This document is an Amendment (No. 0002) to a federal contract solicitation for the Mid-Atlantic Region Construction Multiple Award Task Order Contract (MATOC) issued by the Federal Highway Administration's Eastern Federal Lands Highway Division. The amendment serves three primary purposes: 1) replace sheet R09 in the project plans, 2) provide a summary of bidder questions and clarifications, and 3) incorporate a Transportation Acquisition Regulation (TAR) clause regarding electronic submission of payment requests.
The contract involves construction work at the Chesapeake and Ohio Canal National Historical Park, specifically focusing on work at the Four Locks Tunnel. The amendment clarifies that concrete slab pouring can be split into multiple pours throughout the 113' tunnel with multiple construction joints. The proposal due date remains August 29, 2025, at 2:00 PM EDT. The solicitation includes detailed technical specifications for concrete joint details, reinforcement configurations, and installation requirements, with specific notes addressing joint sealant, bond breakers, and construction methodologies.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7325R000073 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1408/22/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/30/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Mid-Atlantic Region Construction MATOC:
The purpose of this Amendment is to:
1. Replace sheet R09 in the Plans.
2. Provide a summary of responses to questions and clarifications asked by potential bidders.
3. Incorporate Transportation Acquisition Regulation (TAR) Clause 1252.232-70 Electronic
Submission of Payment Requests (DEVIATION) (AUG 2025) into Section I of the solicitation in full text.
Continued ...
15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 7
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
693C7325R000073/0002
The proposal due date of August 29, 2025, by 2pm
EDT remains the same.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Amendment No. 0002
Info Page 1 of 1
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Project MD NP CHOH 235(2), 242(1), ETC.
Solicitation: 693C73-25-R-000073
The purpose of this Amendment is to:
1. Replace sheet R09 in the Plans.
2. Provide a summary of responses to questions and clarifications asked by potential bidders.
3. Incorporate Transportation Acquisition Regulation (TAR) Clause 1252.232-70 Electronic Submission of Payment Requests (DEVIATION) (AUG 2025) into Section I of the solicitation in full text.
The proposal due date of August 29, 2025, by 2pm EDT remains the same.
MDE ESC No. 25-SF-0019, MDE WW No. 24-NT-3145 MDE ESC No. 25-SF-0006, MDE WW No. 24-NT-3146 MDE ESC No. 25-SF-0020, MDE WW No. 24-NT-3144 PMIS No. 263673 NPS Drwg No. 412/191616
CRCP
I
Ci. Joint ----5:
1"
Silicone joint sealant (See Note 4)
Asphalt pavement (Typ.)
1 " bituminous plank bond breaker (See Note 7,8)
CONCRETE APPROACH SLAB EXPANSION JOINT DETAIL
Ci. Joint \ !L-50" I L/2
Continously Reinforced Concrete Pavement
(CRCP)
Dowel cap
Ci. Joint s
I
I
CRCP reinforceme,nt I i 1"
I
Silicone joint sealant (See Note 4)
Concrete approach (Typ.)
Tapered plate dowel (Note 10,11)
CONCRETE APPROACH SLAB EXPANSION JOINT
WITH PLATE DOWEL DETAIL
# 7SE4 Longitudinal bars
V
Additional # 7 rebar ---+-+---jl------li--J
(Typ.)
• • �-- - ----- --- - - - ---- - -1-- ------ --- -- -- ---I-- -- ----- -- --- -- 1------ -·- ---- - - I---- - - f- -1----
#7SE4 Longitudinal bars _j Ci. Joint -_______.,, No splices allowed within 1 O ft of the construction joint
CRCP TRANSVERSE CONSTRUCTION JOINT DETAIL
A-A SECTION
(See Note 12)
Backer rod (See Note 4,5,6,8)
EXPANSION JOINT DETAIL
EXISTING CONCRETE - BRICK WALL
Existing Stone Masonry (Typ.)
