Pre-Proposal Meeting Minutes.pdf

PDF 86 KB Posted

Attached to
MMAC Operations and Maintenance Services Federal contract opportunity
Solicitation number
6973GH-22-R-00025
Issued by
Department of Transportation Federal Aviation Administration Franchise Acquisition Services

About this file

The document summarizes pre-proposal meeting minutes for a solicitation seeking operations and maintenance services. The solicitation was issued by the Department of Transportation Federal Aviation Administration for services at the Mike Monroney Aeronautical Center. Services include grounds maintenance, maintenance of air handling units and other building equipment, and material handling equipment. An amendment to the solicitation will correct items discussed and provide an attendee list and minutes. Questions asked at the site visit will also be answered as part of the amendment. The period of performance is for a one year base period and four one-year options. Proposals are due within 90 days and there will be a 30 day transition period between contracts.

View the file

Other files for this federal contract opportunity

Other files attached to MMAC Operations and Maintenance Services, newest first.
File Type Posted
6973GH-22-R-00025 Amendment 0003.pdf PDF
Attachment 02 Section B Supplies or Services Price Cost Rev 1 7.11.22.xlsx XLSX spreadsheet
Attachment 12 PM Equipment 7-11-22.pdf PDF
Attachment 14 Metasys Equipment 7-11-22.pdf PDF
6973GH-22-R-00025 Amendment 0002.pdf PDF
Attachment 11 Building list 7-11-22.pdf PDF
Cost Principles.pdf PDF
Attachment 01 Performance Work Statement Rev 2 7-11-22.pdf PDF
Attachment 13 Grounds Map 7-11-22.pdf PDF
QA .1 6973GH-22-R-00025 OM Services.pdf PDF
6973GH-22-R-00025 Amendment 0001.pdf PDF
Attachment 10 Client Authorization Letter.pdf PDF
Attachment 01 Perfomance Work Statement 10292021.pdf PDF
Attachment 07 Wage Determination 1986-8773 Revision 46.pdf PDF
Attachment 09 Wage Determination 2005-5315 Revision 17.pdf PDF
SIR 6973GH-22-R-00025.pdf PDF
Attachment 02 Section B Supplies or Services Price Cost.xlsx XLSX spreadsheet
Attachment 06 United Association of Journeyman and Apprentices of the Plumbing and Pipe Fitting Union.pdf PDF
Atttachment 08 Wage Determination OK22-0049.pdf PDF
Attachment 03 Operations and Maintenance Past Performance Survey.docx DOCX document
Attachment 04 IBEW CBA 2022-2025.pdf PDF
Attachment 05 International Association of Machinists and Aerospace Workers.pdf PDF
Show all 22

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPERATIONS AND MAINTENANCE SERVICES

6973GH-22-R-00025

PRE-PROPOSAL CONFERENCE

MEETING MINUTES

9:30 – 9:45 INTRODUCTIONS

9:40 – 9:50 UPCOMING CHANGES SIR AMENDMENT

9:55 – 11:00 SITE WALKTRHOUGH

THE ACQUISITION METHOD BEING USED FOR THIS PROCUREMENT IS BEST

VALUE FULL TRADE-OFF SOURCE SELECTION PROCEDURES. FOR SPECIFIC

INFORMATION REGARDING EVALUATION OF PROPOSALS, REFER TO

SECTION M OF THE SIR

UPCOMING CHANGES VIA AMENDMENT

A. NO PAGE LIMITATION FOR SUBMISSION OF VOLUME II – FACTOR 3

PAST PERFORMANCE ONLY. FACTORS 1 AND 2 WILL REMAIN AT A 75

PAGE LIMIT

B. CORRECT PROVISION 3.2.2.3-20 TO REFLECT CYNTHIA COOPER AND

ANDRE CASIANO AS POC’S FOR PROPOSAL SUBMISSION

C. REFLECT A MINIMUM OFFER ACCEPTANCE PERIOD OF 90 DAYS AND

THIS WILL BE UPDATED WITH AN AMENDMENT VIA 3.2.2.3-2

MINIMUM OFFER ACCEPTANCE PERIOD

D. CLIENT AUTHORIZATION LETTER WILL BE ADDED AS ATTACHMENT

10 AS IT WAS INADVERTANTLY LEFT OFF OF THE SIR

E. TRANSITION PERIOD IS 30 DAYS NOT 45 DAYS. SIR SECTION F.1

REFLECTS A PERIOD OF 45 DAYS WHICH IS INCORRECT.

