This document contains questions and answers from a bidders' conference for the UT FLAP 2500(1) Taylor Mountain Road project solicitation. The solicitation is for a 3R and 4R road rehabilitation and resurfacing project located approximately 6 miles north of Vernal, Utah. Major work elements include widening the roadway, vertical and horizontal alignment changes, cut slopes, embankment, deep patch embankment stabilization, aggregate base course, and paving. Drainage improvements, pavement markings, and updated signing are also included. The questions and answers provide clarification on trench depths for culverts, the structural section and pay items for subexcavation and deep patch work, placement of traffic control devices and labor costs, and the availability of state lands for an asphalt plant and aggregate crushing. No bid due date or award date is specified in the document.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions and Answers during Advertisement for UT FLAP 2500(1), Taylor Mountain Road
November 2, 2021
Questions Answers 1 I cannot find any trench depth information for the culverts that are in the “Full depth reclamation” area of this project.
Sheet T7 in the Plans show pipe bedding details and culvert cross sections are shown on Sheets Z1 through Z11 in the Cross Sections file.
November 8, 2021
2 I am not seeing what we are to do in the structural section of the
Subexcavation & Deep Patch Bid Items. It doesn’t show placing & paying for Aggregate Base and Asphalt in those items and summary sheets don’t show any quantities for these materials in those locations either.
Match the pavement structural section as shown in the typical section on sheet A6 and the quantities are paid for and included as shown in the surfacing summary on sheet B5, for the respective station range and pay items.
November 17, 2021
3 RE: Traffic control devices. Where do I put labor for our maintainer and also an assistant when needed?
Refer to the following Sections in the FP-14: 635.01 "..work consists of furnishing, installing, maintaining….", 635.04 General "Furnish, install, and maintain temporary traffic control devices…."
November 18, 2021
4 Are we allowed to use the State lands gravel pit on US-40 just east of the Green River Bridge in Jensen, Utah to set an asphalt plant and crush the needed aggregate?
No government furnished material sources were identified/provided for this project. Use of the State lands gravel pit on US-40 would need to be obtained by the contractor from the owner/operator/agency/etc. and materials produced the responsibility of the contractor to meet project specifications. Land not identified in the plans requires owner consent and proof of environmental compliance prior to use during construction and owner acceptance of final (post construction) conditions for contract closeout.