Bid Tabulation Monterey Bay.pdf

PDF 1 MB Posted

Attached to
CA FLAP SCRT5(1) Monterey Bay Sanctuary Scenic Trail
Solicitation number
6982AF23B000033
Issued by

About this file

This document is a Bid Tabulation for a federal contract opportunity to develop the Monterey Bay Sanctuary Scenic Trail, a 7.5-mile multi-use bicycle and pedestrian trail in Santa Cruz County, California. The proposed project includes an asphalt-paved trail with unpaved gravel shoulders, as well as improvements to two parking lots along Highway 1.

The Bid Tabulation provides details on the bids received, including the bid amounts, unit prices, and responsiveness for four bidders: AE West LLC, Goodfellow Brothers California, LLC, Granite Rock Company, and Joseph J. Albanese Inc. AE West LLC was identified as the apparent low bidder after the HUBZone Price Preference. The total bid amounts ranged from $32,053,693.50 to $41,841,288.83. The bid schedule included a base schedule and two optional schedules (X and Y). The contract is being procured by the Federal Highway Administration (FHWA) Central Federal Lands Highway Division in cooperation with the Santa Cruz County Regional Transportation Commission.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

HUBZone Price Evaluation

CA FLAP SCR T5(1) Monterey Bay Sanctuary Scenic Trail Schedule A Option X Option Y Total Bid Amount 10% factor Adjusted Bid Amount

Contractor

Goodfellow Brothers California, LLC (LB) $32,687,096.10 $2,450,393.50 $2,900,045.70 $38,037,535.30 $3,803,753.53 $41,841,288.83 Granite Rock Company (LB) $30,090,196.95 $2,439,354.50 $2,983,181.70 $35,512,733.15 $3,551,273.32 $39,064,006.47 Joseph J Alanese Inc. (LB) $27,676,509.00 $2,117,031.50 $2,260,153.00 $32,053,693.50 $3,205,369.35 $35,259,062.85

$29,788,902.94 $2,799,760.81 $3,841,340.74 $36,430,004.49 $36,430,004.49AE West LLC (SBC, HUBZONE)

*Apparent low bidder after HUBZone Price Preference.

Tabulation of Bids Report Date: 03/29/24

1 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Contractor Responsive?

Engineer's Estimate

AE West LLC

Goodfellow Brothers California, LLC

Granite Rock Company

Joseph J. Albanese Inc

Base Schedule A

$27,000,000.00

$29,788,902.94

$32,687,096.10

$30,090,196.95

$27,676,509.00

Option: Y

$3,635,000.00

$3,841,340.74

$2,900,045.70

$2,983,181.70

$2,260,153.00

Option: X

$1,960,000.00

$2,799,760.81

$2,450,393.50

$2,439,354.50

$2,117,031.50

Contractor Responsive?

Engineer's Estimate

AE West LLC

Goodfellow Brothers California, LLC

Granite Rock Company

Joseph J. Albanese Inc

Total Base Schedule A and Option(s): Y

$30,635,000.00

$33,630,243.68

$35,587,141.80

$33,073,378.65

$29,936,662.00

Total Base Schedule A and Option(s): YX

$32,595,000.00

$36,430,004.49

$38,037,535.30

$35,512,733.15

$32,053,693.50

Total Base Schedule A and Option(s): X

$28,960,000.00

$32,588,663.75

$35,137,489.60

$32,529,551.45

$29,793,540.50

2 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Solcitation No: 6982AF23B000033

Division: Central Federal Lands

State: CA County: Santa Cruz

Federal Land: U.S. Bureau of Land Management Opened at: Lakewood

Opened by: Karsten

Date: 03/26/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Joseph J. Albanese Inc Schedule Y- Bid total- $2,206,153.00 Calculated Total- $2,260,153.00

Total Bid- $31,999,693.50 Calculated Total-$32,053,693.50

$2,260,153.00 851 Martin Ave Santa Clara, CA 95050

Goodfellow Brothers California, LLC $2,900,045.70 50 Contractors Street Livermore, CA 94551

Granite Rock Company $2,983,181.70 5225 Hellyer Ave Suite 220 San Jose, CA 95138

AE West LLC Bid Item A0110:

Bid total- $323,640.00 Calculated total- $416,640.00

Schedule A bid total- $29,695,902.94 Calculated total-$29,788,902.94

Schedule X Bid total- $2,799,760.80 Calculated total- $2,799,760.81

Schedule Y Bid total- $3,841,340.71 Calculated total- $3,841,340.74

Bid total- $36,337,004.45 Calculated total- $36,430,004.49

$3,841,340.71 3112 Spring Hollow Ct Ann Arbor , MI 48105

Engineer's Estimate $3,635,000.00

Contracting Officer

03.29.2024

3 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3000 15101-0000 MOBILIZATION

Joseph J. Albanese Inc Lump Sum $6,760.00 Goodfellow Brothers California, LLC Lump Sum $20,000.00 Granite Rock Company Lump Sum $258,000.00 AE West LLC Lump Sum $355,096.52 Engineer's Estimate ALL LPSM Lump Sum $454,381.70

Y3010 15206-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING STAKE

Joseph J. Albanese Inc $5,000.00 $1,615.00 Goodfellow Brothers California, LLC $24,000.00 $7,752.00 Granite Rock Company $23,000.00 $7,429.00 AE West LLC $61,686.19 $19,924.64 Engineer's Estimate 0.323 MILE $10,000.00 $3,230.00

Y3020 15214-3000 SURVEY AND STAKING, PARKING AREA

Joseph J. Albanese Inc Lump Sum $6,140.00 Goodfellow Brothers California, LLC Lump Sum $5,500.00 Granite Rock Company Lump Sum $4,000.00 AE West LLC Lump Sum $30,843.09 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

Y3030 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE

Joseph J. Albanese Inc $1,190.00 $3,570.00 Goodfellow Brothers California, LLC $1,100.00 $3,300.00 Granite Rock Company $4,000.00 $12,000.00 AE West LLC $4,318.03 $12,954.09 Engineer's Estimate 3 EACH $3,500.00 $10,500.00

Y3040 15216-2000 SURVEY AND STAKING, GRADE FINISHING STAKES

Joseph J. Albanese Inc $9,000.00 $5,814.00 Goodfellow Brothers California, LLC $8,000.00 $5,168.00 Granite Rock Company $11,600.00 $7,493.60 AE West LLC $8,019.21 $5,180.41 Engineer's Estimate 0.646 MILE $13,500.00 $8,721.00

Y3050 15301-0000 CONTRACTOR QUALITY CONTROL

Joseph J. Albanese Inc Lump Sum $12,300.00 Goodfellow Brothers California, LLC Lump Sum $2,000.00 Granite Rock Company Lump Sum $15,000.00 AE West LLC Lump Sum $67,854.80 Engineer's Estimate ALL LPSM Lump Sum $100,200.00

4 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3060 15401-0000 CONTRACTOR TESTING

Joseph J. Albanese Inc Lump Sum $9,710.00 Goodfellow Brothers California, LLC Lump Sum $4,000.00 Granite Rock Company Lump Sum $30,000.00 AE West LLC Lump Sum $27,141.92 Engineer's Estimate ALL LPSM Lump Sum $85,900.00

Y3070 15501-0000 CONSTRUCTION SCHEDULE

Joseph J. Albanese Inc Lump Sum $21,200.00 Goodfellow Brothers California, LLC Lump Sum $1,000.00 Granite Rock Company Lump Sum $2,500.00 AE West LLC Lump Sum $4,318.03 Engineer's Estimate ALL LPSM Lump Sum $12,500.00

Y3080 15701-0000 SOIL EROSION CONTROL (CALTRANS SWDR MANAGEMENT, REPORTING & IMPLEMENTATION)

Joseph J. Albanese Inc Lump Sum $5,530.00 Goodfellow Brothers California, LLC Lump Sum $5,000.00 Granite Rock Company Lump Sum $10,500.00 AE West LLC Lump Sum $67,854.80 Engineer's Estimate ALL LPSM Lump Sum $65,000.00