Ci. Joint
Silicone joint sealant (See Note 4)
Existing concrete slab
STRUCTURE NO. STRUCTURE NAME FEATURES INTERSECTED
3100-020P FOUR LOCKS TUNNEL
NO. DATE BY REVISIONS
£ 8/21/25 NN CONSTRUCTION JOINT DET. AND NOTE 12
DESIGNED BY
NR
C&O CANAL
DRAWN BY CHECKED BY
NR NN
����-��-��-�-��-�J\)--�-��-��-��-��
CRCP TRANSVERSE CONSTRUCTION JOINT DETAIL
PLAN VIEW
(See Note 12)
Existing Stone Masonry �I � (Typ.) /
Ci. Joint � Silicone joint sealant (See Note 4)
½" bituminous plank bond breaker (See Note 7,8)
CRCP
BOND BREAKER
EXPANSION JOINT DETAIL
CRCP CONCRETE - BRICK WALL
LOCATION
CHESAPEAKE AND OHIO CANAL NATIONAL HISTORICAL PARK
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
OFFICE OF FEDERAL LANDS HIGHWAY
PROJECT TEAM LEAD SCALE
Carlos Pena-Marsh Not to Scale
BRIDGE PLAN SHEET DATE
9 of 10 MARCH 2025
RG / BRP NO.
BRP-1340
PROJECT
MD NP CHOH 235(2), 242(1), ETC.
Notes:
SHEET
NUMBER
R09
1. See "CONCRETE SLAB REINFORCEMENT" sheet for additional information.
2. See "CONCRETE SLAB" sheet for additional information.
3. Maintain joint sealant shape factor of 1: 1 or as recommended by sealant manufacturer .
4. Furnish silicone joint sealant conforming to Subsection 712.01(e) for horizontal joints and Subsection 712.01(d) for all other joints.
5. Measure joint opening after cleaning to select size of backer rod conforming to Subsection 712.01(f).
6. Silicone joint sealant sequence of work:
a. Remove existing joint material, clean joint opening of debris and remove laitance with oil-free compressed air.
b. Install new expansion joint material according to manufacturer's recommendation.
7. Install bituminous type expansion joint filler bond breaker conform Subsection 712.01(b)(1) between the CRCP slab and existing stone masonry and between CRCP slab and historic curb as approved by the CO.
8. Ensure watertight seal is created throughout the tunnel width when placing curb joint material.
9. Stagger the lap configurations so that no more than ½ of the longitudinal steel is spliced in any given 12-ft width and 2-ft length of the pavement
10. Install tapered plate dowels according to manufacturers recommendations
11. Shift the plate dowels horizontally along the joint line to avoid interference with the rebar while keeping them at mid-depth.
Maintain the recommended center-to-center spacing, typically between 12 and 18 inches or according to manufacturers recommendations, ensuring that the dowels remain
,,--�E�en • la t ·oi or: P, Oqu--1.(oOsJ'.'e.r.
12. Minimize the number of construction joints. Provide transverse construction joints that maintain reinforcement continuity and prevent differential movement. Locate construction joint a minimum of 12 ft from the preceding construction joint. Submit the location of construction joint to the CO for approval prior to placement of CRCP.
' I
[ __ _ J
See Note 9
' I -----
' I
[ ____ J
EXAMPLES OF LAP CONFIGURATION
SCHEDULE A
JOINT DETAILS
Bidders Questions Page 1 of 1
Questions / Clarifications
The following questions and issues were submitted via email at eflhd.contracts@dot.gov. The Government response or clarification is provided. The wording of the questions may have been revised and some questions have not been included. The Government’s direct response to the sender may also have been updated below for better clarity.
1. Does the concrete slab through the Four Locks Tunnel require pouring in one complete slab like a bridge deck, or can the slab be split into multiple pours throughout the 113’ tunnel with multiple construction joints?
Response: Splitting the concrete pours into multiple pours will be permitted, see revised plan sheet R09.
mailto:eflhd.contracts@dot.gov
Local Clause:
U.S. Department of Transportation
Federal Highway Administration
(TAR Class Deviation 2025-02) (10) The following statement “The Contractor also affirms that it does not operate any diversity, equity, and inclusion (DEI) initiatives that are inconsistent with the Equal Protection principles of the Constitution and the non-discrimination requirements of Federal law, as interpreted by the Supreme Court in Students for Fair Admissions v. Harvard, 600 U.S. 181 (2023).”
1252.232-70 Electronic Submission of Payment Requests. (DEVIATION) (AUG 2025)
(a) Definitions. As used in this clause—
(1) Contract financing payment has the meaning given in FAR 32.001.
