About this file

This document includes a Statement of Work and related Federal Contract Opportunity notice. The Statement of Work requires the contractor to provide design, excavation, erection, installation, and removal services for the replacement of two 100-foot self-supporting steel antenna towers at the Teterboro RTR site. Services include tower and foundation design, permitting, excavation of foundations, erecting towers with associated platforms and equipment, installing overhead ice bridges and cabling between the towers and shelter. The contractor must also remove the existing guyed towers and foundations down to one foot below grade, and dispose of materials in accordance with regulations.

The related Federal Contract Opportunity is a Screening Information Request seeking offers for the tower replacement work described. The solicitation will result in a firm-fixed-price construction contract awarded by the Federal Aviation Administration. A mandatory site visit will be held on August 14th, and all questions must be submitted by August 26th. Offers are due by September 5th and must be registered on SAM.gov by that date. The FAA reserves the right to communicate with offerors and award is not a commitment by the government.

TEB Statement of Work (pdf)

View the file

Other files for this federal contract opportunity

Other files attached to SCREENING INFORMATION REQUEST/REQUEST FOR OFFER RTR Tower Replacement in Teterboro, NJ, newest first.
File Type Posted
Experience Information Form.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
Solicitation Amendment 6973GH-19-R-00230 0002.pdf PDF
WAGE DETERMINATION NJ20180026.pdf PDF
Performance Bond.pdf PDF
site visit QA.pdf PDF
TEB tower replacement spec final.pdf PDF
Solicitation Amendment 6973GH-19-R-00230 0001.pdf PDF
TEB RTR Tower Project Drawings.pdf PDF
6973GH-19-R-00230.pdf PDF
Payment Bond.pdf PDF
Geotech Report_Teterboro Airport1.pdf PDF
ACM and LBP inspection.pdf PDF
site visit QA.pdf PDF
Experience Information Form.pdf PDF
TEB Statement of Work.pdf PDF
Payment Bond.pdf PDF
6973GH-19-R-00230.pdf PDF
Geotech Report_Teterboro Airport1.pdf PDF
TEB tower replacement spec final.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
Performance Bond.pdf PDF
Solicitation Amendment 6973GH-19-R-00230 0001.pdf PDF
TEB RTR Tower Project Drawings.pdf PDF
WAGE DETERMINATION NJ20180026.pdf PDF
6973GH-19-R-00230.pdf PDF
Payment Bond.pdf PDF
Experience Information Form.pdf PDF
Geotech Report_Teterboro Airport1.pdf PDF
WAGE DETERMINATION NJ20180026.pdf PDF
Performance Bond.pdf PDF
TEB Statement of Work.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
TEB RTR Tower Project Drawings.pdf PDF
TEB tower replacement spec final.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PR # ES-19-01110

Teterboro RTR Tower Replacement Teterboro, NJ

The Contractor shall provide the necessary labor, materials, supplies, and equipment to:

Provide design for tower and foundations for two 100 ft. high self-supporting steel antenna towers using provided soil boring data. NOTE: Design must include all items necessary to meet Port Authority of NY and NJ (PANYNJ) Tenant Construction and Alteration Process (TCAP)

Prepare all forms and documents necessary for compliance with the PANYNJ TCAP to the FAA for signature. Submit and obtain a permit to build from PANYNJ. Pay all fee necessary for this process. See PANYNJ website for Tenant Construction Review Manual for design and process requirements.

Excavate and install concrete foundations for the two antenna towers, Provide and erect the antenna towers along with all associated items including: platform, railings, climbing ladder, wave-guide ladder, LMR-900 cables, antenna mounts, grounding and lightning protection, obstruction lighting, etc.

Provide and install overhead ice bridge from each tower to the RTR shelter.

Install LMR-900 coax cables (GFM) from the RTR shelter to the new towers;

Provide and install 2 ground bars and 24 polyphasers inside the RTR shelter.

Perform site work as required.

Remove the existing two existing steel 100-ft high-guyed towers and all associated guys and concrete foundations (to 1ft below grade). Communications towers tested positive for Lead Base Paint use proper methods for removal and recycle tower per all Federal, State, and Local regulations. Remove all communication cables and antennas from the existing towers.