Y3090 15705-1400 SOIL EROSION CONTROL, FIBER ROLL (CALTRANS TYPE 1)

Joseph J. Albanese Inc $4.00 $5,200.00 Goodfellow Brothers California, LLC $8.80 $11,440.00 Granite Rock Company $3.20 $4,160.00 AE West LLC $19.13 $24,869.00 Engineer's Estimate 1,300 LNFT $6.00 $7,800.00

Y3100 15706-0200 SOIL EROSION CONTROL, CHECK DAM

Joseph J. Albanese Inc $210.00 $630.00 Goodfellow Brothers California, LLC $1,500.00 $4,500.00 Granite Rock Company $220.00 $660.00 AE West LLC $925.29 $2,775.87 Engineer's Estimate 3 EACH $500.00 $1,500.00

Y3110 15706-1000 SOIL EROSION CONTROL, INLET PROTECTION

Joseph J. Albanese Inc $525.00 $2,100.00 Goodfellow Brothers California, LLC $475.00 $1,900.00 Granite Rock Company $250.00 $1,000.00 AE West LLC $1,788.90 $7,155.60 Engineer's Estimate 4 EACH $320.00 $1,280.00

5 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3120 15706-1600 SOIL EROSION CONTROL, STABILIZED CONSTRUCTION EXIT

Joseph J. Albanese Inc $15,900.00 $15,900.00 Goodfellow Brothers California, LLC $5,000.00 $5,000.00 Granite Rock Company $8,000.00 $8,000.00 AE West LLC $10,642.10 $10,642.10 Engineer's Estimate 1 EACH $8,000.00 $8,000.00

Y3130 15802-0000 WATERING FOR DUST CONTROL

Joseph J. Albanese Inc Lump Sum $27,000.00 Goodfellow Brothers California, LLC Lump Sum $2,000.00 Granite Rock Company Lump Sum $12,000.00 AE West LLC Lump Sum $9,475.00 Engineer's Estimate ALL LPSM Lump Sum $45,000.00

Y3140 20101-0000 CLEARING AND GRUBBING

Joseph J. Albanese Inc $7,400.00 $15,540.00 Goodfellow Brothers California, LLC $38,000.00 $79,800.00 Granite Rock Company $18,000.00 $37,800.00 AE West LLC $14,265.77 $29,958.12 Engineer's Estimate 2.1 ACRE $20,000.00 $42,000.00

Y3150 20301-2400 REMOVAL OF SIGN

Joseph J. Albanese Inc $150.00 $2,250.00 Goodfellow Brothers California, LLC $175.00 $2,625.00 Granite Rock Company $165.00 $2,475.00 AE West LLC $370.12 $5,551.80 Engineer's Estimate 15 EACH $300.00 $4,500.00

Y3160 20302-2600 REMOVAL OF PAVEMENT MARKINGS

Joseph J. Albanese Inc $3.00 $36,000.00 Goodfellow Brothers California, LLC $2.30 $27,600.00 Granite Rock Company $3.00 $36,000.00 AE West LLC $2.78 $33,360.00 Engineer's Estimate 12,000 LNFT $1.50 $18,000.00

Y3170 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS

Joseph J. Albanese Inc Lump Sum $26,900.00 Goodfellow Brothers California, LLC Lump Sum $45,000.00 Granite Rock Company Lump Sum $16,000.00 AE West LLC Lump Sum $9,582.42 Engineer's Estimate ALL LPSM Lump Sum $30,000.00

6 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3180 20401-0000 ROADWAY EXCAVATION

Joseph J. Albanese Inc $22.00 $185,240.00 Goodfellow Brothers California, LLC $74.00 $623,080.00 Granite Rock Company $22.00 $185,240.00 AE West LLC $19.89 $167,473.80 Engineer's Estimate 8,420 CUYD $60.00 $505,200.00

Y3190 20435-2500 BACKFILL, PERMEABLE

Joseph J. Albanese Inc $200.00 $46,000.00 Goodfellow Brothers California, LLC $211.00 $48,530.00 Granite Rock Company $237.00 $54,510.00 AE West LLC $80.11 $18,425.30 Engineer's Estimate 230 CUYD $125.00 $28,750.00

Y3200 21101-2000 ROADWAY OBLITERATION, METHOD 2

Joseph J. Albanese Inc $23.00 $12,075.00 Goodfellow Brothers California, LLC $12.00 $6,300.00 Granite Rock Company $22.00 $11,550.00 AE West LLC $26.62 $13,975.50 Engineer's Estimate 525 SQYD $20.00 $10,500.00

Y3210 25101-0200 PLACED RIPRAP, METHOD A, CLASS 2

Joseph J. Albanese Inc $325.00 $19,500.00 Goodfellow Brothers California, LLC $605.00 $36,300.00 Granite Rock Company $380.00 $22,800.00 AE West LLC $311.61 $18,696.60 Engineer's Estimate 60 CUYD $250.00 $15,000.00

Y3220 25126-0000 REMOVE AND RESET BOULDER

Joseph J. Albanese Inc $765.00 $11,475.00 Goodfellow Brothers California, LLC $470.00 $7,050.00 Granite Rock Company $350.00 $5,250.00 AE West LLC $436.18 $6,542.70 Engineer's Estimate 15 EACH $350.00 $5,250.00

Y3230 30202-2000 ROADWAY AGGREGATE, METHOD 2

Joseph J. Albanese Inc $44.00 $204,600.00 Goodfellow Brothers California, LLC $77.00 $358,050.00 Granite Rock Company $82.00 $381,300.00 AE West LLC $87.36 $406,224.00 Engineer's Estimate 4,650 TON $90.00 $418,500.00

7 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3240 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Joseph J. Albanese Inc $150.00 $285,000.00 Goodfellow Brothers California, LLC $205.00 $389,500.00 Granite Rock Company $176.00 $334,400.00 AE West LLC $468.38 $889,922.00 Engineer's Estimate 1,900 TON $215.00 $408,500.00

Y3250 40601-0000 FOG SEAL

Joseph J. Albanese Inc $1,900.00 $11,780.00 Goodfellow Brothers California, LLC $2,650.00 $16,430.00 Granite Rock Company $1,200.00 $7,440.00 AE West LLC $1,848.90 $11,463.18 Engineer's Estimate 6.2 TON $1,800.00 $11,160.00

Y3260 40605-0000 BLOTTER

Joseph J. Albanese Inc $200.00 $19,000.00 Goodfellow Brothers California, LLC $137.00 $13,015.00 Granite Rock Company $400.00 $38,000.00 AE West LLC $61.63 $5,854.85 Engineer's Estimate 95 TON $1,000.00 $95,000.00

Y3270 41102-1000 PRIME COAT, METHOD 1

Joseph J. Albanese Inc $2.00 $13,200.00 Goodfellow Brothers California, LLC $2.50 $16,500.00 Granite Rock Company $1.70 $11,220.00 AE West LLC $1.79 $11,814.00 Engineer's Estimate 6,600 SQYD $1.50 $9,900.00

Y3280 41201-0000 TACK COAT

Joseph J. Albanese Inc $1,250.00 $7,000.00 Goodfellow Brothers California, LLC $2,350.00 $13,160.00 Granite Rock Company $1,200.00 $6,720.00 AE West LLC $1,047.71 $5,867.18 Engineer's Estimate 5.6 TON $1,800.00 $10,080.00

Y3290 41301-0400 ASPHALT PAVEMENT MILLING, 1 1/2-INCH DEPTH

Joseph J. Albanese Inc $31.00 $12,090.00 Goodfellow Brothers California, LLC $28.50 $11,115.00 Granite Rock Company $40.00 $15,600.00 AE West LLC $20.55 $8,014.50 Engineer's Estimate 390 SQYD $40.00 $15,600.00

8 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3300 50101-0800 MINOR CONCRETE PAVEMENT, REINFORCED, 8-INCH DEPTH

Joseph J. Albanese Inc $165.00 $23,100.00 Goodfellow Brothers California, LLC $194.00 $27,160.00 Granite Rock Company $170.00 $23,800.00 AE West LLC $310.80 $43,512.00 Engineer's Estimate 140 SQYD $300.00 $42,000.00

