Pre-Proposal Meeting Minutes.pdf
PDF 86 KB Posted
- Attached to
- MMAC Operations and Maintenance Services Federal contract opportunity
- Solicitation number
- 6973GH-22-R-00025
About this file
The document summarizes pre-proposal meeting minutes for a solicitation seeking operations and maintenance services. The solicitation was issued by the Department of Transportation Federal Aviation Administration for services at the Mike Monroney Aeronautical Center. Services include grounds maintenance, maintenance of air handling units and other building equipment, and material handling equipment. An amendment to the solicitation will correct items discussed and provide an attendee list and minutes. Questions asked at the site visit will also be answered as part of the amendment. The period of performance is for a one year base period and four one-year options. Proposals are due within 90 days and there will be a 30 day transition period between contracts.
View the file
Other files for this federal contract opportunity
Show all 22
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPERATIONS AND MAINTENANCE SERVICES
6973GH-22-R-00025
PRE-PROPOSAL CONFERENCE
MEETING MINUTES
9:30 – 9:45 INTRODUCTIONS
9:40 – 9:50 UPCOMING CHANGES SIR AMENDMENT
9:55 – 11:00 SITE WALKTRHOUGH
THE ACQUISITION METHOD BEING USED FOR THIS PROCUREMENT IS BEST
VALUE FULL TRADE-OFF SOURCE SELECTION PROCEDURES. FOR SPECIFIC
INFORMATION REGARDING EVALUATION OF PROPOSALS, REFER TO
SECTION M OF THE SIR
UPCOMING CHANGES VIA AMENDMENT
A. NO PAGE LIMITATION FOR SUBMISSION OF VOLUME II – FACTOR 3
PAST PERFORMANCE ONLY. FACTORS 1 AND 2 WILL REMAIN AT A 75
PAGE LIMIT
B. CORRECT PROVISION 3.2.2.3-20 TO REFLECT CYNTHIA COOPER AND
ANDRE CASIANO AS POC’S FOR PROPOSAL SUBMISSION
C. REFLECT A MINIMUM OFFER ACCEPTANCE PERIOD OF 90 DAYS AND
THIS WILL BE UPDATED WITH AN AMENDMENT VIA 3.2.2.3-2
MINIMUM OFFER ACCEPTANCE PERIOD
D. CLIENT AUTHORIZATION LETTER WILL BE ADDED AS ATTACHMENT
10 AS IT WAS INADVERTANTLY LEFT OFF OF THE SIR
E. TRANSITION PERIOD IS 30 DAYS NOT 45 DAYS. SIR SECTION F.1
REFLECTS A PERIOD OF 45 DAYS WHICH IS INCORRECT.
IN ORDER TO BE FAIR TO ALL COMPETITORS, INCLUDING THOSE NOT
PRESENT TODAY, ATTENDEES WERE INSTRUCTED TO PLEASE SUBMIT
QUESTIONS IN WRITING TO CYNTHIA COOPER AND ANDRE CASIANO VIA
EMAIL AT CYNTHIA.COOPER@FAA.GOV AND ANDRE.CASIANO@FAA.GOV.
ATTENDEES WERE REMINDED THAT EVEN IF THERE ARE DISCUSSIONS AS
A RESULT OF TODAY’S MEETING, THE SIR PACKAGE (INCLUDING ALL
ATTACHMENTS) REMAINS UNCHANGED UNLESS IT IS FORMALLY
CHANGED BY A SOLICITATION AMENDMENT.
RFP UPDATE: SIR AMENDMENT 0001 WILL BE ISSUED WITHIN THE NEXT
FEWS DAYS TO CORRECT ITEMS A, B, C, D, AND E ABOVE AS WELL AS
PROVIDE THE LIST OF ATTENDEES AND MINUTES OF THE PRE PROPOSAL
CONFERENCE.
ATTENDEES WERE SHOWN THE GROUNDS MAINTANENCE BUILDING
WHICH INCLUDED AN OPPORTUNITY TO VIEW GFE. A LIST OF GFP WILL BE
PROVIDED AND POSTED TO SAM.GOV
ATTENDEES WERE SHOWN SOME OF THE AIR CHILLER UNITS AT THE MAIN
OPERATIONS AND MAINTANENCE BUILDING. THE FAA CAMPUS DOES NOT
HAVE STANDARZATION OF THESE PIECES OF EQUIPMENT. SOME
BUILDINGS MAY HAVE A DIFFERENT MAKE/MODEL OF AIR HANDLERS
ATTENDEES WERE SHOWN THE CCMS ROOM. THE AUTOMATION
SOFTWARE USED AT MMAC IS JOHNSON CONTROLS INC. METASYS
ATTENDEES WERE SHOWN SOME OF AIR HANDLERS AND BOILERS IN THE
BASEMENT OF THE MAIN OPERATIONS AND MAINTANENCE BUILDING
ATTENDEES WERE SHOWN THE AREA WHERE MAINTENANCE IS
PERFORMED ON MATERIAL HANDLING EQUIPMENT AND ATVs
QUESTIONS POSED AT THE SITE VISIT WHICH WILL BE INCLUDED IN THE
POSTED Q&A
1. ARE AIR HANDLING UNIT FILTERS MERV 13 RATED?
2. WHAT IS THE CURRENT WORK ORDER SYSTEM BEING UTILIZED?
3. IS MIXING FOR PESTICIDES DONE ON-SITE AT THE MMAC?
4. HOW IS INITIAL EQUIPMENT HANDOVER DONE FOR NEW
EQUIPMENT BEING ADDED TO THE O&M SERVICES CONTRACT FOR
MAINTANENCE
5. ARE THERE OTHER BUILDINGS WHERE O&M CONTRACTORS WILL
WORK OUT OF, OR IS BUILDING 15 THE ONLY AREA?
6. ARE THERE SPECIAL ACCCESS REQUIRMENTS FOR THE FLIGHTLINE
ACCESS?
7. DO ALL O&M CONTRACT EMPLOYEES REQUIRE FLIGHTLINE
ACCESS?
8. ARE THERE ANY GSA LEASED VEHICLES UNDER THIS CONTRACT
AND IF SO, DOES THE CONTRACTOR NEED TO COORDINATE
MAINTANENCE SERVICE FOR THEM?
9. ARE THERE ANY SATELLITE LOCATIONS OUTSIDE OF THE MIKE
MONRONEY AERONATICAL CENTER THAT SERVICE MUST BE
PROVIDED AT?
ATTENDEES:
Name of Company: Chugach Government Solutions Name and Title: Jeremiah Gideon, Capture Manager
Name of Company: King & George, LLC Name and Title: Billy Miller, Dir. Project Controls
Name of Company: Southwest Facility Support Services (SWFS), LLC Name and Title: Quetta Fritsch, Managing Partner
Name of Company: Jones Lang Lasalle (JLL) Name and Title: De’Von Williams – Executive Director
GOVERNMENT ATTENDEES:
Cynthia Cooper, Contracting Officer, AAQ-731
Andre Casiano, Contract Specialist, AAQ-731
Kyle Daniel, Technical Rep, AMP-300