This document includes a request for bid for a federal-aid highway project and related questions and answers. The UT FLAP 2500(1) Taylor Mountain Road project is located approximately 6 miles north of Vernal, Utah and consists of rehabilitating, restoring, and resurfacing approximately 4.95 miles and reconstructing approximately 1.71 miles of road. Major work elements include widening the roadway, completing vertical and horizontal alignment changes to improve safety, and construction activities such as cut slopes, embankment, patching, aggregate base course, and paving. Additional improvements involve clearing vegetation, stabilizing shoulders, installing drainage structures, and updating signage and pavement markings. Significant work quantities include clearing and grubbing, embankment construction, aggregate base, full depth reclamation, and asphalt concrete pavement. Bids for the project are due by the date specified in the solicitation.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for UT FLAP 2500(1), Taylor Mountain Road

November 2, 2021

Questions Answers 1 I cannot find any trench depth information for the culverts that are in the “Full depth reclamation” area of this project.

Sheet T7 in the Plans show pipe bedding details and culvert cross sections are shown on Sheets Z1 through Z11 in the Cross Sections file.