Y3310 60201-0600 18-INCH PIPE CULVERT (METALLIC_COATED CORRUGATED STEEL)

Joseph J. Albanese Inc $150.00 $67,500.00 Goodfellow Brothers California, LLC $244.00 $109,800.00 Granite Rock Company $185.00 $83,250.00 AE West LLC $105.49 $47,470.50 Engineer's Estimate 450 LNFT $250.00 $112,500.00

Y3320 60210-0600 END SECTION FOR 18-INCH PIPE CULVERT (METALLIC_COATED CORRUGATED STEEL)

Joseph J. Albanese Inc $1,175.00 $2,350.00 Goodfellow Brothers California, LLC $1,800.00 $3,600.00 Granite Rock Company $325.00 $650.00 AE West LLC $4,287.13 $8,574.26 Engineer's Estimate 2 EACH $1,500.00 $3,000.00

Y3330 60403-0000 INLET (TYPE G1)

Joseph J. Albanese Inc $5,500.00 $11,000.00 Goodfellow Brothers California, LLC $6,200.00 $12,400.00 Granite Rock Company $6,000.00 $12,000.00 AE West LLC $12,143.59 $24,287.18 Engineer's Estimate 2 EACH $7,500.00 $15,000.00

Y3340 60403-0000 INLET (TYPE GO)

Joseph J. Albanese Inc $7,450.00 $7,450.00 Goodfellow Brothers California, LLC $8,600.00 $8,600.00 Granite Rock Company $6,000.00 $6,000.00 AE West LLC $8,542.51 $8,542.51 Engineer's Estimate 1 EACH $10,000.00 $10,000.00

Y3350 60901-1200 CURB, CONCRETE, 14-INCH DEPTH

Joseph J. Albanese Inc $55.00 $5,500.00 Goodfellow Brothers California, LLC $63.00 $6,300.00 Granite Rock Company $82.00 $8,200.00 AE West LLC $58.12 $5,812.00 Engineer's Estimate 100 LNFT $80.00 $8,000.00

9 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3360 60902-1200 CURB AND GUTTER, CONCRETE, 14-INCH DEPTH

Joseph J. Albanese Inc $75.00 $49,500.00 Goodfellow Brothers California, LLC $71.00 $46,860.00 Granite Rock Company $40.00 $26,400.00 AE West LLC $68.42 $45,157.20 Engineer's Estimate 660 LNFT $110.00 $72,600.00

Y3370 60905-1000 GUTTER, CONCRETE (6-INCH DEPTH)

Joseph J. Albanese Inc $55.00 $1,375.00 Goodfellow Brothers California, LLC $66.00 $1,650.00 Granite Rock Company $257.00 $6,425.00 AE West LLC $100.25 $2,506.25 Engineer's Estimate 25 LNFT $100.00 $2,500.00

Y3380 60915-1000 WHEELSTOP, CONCRETE

Joseph J. Albanese Inc $160.00 $8,160.00 Goodfellow Brothers California, LLC $128.00 $6,528.00 Granite Rock Company $300.00 $15,300.00 AE West LLC $154.08 $7,858.08 Engineer's Estimate 51 EACH $150.00 $7,650.00

Y3390 61501-0100 SIDEWALK, CONCRETE (REINFORCED, 5-INCH DEPTH)

Joseph J. Albanese Inc $145.00 $23,925.00 Goodfellow Brothers California, LLC $137.00 $22,605.00 Granite Rock Company $116.00 $19,140.00 AE West LLC $132.21 $21,814.65 Engineer's Estimate 165 SQYD $255.00 $42,075.00

Y3400 61501-0100 SIDEWALK, CONCRETE (4-INCH DEPTH)

Joseph J. Albanese Inc $125.00 $53,125.00 Goodfellow Brothers California, LLC $107.00 $45,475.00 Granite Rock Company $100.00 $42,500.00 AE West LLC $109.15 $46,388.75 Engineer's Estimate 425 SQYD $200.00 $85,000.00

Y3410 61505-1000 ACCESSIBILITY RAMP, CONCRETE

Joseph J. Albanese Inc $1,000.00 $2,000.00 Goodfellow Brothers California, LLC $6,300.00 $12,600.00 Granite Rock Company $4,500.00 $9,000.00 AE West LLC $4,303.45 $8,606.90 Engineer's Estimate 2 EACH $7,000.00 $14,000.00

10 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3420 61701-4500 GUARDRAIL SYSTEM MGS, TYPE 2, CLASS A STEEL POSTS

Joseph J. Albanese Inc $70.00 $67,375.00 Goodfellow Brothers California, LLC $75.00 $72,187.50 Granite Rock Company $82.00 $78,925.00 AE West LLC $133.55 $128,541.88 Engineer's Estimate 962.5 LNFT $75.00 $72,187.50

Y3430 61702-0000 TERMINAL SECTION (CALTRANS BURIED END ANCHOR)

Joseph J. Albanese Inc $19,400.00 $38,800.00 Goodfellow Brothers California, LLC $17,100.00 $34,200.00 Granite Rock Company $18,000.00 $36,000.00 AE West LLC $18,982.06 $37,964.12 Engineer's Estimate 2 EACH $10,000.00 $20,000.00

Y3440 61702-1500 TERMINAL SECTION, TYPE MGS TANGENT

Joseph J. Albanese Inc $7,750.00 $15,500.00 Goodfellow Brothers California, LLC $6,800.00 $13,600.00 Granite Rock Company $9,000.00 $18,000.00 AE West LLC $10,538.73 $21,077.46 Engineer's Estimate 2 EACH $7,500.00 $15,000.00

Y3450 61901-0000 FENCE (CABLE RAILING)

Joseph J. Albanese Inc $175.00 $107,800.00 Goodfellow Brothers California, LLC $188.00 $115,808.00 Granite Rock Company $600.00 $369,600.00 AE West LLC $246.52 $151,856.32 Engineer's Estimate 616 LNFT $80.00 $49,280.00

Y3460 61904-0000 BOLLARD POST

Joseph J. Albanese Inc $1,500.00 $6,000.00 Goodfellow Brothers California, LLC $2,700.00 $10,800.00 Granite Rock Company $1,800.00 $7,200.00 AE West LLC $5,176.92 $20,707.68 Engineer's Estimate 4 EACH $1,000.00 $4,000.00

Y3470 62201-0250 DUMP TRUCK, 10 CUBIC YARD MINIMUM CAPACITY

Joseph J. Albanese Inc $195.00 $3,900.00 Goodfellow Brothers California, LLC $140.00 $2,800.00 Granite Rock Company $204.00 $4,080.00 AE West LLC $234.20 $4,684.00 Engineer's Estimate 20 HOUR $175.00 $3,500.00

11 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3480 62201-0450 BACKHOE LOADER, 4 CUBIC FOOT MINIMUM RATED CAPACITY BUCKET, 18-INCH WIDTH

Joseph J. Albanese Inc $275.00 $5,500.00 Goodfellow Brothers California, LLC $193.00 $3,860.00 Granite Rock Company $304.00 $6,080.00 AE West LLC $289.66 $5,793.20 Engineer's Estimate 20 HOUR $200.00 $4,000.00

Y3490 62201-0850 WHEEL LOADER, 1 CUBIC YARD MINIMUM RATED CAPACITY

Joseph J. Albanese Inc $305.00 $6,100.00 Goodfellow Brothers California, LLC $174.00 $3,480.00 Granite Rock Company $232.00 $4,640.00 AE West LLC $283.50 $5,670.00 Engineer's Estimate 20 HOUR $225.00 $4,500.00

Y3500 62201-2800 MOTOR GRADER, 8 FOOT MINIMUM BLADE

Joseph J. Albanese Inc $245.00 $4,900.00 Goodfellow Brothers California, LLC $284.00 $5,680.00 Granite Rock Company $368.00 $7,360.00 AE West LLC $301.99 $6,039.80 Engineer's Estimate 20 HOUR $250.00 $5,000.00

