may be constructed by the Park.

• Bonnie Claire Road, Route 11

• Harmony Borrax Works Interpretive Trail

As part of the ERFO scoping a site visit was conducted by CFLHD from October 11-12, 2023.

Photos of existing conditions can be found in Appendix A of the Drainage Report

The scope of the project includes asphalt repairs, roadway reconditioning, culvert replacement/placement, and adding protective armoring in specific locations.

A field investigation was not conducted by Pavements and Materials for this project.

Recommendations for pavement structural sections and materials are based on pavement measurements by field construction engineers and previously constructed projects.

The scope of the asphalt repair work is to match the existing structural section or repair as an asphalt concrete pavement patch. The work will permanently patch the roadways in sections that have been temporarily repaired using cold patch asphalt or native material as a temporary surfacing course.

TRAFFIC

Traffic counts are not applicable to this project.

DESIGN RECOMMENDATIONS

Recommendation for locations requiring repairs for existing paved roadways:

418 - ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1

Layer Thickness

403 Asphalt Concrete Pavement, Type I 4 inches

703.06 Crushed Aggregate 6 inches

Recommendation for locations requiring repairs for existing earth or gravel roadways:

302 - AGGREGATE SURFACE COURSE, 6-INCH DEPTH

302 Aggregate Surface Course, 6-inch depth 6 inches

Recommendation for locations requiring repairs for existing asphalt paved sidewalks and trails:

615 - SIDEWALK, ASPHALT

403 Asphalt Concrete Pavement, Type I 2 inches

704.02 Bedding Material 4 inches

ADDITIONAL RECOMMENDATIONS:

• Saw cutting, Prime Coat, Tack Coat, and Blotter are included in the patching pay item.

• Repair and reconditioning of the base and subgrade for areas that settled since the temporary repair are included in the patching pay item.

• Include a nominal amount of subexcavation (200 cu yd) to be used at discretion of the

CO.

• For the 403 Asphalt Concrete Pavement specify that it is Asphalt Concrete Pavement, Type I. The Type I specifies the asphalt concrete pavement conforms to current state department of transportation material specifications and JMF.

• No locations have been identified for the 30203-2140 Aggregate Surface Course, 6-inch depth, SQYD pay item.

• Recommend the following bid items.

Item Number Item Description Unit

20402-0000 SUBEXCAVATION CUYD

30203-2140 ROADWAY AGGREGATE, METHOD 2, SURFACE

COURSE, 6-INCH DEPTH SQYD

41801-2000 ASPHALT CONCRETE PAVEMENT PATCH, TYPE 1 SQYD

61501-1100 SIDEWALK, ASPHALT SQYD

CONSTRUCTION CONSIDERATIONS & SPECIAL CONTRACT PROVISIONS

CFLHD standard SCR’s related to pavements & materials will be used.

• A SCR edited from the LOS for 302 surfacing aggregate has been developed for this project..

A SCR for 403 Asphalt Concrete Pavement has been developed to use with the 418 Asphalt Concrete Pavement Patch, Type 1 or Type 2.

• A SCR for 418 Asphalt Concrete Pavement has been developed for the 418 Asphalt Concrete Pavement Patch, Type 1 or Type 2 pay items used

Memorandum