QandA 10.7.24- TX FLAP FM 709(1).pdf
PDF 115 KB Posted
- Attached to
- TX FLAP FM 709(1) – Access to Navarro Mills Lake
- Solicitation number
- 6982AF23B000037
About this file
This document contains Questions and Answers related to the federal contract opportunity for the TX FLAP FM 709(1) – Access to Navarro Mills Lake project.
The key details are:
- The project involves 3R rehabilitation to 3.8 miles of FM 709 to provide access to the Navarro Mills Harbor Marina and Dam Road, including full depth reclamation, shoulder widening, and asphalt concrete paving.
- The principal work items include 7,820 CY of embankment construction, 29,000 tons of aggregate base, 49,750 SY of recycled aggregate base with cement, 7,000 tons of asphalt concrete paving, and various drainage structure work.
- The anticipated schedule is to advertise in September 2024, award in Fall 2024, and construct from November 2024 to August 2025.
- The estimated cost range is between $5,000,000 and $10,000,000.
- The Q&A addresses questions regarding roadway excavation, the construction schedule, and the cement treated aggregate course.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for TX FLAP FM 709(1) Navarro Mills Lake Road
October 2, 2024
Questions Answers 1 There is no pay item listed for Roadway Excavation in the
Summary of Quantities Sheets of the plans yet there is a detail for Roadway Excavation on Sheet A9 of the plans as well as tabs in the Grading Summary on Sheet B3 of the plans for Roadway Excavation in the quantity of 12,957 CY. Is Roadway Excavation incidental to an item and I am missing the note or is it missing from the Summary of Quantities/Bid Items?
We are paying for embankment construction only.
2 On the Sam.gov solicitation it lists construction from November 2024–August 2025, but the SCRs say the expected NTP is 12/13/24 with the period of performance ending 2/12/26. Am I correct in assuming that the SCRs would govern here?
See amendment A001dated 10/08/24
3 In the SCR for the Cement Treated Aggregate Course it says, "At the option of the contractor, the existing surfacing and aggregate base may be salvaged, processed, and reused to reduce the quantity of imported crushed aggregate." Wouldn't any imported aggregate be paid in the Roadway Aggregate that has a quantity of 28,500 tons?
See pay item 30703-0000