Bid Opening Summary .pdf

PDF 191 KB Posted

Attached to
CA YOSE 17(4) & 941(1) Tioga Road & Tuolumne Meadows & Tenaya Lake Parking
Solicitation number
6982AF20B000013
Issued by

About this file

This bid opening summary documents the bids received for the Tioga Road & Tuolumne Meadows Project. Four contractors submitted bids by the August 28, 2020 deadline to complete roadway resurfacing and restoration work along 12 miles of Tioga Pass Road in Yosemite National Park, and to reconfigure and expand parking areas in Tuolumne Meadows and at Tenaya Lake. The bids ranged from $30.5 million to $46.7 million. Granite Construction provided the lowest bid at $35.6 million, while George Reed Inc. submitted the highest bid. The engineer's estimate for the project was $30.6 million. Work is anticipated to begin in August 2020 and be completed by October 2022. It will involve asphalt paving, concrete work, utility relocations, excavation, and parking area improvements across culturally and environmentally sensitive park lands.

This federal contract opportunity posted by the Department of Transportation Federal Highway Administration involves resurfacing Tioga Road and restoring parking areas in Yosemite National Park. Work includes repaving 12 miles of road, expanding parking in Tuolumne Meadows and Tenaya Lake, and upgrading facilities. The estimated value is $25-35 million. Bids were due in August 2020, with construction from then through October 2022. The project increases formal parking and improves safety at busy sites that see over 600,000 annual visitors. Experience with similar national park projects is required. Work components comprise paving, drainage, utilities, signage, and landscape restoration. The solicitation is a full and open competition.

View the file

Other files

File Type Posted
Bid Tabs - CA FTNP NPS YOSE 17(4) 941(1).pdf PDF
Amendment A005 .pdf PDF
QnA - August 27 2020.pdf PDF
Interested Vendor List 8 26 2020 Rev 1.pdf PDF
Interested Vendor List 8 26 2020.pdf PDF
Amendment A004.pdf PDF
QnA - August 25 2020.pdf PDF
Amendment A003 .pdf PDF
QnA - August 21 2020.pdf PDF
Amendment A002 - Wage Decision.pdf PDF
Interested Vendor List 8 19 2020.pdf PDF
QnA - August 19 2020 .pdf PDF
QnA - August 18 2020 Rev1.pdf PDF
Amendment A001 .pdf PDF
QnA - August 18 2020 .pdf PDF
QnA 8 12 2020 Tioga.pdf PDF
Interested Vendors List 8 12 2020.pdf PDF
QnA 8 3 2020 Tioga.pdf PDF
CA YOSE 17(4) 941(1) Plans.pdf PDF
Tioga Plans Part 2 of 3 - E through U Sections.pdf PDF
Plans Part 3 of 3 - V and W Sections.pdf PDF
CA PRA YOSE 17(3) Yosemite National Park Pavements Report.pdf PDF
Tuolumne Meadows Parking - FINAL Geotech Report_20200710.pdf PDF
6982AF20B000013 IFB.pdf PDF
Plans - Part 1 of 3 A through D sections.pdf PDF
Plans Part 3 of 3 - V and W Sections.pdf PDF
YOSE17(4)-Justification for Other than Full and Open Competition_Redacted.pdf PDF
CA FTBR FSTR(2) Final Hydrology and Hydraulics Recommendations Report.pdf PDF
Plans Part 2 of 3 - E through U Sections.pdf PDF
CA FTBR FSTR(2) Final Geotech Report.pdf PDF
fp14.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Opening Summary

Project Name: Tioga Road & Tuolumne Meadows Project Number: CA FTNP NPS YOSE 17(4) 941(1) Bid Opening Date: 8/28/2020 Time: 2:00 p.m. MST Bid Opening Location: Lakewood, CO Bid Opening Officer: Jorey Deml

Amendments: (1) 08/18/2020 (2) _8/21/2020__(3) 8/24/2020 (4) 8/26/2020 (5) 8/27/2020

Bidder’s Name Part A Option X Option Y BID TOTAL 1.Granite Construction

$33,058,866.00 $642,261.00 $1,850,535.00 $35,551,662.00, 2.Steve Manning Construction

$31,686,924.94 $1,740,300.00 $3,368,210.00 $36,795,434.94

3. George Reed Inc.

$42,295,902.08 $1,253,948.50 $3,164,740.75 $46,714,591.33

4. Goodfellow Bros.

$30,517,452.00 $793,683.00 $2,336,630.00 $33,647,765.00

Engineer’s Estimate

$27,600,518.50 $956,000.00 $2,051,581.50 $30,608,100.00

File details come from the government source that posted it. Updated .