Y3510 62201-3300 HYDRAULIC EXCAVATOR, 3/4 CUBIC YARD MINIMUM CAPACITY

Joseph J. Albanese Inc $485.00 $9,700.00 Goodfellow Brothers California, LLC $262.00 $5,240.00 Granite Rock Company $310.00 $6,200.00 AE West LLC $326.64 $6,532.80 Engineer's Estimate 20 HOUR $275.00 $5,500.00

Y3520 62301-0000 GENERAL LABOR

Joseph J. Albanese Inc $130.00 $2,600.00 Goodfellow Brothers California, LLC $82.00 $1,640.00 Granite Rock Company $165.00 $3,300.00 AE West LLC $166.40 $3,328.00 Engineer's Estimate 20 HOUR $90.00 $1,800.00

Y3530 62302-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES

Joseph J. Albanese Inc $220.00 $4,400.00 Goodfellow Brothers California, LLC $460.00 $9,200.00 Granite Rock Company $233.00 $4,660.00 AE West LLC $166.40 $3,328.00 Engineer's Estimate 20 HOUR $250.00 $5,000.00

12 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3540 62302-1100 SPECIAL LABOR, HIRED SURVEY SERVICES

Joseph J. Albanese Inc $220.00 $4,400.00 Goodfellow Brothers California, LLC $375.00 $7,500.00 Granite Rock Company $470.00 $9,400.00 AE West LLC $394.43 $7,888.60 Engineer's Estimate 20 HOUR $275.00 $5,500.00

Y3550 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (DUST MONITORING)

Joseph J. Albanese Inc Lump Sum $41,000.00 Goodfellow Brothers California, LLC Lump Sum $5,000.00 Granite Rock Company Lump Sum $17,000.00 AE West LLC Lump Sum $71,244.34 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

Y3560 62303-1000 SPECIAL LABOR, HIRED TECHNICAL SERVICES (BIOLOGICAL MONITORING)

Joseph J. Albanese Inc Lump Sum $9,980.00 Goodfellow Brothers California, LLC Lump Sum $5,000.00 Granite Rock Company Lump Sum $13,000.00 AE West LLC Lump Sum $71,244.34 Engineer's Estimate ALL LPSM Lump Sum $20,000.00

Y3570 62510-2000 SEEDING, HYDRAULIC METHOD

Joseph J. Albanese Inc $3,900.00 $5,850.00 Goodfellow Brothers California, LLC $3,000.00 $4,500.00 Granite Rock Company $2,700.00 $4,050.00 AE West LLC $9,860.81 $14,791.22 Engineer's Estimate 1.5 ACRE $15,000.00 $22,500.00

Y3580 62515-2000 MULCHING, HYDRAULIC METHOD

Joseph J. Albanese Inc $4,140.00 $6,210.00 Goodfellow Brothers California, LLC $2,150.00 $3,225.00 Granite Rock Company $1,900.00 $2,850.00 AE West LLC $2,711.73 $4,067.60 Engineer's Estimate 1.5 ACRE $15,000.00 $22,500.00

Y3590 62550-2000 BIOTIC SOIL AMENDMENT, HYDRAULIC METHOD

Joseph J. Albanese Inc $8,290.00 $9,119.00 Goodfellow Brothers California, LLC $6,900.00 $7,590.00 Granite Rock Company $6,100.00 $6,710.00 AE West LLC $9,860.81 $10,846.89 Engineer's Estimate 1.1 ACRE $10,000.00 $11,000.00

13 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3600 62901-0800 ROLLED EROSION CONTROL PRODUCT, TYPE 2.D

Joseph J. Albanese Inc $7.00 $14,000.00 Goodfellow Brothers California, LLC $6.00 $12,000.00 Granite Rock Company $6.50 $13,000.00 AE West LLC $45.64 $91,280.00 Engineer's Estimate 2,000 SQYD $10.00 $20,000.00

Y3610 63301-0000 SIGN SYSTEM

Joseph J. Albanese Inc $1,760.00 $33,440.00 Goodfellow Brothers California, LLC $600.00 $11,400.00 Granite Rock Company $580.00 $11,020.00 AE West LLC $961.42 $18,266.98 Engineer's Estimate 19 EACH $900.00 $17,100.00

Y3620 63309-0000 DELINEATOR (TYPE F, CLASS 2)

Joseph J. Albanese Inc $96.00 $480.00 Goodfellow Brothers California, LLC $69.00 $345.00 Granite Rock Company $70.00 $350.00 AE West LLC $363.62 $1,818.10 Engineer's Estimate 5 EACH $500.00 $2,500.00

Y3630 63313-0000 RUMBLE STRIP (CENTERLINE)

Joseph J. Albanese Inc $27.00 $59,805.00 Goodfellow Brothers California, LLC $16.00 $35,440.00 Granite Rock Company $5.00 $11,075.00 AE West LLC $18.49 $40,955.35 Engineer's Estimate 2,215 LNFT $6.00 $13,290.00

Y3640 63401-1700 PAVEMENT MARKINGS, TYPE I, SOLID

Joseph J. Albanese Inc $5.00 $82,500.00 Goodfellow Brothers California, LLC $4.00 $66,000.00 Granite Rock Company $4.40 $72,600.00 AE West LLC $3.08 $50,820.00 Engineer's Estimate 16,500 LNFT $2.00 $33,000.00

Y3650 63405-3300 PAVEMENT MARKINGS, TYPE I, TURN ARROW

Joseph J. Albanese Inc $194.00 $776.00 Goodfellow Brothers California, LLC $154.00 $616.00 Granite Rock Company $165.00 $660.00 AE West LLC $154.08 $616.32 Engineer's Estimate 4 EACH $1,000.00 $4,000.00

14 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3660 63405-3350 PAVEMENT MARKINGS, TYPE I, STRAIGHT ARROW

Joseph J. Albanese Inc $194.00 $776.00 Goodfellow Brothers California, LLC $154.00 $616.00 Granite Rock Company $165.00 $660.00 AE West LLC $154.08 $616.32 Engineer's Estimate 4 EACH $1,000.00 $4,000.00

Y3670 63405-3500 PAVEMENT MARKINGS, TYPE I, "STOP" WORD MESSAGE

Joseph J. Albanese Inc $350.00 $700.00 Goodfellow Brothers California, LLC $277.00 $554.00 Granite Rock Company $300.00 $600.00 AE West LLC $271.17 $542.34 Engineer's Estimate 2 EACH $1,000.00 $2,000.00

Y3680 63405-3650 PAVEMENT MARKINGS, TYPE I, ACCESSIBILITY SYMBOL

Joseph J. Albanese Inc $648.00 $1,944.00 Goodfellow Brothers California, LLC $513.00 $1,539.00 Granite Rock Company $550.00 $1,650.00 AE West LLC $597.82 $1,793.46 Engineer's Estimate 3 EACH $1,000.00 $3,000.00

Y3690 63406-0000 RAISED PAVEMENT MARKER (TYPE D)

Joseph J. Albanese Inc $26.00 $4,160.00 Goodfellow Brothers California, LLC $21.00 $3,360.00 Granite Rock Company $22.00 $3,520.00 AE West LLC $24.65 $3,944.00 Engineer's Estimate 160 EACH $35.00 $5,600.00

Y3700 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3

Joseph J. Albanese Inc $330.00 $1,320.00 Goodfellow Brothers California, LLC $86.00 $344.00 Granite Rock Company $330.00 $1,320.00 AE West LLC $332.81 $1,331.24 Engineer's Estimate 4 EACH $300.00 $1,200.00

Y3710 63502-0700 TEMPORARY TRAFFIC CONTROL, CONE

Joseph J. Albanese Inc $76.00 $3,800.00 Goodfellow Brothers California, LLC $29.00 $1,450.00 Granite Rock Company $30.00 $1,500.00 AE West LLC $61.63 $3,081.50 Engineer's Estimate 50 EACH $40.00 $2,000.00

15 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3720 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM

