Solicitation Amendment 6973GH-19-R-00230 0002.pdf

PDF 1 MB Posted

Attached to
SCREENING INFORMATION REQUEST/REQUEST FOR OFFER RTR Tower Replacement in Teterboro, NJ Federal contract opportunity
Solicitation number
6973GH-19-R-00230
Issued by
Department of Transportation Federal Aviation Administration Aeronautical Center

About this file

This solicitation amendment extends the deadline for proposals for a firm-fixed-price construction contract to replace two RTR towers in Teterboro, New Jersey. The Federal Aviation Administration seeks proposals by September 7, 2019 to remove the existing towers and install replacement towers with six antenna mounts each. Offerors must acknowledge receipt of this amendment extending the deadline. The amendment provides an asbestos and lead-based paint inspection report, clarifies that twelve runs of LMR-900 cable will be government-furnished material, and requires the contractor to design tower foundations using supplied geotechnical data. The period of performance is 240 calendar days, with designs due 120 days after the notice to proceed and construction to be completed 120 days following design completion.

Solicitation Amendment 6973GH-19-R-00230 0002 (pdf)

View the file

Other files for this federal contract opportunity

Other files attached to SCREENING INFORMATION REQUEST/REQUEST FOR OFFER RTR Tower Replacement in Teterboro, NJ, newest first.
File Type Posted
Experience Information Form.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
WAGE DETERMINATION NJ20180026.pdf PDF
Performance Bond.pdf PDF
Geotech Report_Teterboro Airport1.pdf PDF
ACM and LBP inspection.pdf PDF
site visit QA.pdf PDF
TEB tower replacement spec final.pdf PDF
Solicitation Amendment 6973GH-19-R-00230 0001.pdf PDF
TEB Statement of Work.pdf PDF
TEB RTR Tower Project Drawings.pdf PDF
6973GH-19-R-00230.pdf PDF
Payment Bond.pdf PDF
site visit QA.pdf PDF
Experience Information Form.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
Performance Bond.pdf PDF
Solicitation Amendment 6973GH-19-R-00230 0001.pdf PDF
TEB RTR Tower Project Drawings.pdf PDF
WAGE DETERMINATION NJ20180026.pdf PDF
TEB Statement of Work.pdf PDF
Payment Bond.pdf PDF
6973GH-19-R-00230.pdf PDF
Geotech Report_Teterboro Airport1.pdf PDF
TEB tower replacement spec final.pdf PDF
6973GH-19-R-00230.pdf PDF
TEB RTR Tower Project Drawings.pdf PDF
TEB tower replacement spec final.pdf PDF
Payment Bond.pdf PDF
Experience Information Form.pdf PDF
Geotech Report_Teterboro Airport1.pdf PDF
WAGE DETERMINATION NJ20180026.pdf PDF
Performance Bond.pdf PDF
TEB Statement of Work.pdf PDF
Contractor's Release Form DOT F 4220.4.doc DOC document
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

(SF-30) FAA Template No. 11 (8/97)

FACILITY CODE

9A. AMENDMENT OF SOLICITATION

NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

OMB Control No. 2120-0595

p. 1

The purpose of this amendment is to extend the date for receipt of proposals to October 7, 2019, and to make the following clarifications/updates to the existing SIR:

1) An ACM and LBP inspection report was recently obtained for the facility; see attachment.

2) 12 runs of LMR-900 cable shall be installed from the ground bar at each tower to the ground bar at the building. The LMR-900 is GFM. All other materials to install the LMR-900 shall be furnished by the contractor. Contractor shall provide clips and hangers to accommodate LMR-900 cables.

3) The tower is a 6 arm tower with 6 antenna mounts.

4) The contractor shall provide foundation design including any pile design using data from the provided Geo technical report. The contractor may propose alternated foundation design and submit for approval.

5) The period of performance for this project will be as follows: The designs will be completed no later than 120 calendar days after the notice to proceed.

Following design completion, the building and final construction shall be completed 120 calendar days after the notice to proceed following completion of the design portion.

topmostSubform[0]:
Page1[0]:
AmendmentNo[0]: 0002
Code[0]:
Code[1]:
AccountingData[0]:
A13[0]:
C13[0]:
D13[0]:
NameandTitleSigner[0]:
NameandTitleOfficer[0]: Janice K Hammonds
Description[0]:
FacilityCode[0]:
Code[2]:
IssuedBy[0]: AAQ-722 DIVERSIFIED FRANCHISE ACQ

FAA AERONAUTICAL CENTER

OKLAHOMA CITY OK 73125

NameandAddress[0]:
AdministeredBy[0]:
ContractIDCode[0]:
ReqNumber[0]: ES-19-01110
AmendmentNo[1]: 6973GH-19-R-00230
ModificationNo[0]:
ProjectNo[0]:
Page[0]: 1
Pages[0]: 1
EffectiveDate[0]: 9/05/2019
Dated9B[0]: 08/02/2019
Dated10B[0]:
CheckBox9[0]: 1
CheckBox10[0]: Off
CheckBox11[0]: 1
CheckBox13A[0]: Off
CheckBox13B[0]: Off
CheckBox13C[0]: Off
CheckBox13D[0]: Off
IsNot[0]: Off
Is[0]: Off
Extended[0]: 1
NotExtended[0]: Off
2019-09-05T10:05:52-0500
Janice Kay Hammonds
DateSigned[0]:
DateSigned[1]: 9.5.19
Copies[0]: 1
CopiesReturned[0]:

File details come from the government source that posted it. Updated .