This document contains questions and answers from an advertisement for the SD TIG BIA 10(1) Lower Brule Road project. The project involves reconstructing 13.54 miles of roadway on the Lower Brule Sioux Tribe Reservation, including safety improvements, pulverization, subgrade reconditioning, widening, earthwork, drainage, aggregate base, and hot-asphalt concrete pavement. The fixed-price variable scope contract value is $16.6 million. Contractors are responsible for securing permissions and clearances for any borrow or waste areas outside construction limits, and for addressing soft subgrade areas prior to paving. Clarification was provided on bend angles for reinforced concrete pipe culverts. The pavement structural sections specified supersede references to unrelated tables.

View the file

Other files

File Type Posted
Bid Opening Summary.pdf PDF
A004.pdf PDF
QnA 10.26.2020.pdf PDF
QnA 10.22.2020.pdf PDF
A003.pdf PDF
A002.pdf PDF
QnA 10.20.2020.pdf PDF
QnA 10.19.2020.pdf PDF
A001.pdf PDF
SD TIG BIA10(1) Xsections.pdf PDF
SD TIG BIA 10(1) Lower Brule - V2 tech memo-FINAL.pdf PDF
SD TIG BIA10(1) Supplemental Package and BIA Plans 8-24-2020.pdf PDF
6982AF20B000025.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers during Advertisement for

SD TIG BIA 10(1) Lower Brule Road

October 16, 2020

Questions Answers

1 On sheet A2 of the plans that shows the FDR Typical Section, note 7 states “Spread pulverized material and pave across the available width on all curves. Add aggregate base if necessary”. My question/concern regarding this note is twofold. First, who determines if additional aggregate base is necessary? Second, how is the contractor supposed to figure these possible additional costs of additional aggregate base?

The contractor is required to provide aggregate base to meet the lines and grades shown in the plans.

Within the FDR section there are some segments in which the existing pavement width is slightly narrower (12 inches or less) than the proposed width.

2 I realize that the granular base material gets primed before the winter of 2021/2022, but undoubtedly there will be soft/unstable areas that show up in the spring of 2022. Is the contractor responsible for these soft/unstable areas?

Yes, the contractor is responsible for a subgrade that meets the specifications prior to paving.

3 Is there a maximum % amount that the Mobilization bid item amount can be compared to the overall total bid amount which in this case is $16.6M?

There is no maximum % amount for the Mobilization bid item. However, all bids are reviewed for unbalanced pricing and a bid may be rejected if it poses an unacceptable risk to the Government. See

FAR 15.404-1(g). The payment structure contained in Section 151 Mobilization should be considered before a determination of the mobilization amount is made.

4 At the pre-bid meeting last week stated that in order for the earthwork quantities to balance so that the contractor does not have to go far to either obtain dirt or waste dirt he will be able to go outside the ROW. Is this correct?

If so, will there be issues associated with whether or not this material will meet specification?

What about an archeological study in these possible borrow and waste areas

Will it be up to the contractor to deal with the landowner?

Per Section 111 of the Special Contract

Requirements, the contractor can utilize on-site borrow or waste sites that are within the contract limits of construction, but outside the limits of the proposed 4R work, to optimize earthwork mass haul.

Per the Geotechnical/Pavements report, the materials underlying the route are generally suitable for embankment construction.

The contractor is responsible for securing necessary permissions and environmental clearances on any borrow or waste areas outside the construction limits of the project.

5 Station 674+55.00 – 66.70’ LT Install 18” x 78.00’ CMP Culvert, 16 gage with 2 safety ends w/o bars

Is missing off of table?

This item is missing off the table and would increase the quantities for 18” culvert, ITEM NO. 60201-0600

78 LNFT and ITEM NO. 60210-0600 Safety Ends end sections, 2 EACH. This will be included in a future amendment.

6 Station 238+63.00 shows on plans 2 -30 degree bends, table say 20 degree bends.

Also couldn’t find a detail or spec on how you want the RCP – CMP transition adaptor

The Pipe Section, sheet 159, is correct showing 20 degree bends.

Pipe culvert plots are required by the specifications before ordering materials and bend angles or culvert lengths may be adjusted based on field conditions.

There are commercially available transitions between

RCP to CMP adaptor fittings.

7 I have a question on the pavement sections in this document. The first pavement section references TX140. See table

The second pavement section references TX7. See table.

These tables are not applicable to the structural section in the plans and specs and are superseded by the Technical Memorandum, Addendum to BIA

Geotechnical Report, dated August 14, 2020. The pavement section is based on the structural section in the typical sections, plans and specs. Sheet A5 of the plans details the locations where stabilization geogrid is specified.