Joseph J. Albanese Inc $368.00 $11,040.00 Goodfellow Brothers California, LLC $69.00 $2,070.00 Granite Rock Company $70.00 $2,100.00 AE West LLC $104.78 $3,143.40 Engineer's Estimate 30 EACH $100.00 $3,000.00

Y3730 63502-1500 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE A

Joseph J. Albanese Inc $119.00 $476.00 Goodfellow Brothers California, LLC $91.00 $364.00 Granite Rock Company $90.00 $360.00 AE West LLC $54.24 $216.96 Engineer's Estimate 4 EACH $275.00 $1,100.00

Y3740 63502-1600 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE B

Joseph J. Albanese Inc $119.00 $476.00 Goodfellow Brothers California, LLC $91.00 $364.00 Granite Rock Company $90.00 $360.00 AE West LLC $176.27 $705.08 Engineer's Estimate 4 EACH $175.00 $700.00

Y3750 63502-1700 TEMPORARY TRAFFIC CONTROL, WARNING LIGHT TYPE C

Joseph J. Albanese Inc $119.00 $3,570.00 Goodfellow Brothers California, LLC $52.00 $1,560.00 Granite Rock Company $50.00 $1,500.00 AE West LLC $60.40 $1,812.00 Engineer's Estimate 30 EACH $50.00 $1,500.00

Y3760 63502-2100 TEMPORARY TRAFFIC CONTROL, CRASH CUSHION

Joseph J. Albanese Inc $10,700.00 $21,400.00 Goodfellow Brothers California, LLC $8,000.00 $16,000.00 Granite Rock Company $16,000.00 $32,000.00 AE West LLC $5,176.92 $10,353.84 Engineer's Estimate 2 EACH $4,500.00 $9,000.00

Y3770 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN (VARIABLE MESSAGE)

Joseph J. Albanese Inc $12,200.00 $73,200.00 Goodfellow Brothers California, LLC $280.00 $1,680.00 Granite Rock Company $540.00 $3,240.00 AE West LLC $295.82 $1,774.92 Engineer's Estimate 6 EACH $1,000.00 $6,000.00

16 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3780 63502-3900 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN

Joseph J. Albanese Inc $640.00 $31,360.00 Goodfellow Brothers California, LLC $430.00 $21,070.00 Granite Rock Company $450.00 $22,050.00 AE West LLC $912.12 $44,693.88 Engineer's Estimate 49 EACH $350.00 $17,150.00

Y3790 63503-0400 TEMPORARY TRAFFIC CONTROL, CONCRETE BARRIER

Joseph J. Albanese Inc $45.00 $99,900.00 Goodfellow Brothers California, LLC $63.00 $139,860.00 Granite Rock Company $40.00 $88,800.00 AE West LLC $78.39 $174,025.80 Engineer's Estimate 2,220 LNFT $100.00 $222,000.00

Y3800 63505-1000 TEMPORARY TRAFFIC CONTROL, PAVEMENT MARKINGS

Joseph J. Albanese Inc $36,000.00 $40,212.00 Goodfellow Brothers California, LLC $20,600.00 $23,010.20 Granite Rock Company $22,300.00 $24,909.10 AE West LLC $18,489.02 $20,652.24 Engineer's Estimate 1.117 MILE $4,400.00 $4,914.80

Y3810 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER

Joseph J. Albanese Inc $125.00 $20,000.00 Goodfellow Brothers California, LLC $100.00 $16,000.00 Granite Rock Company $124.00 $19,840.00 AE West LLC $89.84 $14,374.40 Engineer's Estimate 160 HOUR $115.00 $18,400.00

Y3820 64602-1000 BUILDING, RESTROOM FACILITY (YELLOWBANK)

Joseph J. Albanese Inc Lump Sum $105,000.00 Goodfellow Brothers California, LLC Lump Sum $131,500.00 Granite Rock Company Lump Sum $262,600.00 AE West LLC Lump Sum $205,028.86 Engineer's Estimate ALL LPSM Lump Sum $75,000.00

Y3830 64603-0100 FIXTURE, TRASH RECEPTACLE

Joseph J. Albanese Inc $4,100.00 $4,100.00 Goodfellow Brothers California, LLC $4,600.00 $4,600.00 Granite Rock Company $3,300.00 $3,300.00 AE West LLC $3,565.22 $3,565.22 Engineer's Estimate 1 EACH $3,000.00 $3,000.00

17 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: Y

Schedule Type: Options

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

Y3840 64603-0300 FIXTURE, BENCH

Joseph J. Albanese Inc $3,700.00 $7,400.00 Goodfellow Brothers California, LLC $4,600.00 $9,200.00 Granite Rock Company $4,200.00 $8,400.00 AE West LLC $4,044.89 $8,089.78 Engineer's Estimate 2 EACH $3,000.00 $6,000.00

Y3850 64603-0500 FIXTURE, BICYCLE STORAGE RACK

Joseph J. Albanese Inc $770.00 $3,080.00 Goodfellow Brothers California, LLC $2,900.00 $11,600.00 Granite Rock Company $1,250.00 $5,000.00 AE West LLC $722.60 $2,890.40 Engineer's Estimate 4 EACH $3,000.00 $12,000.00

Total Schedule - All Items

Joseph J. Albanese Inc $2,260,153.00 Goodfellow Brothers California, LLC $2,900,045.70 Granite Rock Company $2,983,181.70 AE West LLC $3,841,340.71 Engineer's Estimate $3,635,000.00

18 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Solcitation No: 6982AF23B000033

Division: Central Federal Lands

State: CA County: Santa Cruz

Federal Land: U.S. Bureau of Land Management Opened at: Lakewood

Opened by: Karsten

Date: 03/26/24

I certify that this Bid Tabulation accurately reflects the offers received for this solicitation.

Signed: _______________________________

Title: _______________________________

Date: _______________________________

Contract Awarded to: ____________________ Award Date: ____________________

Contractor Comment Bid Amount Responsive

Joseph J. Albanese Inc Schedule Y- Bid total- $2,206,153.00 Calculated Total- $2,260,153.00

Total Bid- $31,999,693.50 Calculated Total-$32,053,693.50

$27,676,509.00 851 Martin Ave Santa Clara, CA 95050

AE West LLC Bid Item A0110:

Bid total- $323,640.00 Calculated total- $416,640.00

Schedule A bid total- $29,695,902.94 Calculated total-$29,788,902.94

Schedule X Bid total- $2,799,760.80 Calculated total- $2,799,760.81

Schedule Y Bid total- $3,841,340.71 Calculated total- $3,841,340.74

Bid total- $36,337,004.45 Calculated total- $36,430,004.49

$29,788,902.94 3112 Spring Hollow Ct Ann Arbor , MI 48105

Granite Rock Company $30,090,196.94 5225 Hellyer Ave Suite 220 San Jose, CA 95138

Goodfellow Brothers California, LLC $32,687,096.10 50 Contractors Street Livermore, CA 94551

Engineer's Estimate $27,000,000.00

19 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0010 15101-0000 MOBILIZATION

Joseph J. Albanese Inc Lump Sum $2,866,998.00 AE West LLC Lump Sum $2,614,803.33 Granite Rock Company Lump Sum $2,370,000.00 Goodfellow Brothers California, LLC Lump Sum $3,800,000.00 Engineer's Estimate ALL LPSM Lump Sum $3,072,817.50

A0020 15214-2000 SURVEY AND STAKING, RETAINING WALL (ROCKERY)

Joseph J. Albanese Inc Lump Sum $3,580.00 AE West LLC Lump Sum $6,415.36 Granite Rock Company Lump Sum $5,650.00 Goodfellow Brothers California, LLC Lump Sum $4,100.00 Engineer's Estimate ALL LPSM Lump Sum $10,000.00

A0030 15214-2500 SURVEY AND STAKING, REINFORCED SOIL SLOPE (DAVENPORT)

Joseph J. Albanese Inc Lump Sum $4,610.00 AE West LLC Lump Sum $32,076.82 Granite Rock Company Lump Sum $55,031.00 Goodfellow Brothers California, LLC Lump Sum $5,400.00 Engineer's Estimate ALL LPSM Lump Sum $30,000.00