(2) Payment request means a bill, voucher, invoice, or request for contract financing payment or invoice payment with associated supporting documentation. The payment request must comply with the requirements identified in FAR 32.905(b), “Content of Invoices,” this clause, and the applicable Payment clause included in this contract.
(3) Electronic form means an automated system transmitting information electronically according to the accepted electronic data transmission methods and formats identified in paragraph (c) of this clause. Facsimile, email, and scanned documents are not acceptable electronic forms for submission of payment requests.
(4) Invoice payment has the meaning given in FAR 32.001.
(b) Electronic payment requests. Except as provided in paragraph (e) of this clause, the contractor shall submit payment requests in electronic form. Purchases paid with a Governmentwide commercial purchase card are considered to be an electronic transaction for purposes of this rule, and therefore no additional electronic invoice submission is required.
(c) Processing system. The Department of Transportation utilizes the DELPHI system for processing invoices. The DELPHI module for submitting invoices is called iSupplier. Access to DELPHI is granted with electronic authentication of credentials (name & valid email address) utilizing the GSA credentialing platform login.gov. Vendors submitting invoices are required to submit invoices via iSupplier (DELPHI) and authenticated via www.login.gov.
(d) Invoice requirements. To receive payment and in accordance with the Prompt Payment Act, all invoices submitted as attachments in iSupplier (DELPHI) shall contain the following:
(1) Invoice number and invoice date.
(2) Period of performance covered by invoice.
(3) Contract number and title.
(4) Task/Delivery Order number and title (if applicable).
(5) Amount billed (by CLIN), current and cumulative.
(6) Total ($) of billing.
(7) Cumulative total billed for all contract work to date.
(8) Name, title, phone number, and mailing address of person to be contacted in the event of a defective invoice.
(9) Travel. If the contract includes allowances for travel, all invoices which include charges pertaining to travel expenses will catalog a breakdown of reimbursable expenses with the appropriate receipts to substantiate the travel expenses.
(10) The following statement “The Contractor also affirms that it does not operate any diversity, equity, and inclusion (DEI) initiatives that are inconsistent with the Equal Protection principles of the Constitution and the non-discrimination requirements of Federal law, as interpreted by the Supreme Court in Students for Fair Admissions v. Harvard, 600 U.S. 181 (2023).”
(e) Payment system registration. All persons accessing the iSupplier (DELPHI) will be required to have their own unique user ID and password and be credentialed through login.gov.
(1) Electronic authentication. See www.login.gov for instructions.
(2) To create a www.login.gov account, the user will need a valid email address and a working phone number. The user will create a password and then www.login.gov will reply with an email confirming the email address.
(3) iSupplier (DELPHI) registration instructions: New users should navigate to: http://einvoice.esc.gov to establish an account. Users are required to log in to iSupplier (DELPHI) every 45 days to keep it active.
(4) Training on DELPHI. To facilitate use of DELPHI, comprehensive user information is available at http://einvoice.esc.gov.
(5) Account Management. Vendors are responsible to contact their assigned COR when their firm's points of contacts will no longer be submitting invoices, so they can be removed from the system.
(f) Waivers. For contractors/vendors who are unable to utilize DOT's DELPHI system, waivers may be considered by DOT on a case-by-case basis. Vendors should contact their Contracting Officer's Representative (COR) for procedures.
(g) Exceptions and alternate payment procedures. If, based on one of the circumstances set forth in 1232.7002(a) or (b), and the contracting officer directs that payment requests be made by mail, the contractor shall submit payment requests by mail through the United States Postal Service to the designated agency office. If alternate payment procedures are authorized, the Contractor shall include a copy of the Contracting Officer's written authorization with each payment request. If DELPHI is succeeded by later technology, the Contracting Officer will supply the Contractor with the latest applicable electronic invoicing instructions.
(End of clause)
| FEDERAL HIGHWAY ADMINISTRATION |
| EASTERN FEDERAL LANDS HIGHWAY DIVISION |
| Amendment No. 0002 |
| Project MD NP CHOH 235(2), 242(1), ETC. |
| Solicitation: 693C73-25-R-000073 |
File details come from the government source that posted it. Updated .