This document contains Questions and Answers related to a federal contract opportunity for the TX FLAP FM 709(1) - Access to Navarro Mills Lake road rehabilitation project.

The project involves 3R rehabilitation of 3.8 miles of FM 709 to provide access to the Navarro Mills Harbor Marina and Dam Road. Key work items include full depth reclamation, shoulder widening, asphalt concrete pavement, guardrail installation, culvert replacement, and safety improvements such as signing, pavement markings, and rumble strips. The estimated cost range is $5-10 million, with construction anticipated to occur from November 2024 to August 2025. The Q&A provides clarification on items such as the need for epoxy adhesive for pavement markers, whether the superintendent/QCM can be the same individual, and allowances for extending the period of performance. It also addresses questions about specific material requirements, planned phasing, and other project details.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

TX FLAP FM 709(1) Navarro Mills Lake Road

October 2, 2024

Questions Answers

1 There is no pay item listed for Roadway Excavation in the

Summary of Quantities Sheets of the plans yet there is a detail for

Roadway Excavation on Sheet A9 of the plans as well as tabs in the Grading Summary on Sheet B3 of the plans for Roadway

Excavation in the quantity of 12,957 CY. Is Roadway Excavation incidental to an item and I am missing the note or is it missing from the Summary of Quantities/Bid Items?

We are paying for embankment construction only.

2 On the Sam.gov solicitation it lists construction from November

2024–August 2025, but the SCRs say the expected NTP is

12/13/24 with the period of performance ending 2/12/26. Am I correct in assuming that the SCRs would govern here?

See amendment A001 dated 10/07/24

3 In the SCR for the Cement Treated Aggregate Course it says, "At the option of the contractor, the existing surfacing and aggregate base may be salvaged, processed, and reused to reduce the quantity of imported crushed aggregate." Wouldn't any imported aggregate be paid in the Roadway Aggregate that has a quantity of

28,500 tons?

See pay item 30703-0000

October 10, 2024

1 Could you please clarify the reasoning behind the decision to install plowable markers on this roadway?

See FP-14 Section-634, plan sheet V22, Pavement Markings

2 What are the specific reasons for requiring epoxy adhesive for the placement of these markers? TxDOT does not have an epoxy adhesive that meets the projects specifications. The standard practice in Texas involves using bituminous adhesive for markers

See FP-14 Section-634.10 on asphalt surfaces, and regular or flexible adhesive is typically utilized for the placement of raised markers. Will these standard practices be accepted for this project?

October 24, 2024

1 Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

QCM must be separate. There is no SSHO requirement.

2 Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

See section 153.08 and FP 108.05

3 Are soil boring reports available?

See Pavement report for boring logs

4 What specific materials meet or exceed the TXDOT requirement for Aggregate Base for this project?

See section 307 and refer to 703

5 What specific materials meet or exceed the TXDOT requirement for Cement Treated Aggregate Course for this project?

See section 307 and refer to 703

6 What specific materials meet or exceed the TXDOT requirement for Cement for this project?

See section 307 and refer to FP 701

7 What specific materials meet or exceed the TXDOT requirement for Asphalt Concrete Pavement, Type 1 for this project?

See section 403

8 What specific materials meet or exceed the TXDOT requirement for Prime Coat, Method 1 for this project?

See section 411

9 What is the location for the field office?

Contractor determined

10 Who will be inspecting the project?

See FP-14 section 104 and 153

11 Are new posts required for removing and resetting mailboxes? See section 646

12 When is the planned start and end date for this project?

See FAR clause 52.211-10 and section 108.01

13 For line item A1280 63314-0000 RUMBLE STRIP; please clarify what type of rumble strip is required.

See plan sheet V19-V20, option-1 (Milled centerline).

14 There are segments where the existing tree line is within the clearing area. Will the contractor be required to trim and/or remove trees within the clearing area?

No trees are within the clearing area.

15 There are certain drives that are concrete paved (example: STA

38+60). Will we be required to remove the concrete and pave the new drive in concrete to match existing, or are we to follow the typical sections per sheet A8?

See plan sheet A8, typical section

16 There are approx. 5 drives and 7 mailboxes that were not included on the plans or bid schedule. Are we to base our proposal based on the current bid schedule or will these drives & mailboxes will be incorporated at a later date based on the bid schedule unit prices?

See plan sheet B10, payment will be made for actual work performed as directed and approved by CO.

17 Sheet A6 states the existing asphalt pavement depth varies from

2” to 2.5”. Based on the existing condition, it appears the road has been overlayed at least once and the existing asphalt thickness in a number of sections is much thicker than 2.5”.

a. Are we to submit our proposal with the assumption that the existing asphalt is 2” to 2.5” thick and an adjustment can be made after award?

b. Will the new pavement profile of 7” above existing be based on the current pavement elevation or based on the existing thickness being 2” to 2.5” thick?

A) No bid per the plans.

B) See plan sheet A6 and K1, 7” above current pavement elevation at centerline. See plan and profile sheets.

18 Will there be a staging area for the contractor to use throughout the construction period?

No staging area provided.

19 It does not appear that a wage determination for this project is included with the solicitation. Will the wage determination be issues prior to bid?

See section D of the solicitation

20 Other than SWPPP permits, are there any other permits required for this project?

See section 107, 155 and 157

21 Is there a specific project phasing we are required to follow or does the contractor have the flexibility to phase the project as needed?

See section 108.01(a)

22 Is there a limit to the length of road that can be worked at one time?

23 Will the contractor be allowed to work on several road segments simultaneously?

24 Will the contractor have access to water utilities for construction at no cost or will the contractor be required to pay for water?

Contractor provided

25 For those who cannot attend the bid opening in person, is there a conference number that can be used to call in at?

No. A bid opening summary will be posted on SAM.gov shortly after the bid opening concludes.

26 Are precast Safety End Treatment (SET) Type 2 suitable for the referenced Standard End Sections of pipe culverts?

See plan sheet T-5

27 Is the Supplemental Concrete Pipe Tie required for any portion of this project?

See plan sheet T-4

28 Where can I find specific information for: A0860 60213-0900

BRANCH CONNECTION, 30-INCH 1 EACH?

See FP-14, Sections 602

29 After the removal and installation of the pipe culverts, should there be a line item for asphalt/concrete patchwork after the culvert pipework is completed to subgrade?

No separate payment will be made for asphalt/concrete patch work at pipe culverts.