A0040 15215-3000 SURVEY AND STAKING, DRAINAGE STRUCTURE

Joseph J. Albanese Inc $608.00 $24,320.00 AE West LLC $1,172.04 $46,881.60 Granite Rock Company $954.85 $38,194.00 Goodfellow Brothers California, LLC $2,000.00 $80,000.00 Engineer's Estimate 40 EACH $2,250.00 $90,000.00

A0050 15225-0000 SLOPE, REFERENCE, AND CLEARING AND GRUBBING CONTROL

Joseph J. Albanese Inc $11,000.00 $84,755.00 AE West LLC $7,420.98 $57,178.65 Granite Rock Company $21,984.05 $169,387.11 Goodfellow Brothers California, LLC $9,700.00 $74,738.50 Engineer's Estimate 7.705 MILE $12,500.00 $96,312.50

A0060 15236-2000 SURVEY CONTROL, GRADE FINISHING

Joseph J. Albanese Inc $3,000.00 $46,236.00 AE West LLC $3,207.69 $49,436.92 Granite Rock Company $17,171.43 $264,646.08 Goodfellow Brothers California, LLC $2,300.00 $35,447.60 Engineer's Estimate 15.412 MILE $7,500.00 $115,590.00

20 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0070 15301-0000 CONTRACTOR QUALITY CONTROL

Joseph J. Albanese Inc Lump Sum $495,000.00 AE West LLC Lump Sum $383,550.59 Granite Rock Company Lump Sum $330,000.00 Goodfellow Brothers California, LLC Lump Sum $1,200,000.00 Engineer's Estimate ALL LPSM Lump Sum $800,000.00

A0080 15401-0000 CONTRACTOR TESTING

Joseph J. Albanese Inc Lump Sum $704,000.00 AE West LLC Lump Sum $664,531.15 Granite Rock Company Lump Sum $580,000.00 Goodfellow Brothers California, LLC Lump Sum $150,000.00 Engineer's Estimate ALL LPSM Lump Sum $800,000.00

A0090 15501-0000 CONSTRUCTION SCHEDULE

Joseph J. Albanese Inc Lump Sum $12,800.00 AE West LLC Lump Sum $6,168.62 Granite Rock Company Lump Sum $25,000.00 Goodfellow Brothers California, LLC Lump Sum $10,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00

A0100 15705-0100 SOIL EROSION CONTROL, SILT FENCE

Joseph J. Albanese Inc $4.00 $30,000.00 AE West LLC $13.44 $100,800.00 Granite Rock Company $2.60 $19,500.00 Goodfellow Brothers California, LLC $4.00 $30,000.00 Engineer's Estimate 7,500 LNFT $15.00 $112,500.00

A0110 15705-1400 SOIL EROSION CONTROL, FIBER ROLL

Joseph J. Albanese Inc $4.50 $418,500.00 AE West LLC $4.48 $416,640.00 Granite Rock Company $3.15 $292,950.00 Goodfellow Brothers California, LLC $6.10 $567,300.00 Engineer's Estimate 93,000 LNFT $7.50 $697,500.00

A0120 15802-0000 WATERING FOR DUST CONTROL

Joseph J. Albanese Inc Lump Sum $587,000.00 AE West LLC Lump Sum $207,508.51 Granite Rock Company Lump Sum $500,000.00 Goodfellow Brothers California, LLC Lump Sum $20,000.00 Engineer's Estimate ALL LPSM Lump Sum $500,000.00

21 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0130 20101-0000 CLEARING AND GRUBBING

Joseph J. Albanese Inc $12,800.00 $512,000.00 AE West LLC $6,193.66 $247,746.40 Granite Rock Company $15,000.00 $600,000.00 Goodfellow Brothers California, LLC $13,500.00 $540,000.00 Engineer's Estimate 40.00 ACRE $15,000.00 $600,000.00

A0140 20301-1100 REMOVAL OF GATE

Joseph J. Albanese Inc $1,250.00 $15,000.00 AE West LLC $431.80 $5,181.60 Granite Rock Company $600.00 $7,200.00 Goodfellow Brothers California, LLC $2,000.00 $24,000.00 Engineer's Estimate 12 EACH $2,500.00 $30,000.00

A0150 20301-1900 REMOVAL OF PIPE CULVERT

Joseph J. Albanese Inc $1,630.00 $19,560.00 AE West LLC $1,963.86 $23,566.32 Granite Rock Company $2,200.00 $26,400.00 Goodfellow Brothers California, LLC $4,000.00 $48,000.00 Engineer's Estimate 12 EACH $4,000.00 $48,000.00

A0160 20301-2400 REMOVAL OF SIGN

Joseph J. Albanese Inc $308.00 $7,700.00 AE West LLC $388.62 $9,715.50 Granite Rock Company $175.00 $4,375.00 Goodfellow Brothers California, LLC $175.00 $4,375.00 Engineer's Estimate 25 EACH $250.00 $6,250.00

A0170 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (RAILROAD REMOVAL)

Joseph J. Albanese Inc Lump Sum $101,000.00 AE West LLC Lump Sum $925,292.76 Granite Rock Company Lump Sum $65,000.00 Goodfellow Brothers California, LLC Lump Sum $75,000.00 Engineer's Estimate ALL LPSM Lump Sum $200,000.00

A0180 20304-1000 REMOVAL OF STRUCTURES AND OBSTRUCTIONS (UTILITY REMOVAL)

Joseph J. Albanese Inc Lump Sum $13,600.00 AE West LLC Lump Sum $87,190.50 Granite Rock Company Lump Sum $361,777.76 Goodfellow Brothers California, LLC Lump Sum $275,000.00 Engineer's Estimate ALL LPSM Lump Sum $100,000.00

22 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0190 20402-0000 SUBEXCAVATION

Joseph J. Albanese Inc $140.00 $280,000.00 AE West LLC $20.07 $40,140.00 Granite Rock Company $60.00 $120,000.00 Goodfellow Brothers California, LLC $177.00 $354,000.00 Engineer's Estimate 2,000 CUYD $175.00 $350,000.00

A0200 20420-0000 EMBANKMENT CONSTRUCTION

Joseph J. Albanese Inc $91.00 $2,411,500.00 AE West LLC $77.09 $2,042,885.00 Granite Rock Company $85.00 $2,252,500.00 Goodfellow Brothers California, LLC $118.00 $3,127,000.00 Engineer's Estimate 26,500 CUYD $50.00 $1,325,000.00

A0210 20420-0000 EMBANKMENT CONSTRUCTION (REINFORCED SOIL SLOPE, DAVENPORT)

Joseph J. Albanese Inc $188.00 $1,259,600.00 AE West LLC $93.18 $624,306.00 Granite Rock Company $230.00 $1,541,000.00 Goodfellow Brothers California, LLC $204.00 $1,366,800.00 Engineer's Estimate 6,700 CUYD $150.00 $1,005,000.00

A0220 20420-0000 EMBANKMENT CONSTRUCTION (REINFORCED SOIL SLOPE)

Joseph J. Albanese Inc $135.00 $1,572,750.00 AE West LLC $98.66 $1,149,389.00 Granite Rock Company $135.00 $1,572,750.00 Goodfellow Brothers California, LLC $204.00 $2,376,600.00 Engineer's Estimate 11,650 CUYD $100.00 $1,165,000.00

A0230 21101-1000 ROADWAY OBLITERATION, METHOD 1

Joseph J. Albanese Inc $23.00 $10,925.00 AE West LLC $33.16 $15,751.00 Granite Rock Company $40.00 $19,000.00 Goodfellow Brothers California, LLC $20.00 $9,500.00 Engineer's Estimate 475 SQYD $30.00 $14,250.00

A0240 25101-2100 PLACED RIPRAP, METHOD B, CLASS 1

Joseph J. Albanese Inc $375.00 $72,750.00 AE West LLC $306.82 $59,523.08 Granite Rock Company $575.00 $111,550.00 Goodfellow Brothers California, LLC $525.00 $101,850.00 Engineer's Estimate 194.0 CUYD $200.00 $38,800.00