IN ORDER TO BE FAIR TO ALL COMPETITORS, INCLUDING THOSE NOT

PRESENT TODAY, ATTENDEES WERE INSTRUCTED TO PLEASE SUBMIT

QUESTIONS IN WRITING TO CYNTHIA COOPER AND ANDRE CASIANO VIA

EMAIL AT CYNTHIA.COOPER@FAA.GOV AND ANDRE.CASIANO@FAA.GOV.

ATTENDEES WERE REMINDED THAT EVEN IF THERE ARE DISCUSSIONS AS

A RESULT OF TODAY’S MEETING, THE SIR PACKAGE (INCLUDING ALL

ATTACHMENTS) REMAINS UNCHANGED UNLESS IT IS FORMALLY

CHANGED BY A SOLICITATION AMENDMENT.

RFP UPDATE: SIR AMENDMENT 0001 WILL BE ISSUED WITHIN THE NEXT

FEWS DAYS TO CORRECT ITEMS A, B, C, D, AND E ABOVE AS WELL AS

PROVIDE THE LIST OF ATTENDEES AND MINUTES OF THE PRE PROPOSAL

CONFERENCE.

ATTENDEES WERE SHOWN THE GROUNDS MAINTANENCE BUILDING

WHICH INCLUDED AN OPPORTUNITY TO VIEW GFE. A LIST OF GFP WILL BE

PROVIDED AND POSTED TO SAM.GOV

ATTENDEES WERE SHOWN SOME OF THE AIR CHILLER UNITS AT THE MAIN

OPERATIONS AND MAINTANENCE BUILDING. THE FAA CAMPUS DOES NOT

HAVE STANDARZATION OF THESE PIECES OF EQUIPMENT. SOME

BUILDINGS MAY HAVE A DIFFERENT MAKE/MODEL OF AIR HANDLERS

ATTENDEES WERE SHOWN THE CCMS ROOM. THE AUTOMATION

SOFTWARE USED AT MMAC IS JOHNSON CONTROLS INC. METASYS

ATTENDEES WERE SHOWN SOME OF AIR HANDLERS AND BOILERS IN THE

BASEMENT OF THE MAIN OPERATIONS AND MAINTANENCE BUILDING

ATTENDEES WERE SHOWN THE AREA WHERE MAINTENANCE IS

PERFORMED ON MATERIAL HANDLING EQUIPMENT AND ATVs

QUESTIONS POSED AT THE SITE VISIT WHICH WILL BE INCLUDED IN THE

POSTED Q&A

1. ARE AIR HANDLING UNIT FILTERS MERV 13 RATED?

2. WHAT IS THE CURRENT WORK ORDER SYSTEM BEING UTILIZED?

3. IS MIXING FOR PESTICIDES DONE ON-SITE AT THE MMAC?

4. HOW IS INITIAL EQUIPMENT HANDOVER DONE FOR NEW

EQUIPMENT BEING ADDED TO THE O&M SERVICES CONTRACT FOR

MAINTANENCE

5. ARE THERE OTHER BUILDINGS WHERE O&M CONTRACTORS WILL

WORK OUT OF, OR IS BUILDING 15 THE ONLY AREA?

6. ARE THERE SPECIAL ACCCESS REQUIRMENTS FOR THE FLIGHTLINE

ACCESS?

7. DO ALL O&M CONTRACT EMPLOYEES REQUIRE FLIGHTLINE

ACCESS?

8. ARE THERE ANY GSA LEASED VEHICLES UNDER THIS CONTRACT

AND IF SO, DOES THE CONTRACTOR NEED TO COORDINATE

MAINTANENCE SERVICE FOR THEM?

9. ARE THERE ANY SATELLITE LOCATIONS OUTSIDE OF THE MIKE

MONRONEY AERONATICAL CENTER THAT SERVICE MUST BE

PROVIDED AT?

ATTENDEES:

Name of Company: Chugach Government Solutions Name and Title: Jeremiah Gideon, Capture Manager

Name of Company: King & George, LLC Name and Title: Billy Miller, Dir. Project Controls

Name of Company: Southwest Facility Support Services (SWFS), LLC Name and Title: Quetta Fritsch, Managing Partner

Name of Company: Jones Lang Lasalle (JLL) Name and Title: De’Von Williams – Executive Director

GOVERNMENT ATTENDEES:

Cynthia Cooper, Contracting Officer, AAQ-731

Andre Casiano, Contract Specialist, AAQ-731

Kyle Daniel, Technical Rep, AMP-300