23 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0250 25101-2200 PLACED RIPRAP, METHOD B, CLASS 2

Joseph J. Albanese Inc $385.00 $105,875.00 AE West LLC $286.56 $78,804.00 Granite Rock Company $575.00 $158,125.00 Goodfellow Brothers California, LLC $620.00 $170,500.00 Engineer's Estimate 275.0 CUYD $225.00 $61,875.00

A0260 25101-2400 PLACED RIPRAP, METHOD B, CLASS 4

Joseph J. Albanese Inc $400.00 $20,000.00 AE West LLC $546.83 $27,341.50 Granite Rock Company $675.00 $33,750.00 Goodfellow Brothers California, LLC $535.00 $26,750.00 Engineer's Estimate 50.0 CUYD $300.00 $15,000.00

A0270 25201-1000 SPECIAL ROCK EMBANKMENT, MECHANICALLY-PLACED

Joseph J. Albanese Inc $200.00 $540,000.00 AE West LLC $311.32 $840,564.00 Granite Rock Company $360.00 $972,000.00 Goodfellow Brothers California, LLC $558.00 $1,506,600.00 Engineer's Estimate 2,700 CUYD $275.00 $742,500.00

A0280 25210-0000 ROCKERY

Joseph J. Albanese Inc $155.00 $232,500.00 AE West LLC $163.07 $244,605.00 Granite Rock Company $147.00 $220,500.00 Goodfellow Brothers California, LLC $130.00 $195,000.00 Engineer's Estimate 1,500 SQFT $200.00 $300,000.00

A0290 25701-0600 CONTRACTOR FURNISHED REINFORCED SOIL SLOPE DESIGN (SHOTCRETE FACED)

Joseph J. Albanese Inc Lump Sum $60,000.00 AE West LLC Lump Sum $43,141.03 Granite Rock Company Lump Sum $25,000.00 Goodfellow Brothers California, LLC Lump Sum $37,000.00 Engineer's Estimate ALL LPSM Lump Sum $50,000.00

A0300 30202-2000 ROADWAY AGGREGATE, METHOD 2

Joseph J. Albanese Inc $71.00 $1,597,500.00 AE West LLC $66.63 $1,499,175.00 Granite Rock Company $111.00 $2,497,500.00 Goodfellow Brothers California, LLC $75.00 $1,687,500.00 Engineer's Estimate 22,500 TON $90.00 $2,025,000.00

24 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0310 30202-2100 ROADWAY AGGREGATE, METHOD 2, SURFACE COURSE (CRUSHER FINES)

Joseph J. Albanese Inc $100.00 $350,000.00 AE West LLC $66.65 $233,275.00 Granite Rock Company $100.00 $350,000.00 Goodfellow Brothers California, LLC $82.00 $287,000.00 Engineer's Estimate 3,500 TON $110.00 $385,000.00

A0320 40301-0100 ASPHALT CONCRETE PAVEMENT, TYPE 1

Joseph J. Albanese Inc $175.00 $1,137,500.00 AE West LLC $265.01 $1,722,565.00 Granite Rock Company $200.00 $1,300,000.00 Goodfellow Brothers California, LLC $202.00 $1,313,000.00 Engineer's Estimate 6,500 TON $215.00 $1,397,500.00

A0330 41102-1000 PRIME COAT, METHOD 1

Joseph J. Albanese Inc $1.00 $58,000.00 AE West LLC $1.54 $89,320.00 Granite Rock Company $1.70 $98,600.00 Goodfellow Brothers California, LLC $2.00 $116,000.00 Engineer's Estimate 58,000 SQYD $1.50 $87,000.00

A0340 41105-0000 BLOTTER

Joseph J. Albanese Inc $350.00 $35,000.00 AE West LLC $61.63 $6,163.00 Granite Rock Company $400.00 $40,000.00 Goodfellow Brothers California, LLC $400.00 $40,000.00 Engineer's Estimate 100 TON $100.00 $10,000.00

A0350 50101-0800 MINOR CONCRETE PAVEMENT, REINFORCED, 8-INCH DEPTH

Joseph J. Albanese Inc $200.00 $300,000.00 AE West LLC $286.40 $429,600.00 Granite Rock Company $155.00 $232,500.00 Goodfellow Brothers California, LLC $195.00 $292,500.00 Engineer's Estimate 1,500 SQYD $300.00 $450,000.00

A0360 56601-0000 SHOTCRETE

Joseph J. Albanese Inc $2,700.00 $1,282,500.00 AE West LLC $8,702.05 $4,133,473.75 Granite Rock Company $2,925.00 $1,389,375.00 Goodfellow Brothers California, LLC $2,600.00 $1,235,000.00 Engineer's Estimate 475 SQYD $1,000.00 $475,000.00

25 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0370 60201-0400 12-INCH PIPE CULVERT (HDPE)

Joseph J. Albanese Inc $150.00 $180,000.00 AE West LLC $76.15 $91,380.00 Granite Rock Company $176.00 $211,200.00 Goodfellow Brothers California, LLC $140.00 $168,000.00 Engineer's Estimate 1,200 LNFT $250.00 $300,000.00

A0380 60201-0800 24-INCH PIPE CULVERT (METAL)

Joseph J. Albanese Inc $345.00 $69,000.00 AE West LLC $110.59 $22,118.00 Granite Rock Company $404.00 $80,800.00 Goodfellow Brothers California, LLC $450.00 $90,000.00 Engineer's Estimate 200 LNFT $275.00 $55,000.00

A0390 60201-0800 24-INCH PIPE CULVERT (HDPE)

Joseph J. Albanese Inc $225.00 $76,500.00 AE West LLC $110.61 $37,607.40 Granite Rock Company $266.00 $90,440.00 Goodfellow Brothers California, LLC $300.00 $102,000.00 Engineer's Estimate 340 LNFT $100.00 $34,000.00

A0400 60201-0900 30-INCH PIPE CULVERT (CONCRETE)

Joseph J. Albanese Inc $700.00 $28,000.00 AE West LLC $201.68 $8,067.20 Granite Rock Company $1,000.00 $40,000.00 Goodfellow Brothers California, LLC $500.00 $20,000.00 Engineer's Estimate 40 LNFT $500.00 $20,000.00

A0410 60201-1200 48-INCH PIPE CULVERT (METAL)

Joseph J. Albanese Inc $490.00 $39,200.00 AE West LLC $425.40 $34,032.00 Granite Rock Company $963.00 $77,040.00 Goodfellow Brothers California, LLC $600.00 $48,000.00 Engineer's Estimate 80 LNFT $700.00 $56,000.00

A0420 60210-0400 END SECTION FOR 12-INCH PIPE CULVERT (PLASTIC)

Joseph J. Albanese Inc $2,560.00 $107,520.00 AE West LLC $1,982.51 $83,265.42 Granite Rock Company $417.00 $17,514.00 Goodfellow Brothers California, LLC $1,600.00 $67,200.00 Engineer's Estimate 42 EACH $500.00 $21,000.00

26 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0430 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (METAL)

Joseph J. Albanese Inc $1,670.00 $10,020.00 AE West LLC $3,162.15 $18,972.90 Granite Rock Company $556.00 $3,336.00 Goodfellow Brothers California, LLC $2,000.00 $12,000.00 Engineer's Estimate 6 EACH $850.00 $5,100.00

A0440 60210-0800 END SECTION FOR 24-INCH PIPE CULVERT (PLASTIC)

Joseph J. Albanese Inc $1,740.00 $20,880.00 AE West LLC $2,064.03 $24,768.36 Granite Rock Company $585.00 $7,020.00 Goodfellow Brothers California, LLC $1,800.00 $21,600.00 Engineer's Estimate 12 EACH $500.00 $6,000.00

A0450 60210-0900 END SECTION FOR 30-INCH PIPE CULVERT (CONCRETE)

Joseph J. Albanese Inc $6,690.00 $6,690.00 AE West LLC $13,415.03 $13,415.03 Granite Rock Company $730.00 $730.00 Goodfellow Brothers California, LLC $2,700.00 $2,700.00 Engineer's Estimate 1 EACH $2,500.00 $2,500.00

A0460 60210-1200 END SECTION FOR 48-INCH PIPE CULVERT (METAL)

Joseph J. Albanese Inc $6,090.00 $6,090.00 AE West LLC $8,857.66 $8,857.66 Granite Rock Company $3,088.00 $3,088.00 Goodfellow Brothers California, LLC $6,800.00 $6,800.00 Engineer's Estimate 1 EACH $2,000.00 $2,000.00

A0470 60212-0000 ELBOW

Joseph J. Albanese Inc $1,850.00 $12,950.00 AE West LLC $1,848.90 $12,942.30 Granite Rock Company $1,200.00 $8,400.00 Goodfellow Brothers California, LLC $1,000.00 $7,000.00 Engineer's Estimate 7 EACH $1,000.00 $7,000.00

A0480 60413-0000 TRENCH DRAIN

Joseph J. Albanese Inc $325.00 $89,375.00 AE West LLC $246.52 $67,793.00 Granite Rock Company $825.00 $226,875.00 Goodfellow Brothers California, LLC $820.00 $225,500.00 Engineer's Estimate 275 LNFT $280.00 $77,000.00

27 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0490 60707-0500 LINING 24-INCH PIPE CULVERT

Joseph J. Albanese Inc $970.00 $213,400.00 AE West LLC $499.53 $109,896.60 Granite Rock Company $404.00 $88,880.00 Goodfellow Brothers California, LLC $430.00 $94,600.00 Engineer's Estimate 220 LNFT $400.00 $88,000.00

A0500 60707-0600 LINING 30-INCH PIPE CULVERT

Joseph J. Albanese Inc $1,070.00 $96,300.00 AE West LLC $624.45 $56,200.50 Granite Rock Company $825.00 $74,250.00 Goodfellow Brothers California, LLC $550.00 $49,500.00 Engineer's Estimate 90 LNFT $400.00 $36,000.00

A0510 60707-0900 LINING 48-INCH PIPE CULVERT

Joseph J. Albanese Inc $1,400.00 $56,000.00 AE West LLC $1,416.06 $56,642.40 Granite Rock Company $875.00 $35,000.00 Goodfellow Brothers California, LLC $1,200.00 $48,000.00 Engineer's Estimate 40 LNFT $600.00 $24,000.00

A0520 61102-1545 2-INCH WATERLINE (HDPE)

Joseph J. Albanese Inc $106.00 $28,090.00 AE West LLC $61.02 $16,170.30 Granite Rock Company $132.00 $34,980.00 Goodfellow Brothers California, LLC $104.00 $27,560.00 Engineer's Estimate 265 LNFT $75.00 $19,875.00

A0530 61102-2950 6-INCH WATERLINE, POLYVINYL CHLORIDE (PVC) (HDPE)

Joseph J. Albanese Inc $107.00 $1,203,750.00 AE West LLC $62.35 $701,437.50 Granite Rock Company $110.00 $1,237,500.00 Goodfellow Brothers California, LLC $100.00 $1,125,000.00 Engineer's Estimate 11,250 LNFT $100.00 $1,125,000.00

A0540 61103-1100 12-INCH ENCASEMENT PIPE, GALVANIZED STEEL

Joseph J. Albanese Inc $1,350.00 $270,000.00 AE West LLC $58.86 $11,772.00 Granite Rock Company $3,400.00 $680,000.00 Goodfellow Brothers California, LLC $1,300.00 $260,000.00 Engineer's Estimate 200 LNFT $85.00 $17,000.00

28 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0550 61104-0200 VALVE, AIR RELEASE (4-INCH)

Joseph J. Albanese Inc $9,080.00 $181,600.00 AE West LLC $13,333.69 $266,673.80 Granite Rock Company $11,000.00 $220,000.00 Goodfellow Brothers California, LLC $19,300.00 $386,000.00 Engineer's Estimate 20 EACH $2,900.00 $58,000.00

A0560 61104-0600 VALVE, GATE, 2-INCH

Joseph J. Albanese Inc $2,110.00 $6,330.00 AE West LLC $1,491.43 $4,474.29 Granite Rock Company $730.00 $2,190.00 Goodfellow Brothers California, LLC $2,100.00 $6,300.00 Engineer's Estimate 3 EACH $1,600.00 $4,800.00

A0570 61104-0700 VALVE, GATE, 4-INCH (RISER)

Joseph J. Albanese Inc $4,040.00 $169,680.00 AE West LLC $5,282.26 $221,854.92 Granite Rock Company $1,510.00 $63,420.00 Goodfellow Brothers California, LLC $4,300.00 $180,600.00 Engineer's Estimate 42 EACH $3,700.00 $155,400.00

A0580 61104-0800 VALVE, GATE, 6-INCH (BALL)

Joseph J. Albanese Inc $3,830.00 $65,110.00 AE West LLC $5,982.50 $101,702.50 Granite Rock Company $1,880.00 $31,960.00 Goodfellow Brothers California, LLC $4,400.00 $74,800.00 Engineer's Estimate 17 EACH $3,700.00 $62,900.00

A0590 61105-0000 VALVE BOX

Joseph J. Albanese Inc $365.00 $7,665.00 AE West LLC $554.67 $11,648.07 Granite Rock Company $1,200.00 $25,200.00 Goodfellow Brothers California, LLC $1,150.00 $24,150.00 Engineer's Estimate 21 EACH $1,500.00 $31,500.00

A0600 61108-1000 ADJUST WATER VALVE (CITY AIR RELEASE)

Joseph J. Albanese Inc $9,940.00 $39,760.00 AE West LLC $1,838.81 $7,355.24 Granite Rock Company $6,515.00 $26,060.00 Goodfellow Brothers California, LLC $8,800.00 $35,200.00 Engineer's Estimate 4 EACH $1,400.00 $5,600.00

29 out of 52

Project No: CA FLAP SCR T5(1)

Project Name: Monterey Bay Sanctuary Scenic Trail

Schedule: A

Schedule Type: Base

Line Item Pay Item No. Description Quantity Unit Unit Price Amount

Number

A0610 61109-5000 RELOCATE WATER METER (3/4-INCH METER & BACKFLOW)

Joseph J. Albanese Inc $21,900.00 $21,900.00 AE West LLC $7,355.25 $7,355.25 Granite Rock Company $12,600.00 $12,600.00 Goodfellow Brothers California, LLC $10,600.00 $10,600.00 Engineer's Estimate 1 EACH $2,800.00 $2,800.00

A0620 61109-5000 RELOCATE WATER METER (2-INCH METER & BACKFLOW)

Joseph J. Albanese Inc $44,200.00 $44,200.00 AE West LLC $7,355.25 $7,355.25 Granite Rock Company $15,600.00 $15,600.00 Goodfellow Brothers California, LLC $15,500.00 $15,500.00 Engineer's Estimate 1 EACH $2,000.00 $2,000.00

A0630 61501-0100 SIDEWALK, CONCRETE

Joseph J. Albanese Inc $125.00 $146,875.00 AE West LLC $107.57 $126,394.75 Granite Rock Company $96.00 $112,800.00 Goodfellow Brothers California, LLC $145.00 $170,375.00 Engineer's Estimate 1,175 SQYD $120.00 $141,000.00

A0640 61501-0800 SIDEWALK, AGGREGATE (TIMBER STEPS)

Joseph J. Albanese Inc $300.00 $45,000.00 AE West LLC $601.53 $90,229.50 Granite Rock Company $400.00 $60,000.00 Goodfellow Brothers California, LLC $615.00 $92,250.00 Engineer's Estimate 150 SQYD $200.00 $30,000.00

A0650 61901-0000 FENCE (CABLE RAILING)

Joseph J. Albanese Inc $180.00 $648,000.00 AE West LLC $125.73 $452,628.00 Granite Rock Company $170.00…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .