Results of Bid Opening - NP MACA 12(1) 908(1).pdf

PDF 150 KB Posted

Attached to
NP MACA 12(1), 908(1) - Mammoth Cave National Park
Solicitation number
693C73-25-B-000012
Issued by

About this file

This document is a Bid Opening Abstract for a Federal Highway Administration (FHWA) Eastern Federal Lands Highway Division project at Mammoth Cave National Park. The solicitation (No. 693C73-25-B-000012) involves multiple schedules (A through E) with different performance periods, ranging from 53 to 240 calendar days, and a potential total contract duration of 674 calendar days if all schedules are awarded together.

Eight construction companies submitted bids, with total combined prices ranging from $10,668,698.70 (National Contracting Services, LLC) to $16,326,454.00 (Lee Construction). The Engineer's Estimate is $12,484,428.50. Each bidder provided pricing for individual schedules (Schedule A: Base Work, Schedules B-E: Optional Government Work) and a total combined price. The Eastern Federal Lands Highway Division notes they are reviewing and verifying the information, and the low bidder will be contacted after a thorough review is completed. The bid opening was scheduled for October 7, 2025, at 2:00 p.m. in Ashburn, VA.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Federal Highway Administration Eastern Federal Lands Highway Division

Bid Opening for

Mammoth Cave National Park

PROJECT: NP MACA 12(1), 908(1)

SOLICITATION NO. 693C73-25-B-000012

October 7, 2025 at 2:00 p.m.

Ashburn, VA

*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award, the low bidder will be contacted once a thorough review has been completed.

FEDERAL HIGHWAY ADMINISTRATION

EASTERN FEDERAL LANDS HIGHWAY DIVISION

BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1) October 7, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days, Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Central Southern Construction

SCHEDULE A

$5,050,630.00

SCHEDULE B (GOVERNMENT OPTION 1)

$3,761,725.00

SCHEDULE C (GOVERNMENT OPTION 2)

$1,255,775.00

SCHEDULE D (GOVERNMENT OPTION 3)

$1,678,202.68

SCHEDULE E (GOVERNMENT OPTION 4)

$1,062,475.00

SCHEDULE A + OPTION 1 + OPTION 2 +

OPTION 3 + OPTION 4 =

$12,808,807.68

National Contracting Services, LLC

SCHEDULE A

$3,306,424.77

SCHEDULE B (GOVERNMENT OPTION 1)

$3,163,729.49

SCHEDULE C (GOVERNMENT OPTION 2)

$1,375,139.42

SCHEDULE D (GOVERNMENT OPTION 3)

$2,024,166.68

SCHEDULE E (GOVERNMENT OPTION 4)

$799,238.34

SCHEDULE A + OPTION 1 + OPTION 2

OPTION 3 + OPTION 4 =

$10,668,698.70

*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award, the low bidder will be contacted once a thorough review has been completed.

BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1) October 7, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days, Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Adam’s Contracting

SCHEDULE A

$3,162,075.50

SCHEDULE B (GOVERNMENT OPTION 1)

$3,421,660.00

SCHEDULE C (GOVERNMENT OPTION 2)

$1,347,030.00

SCHEDULE D (GOVERNMENT OPTION 3)

$2,076,160.00

SCHEDULE E (GOVERNMENT OPTION 4)

$832,825.00

SCHEDULE A + OPTION 1 + OPTION 2 +

OPTION 3 + OPTION 4 =

$10,839,750.50

T&T Construction Enterprises, LLC

SCHEDULE A

$4,273,133.39

SCHEDULE B (GOVERNMENT OPTION 1)

$4,760,284.86

SCHEDULE C (GOVERNMENT OPTION 2)

$2,429,370.47

SCHEDULE D (GOVERNMENT OPTION 3)

$2,718,568.62

SCHEDULE E (GOVERNMENT OPTION 4)

$1,464,937.88

SCHEDULE A + OPTION 1 + OPTION 2

OPTION 3 + OPTION 4 =

$15,646,295.22

BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1) October 7, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days, Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Medvolt Construction Services, LLC

SCHEDULE A

$3,437,908.78

SCHEDULE B (GOVERNMENT OPTION 1)

$3,283,691.40

SCHEDULE C (GOVERNMENT OPTION 2)

$1,698,529.51

SCHEDULE D (GOVERNMENT OPTION 3)

$1,954,111.06

SCHEDULE E (GOVERNMENT OPTION 4)

$881,967.02

SCHEDULE A + OPTION 1 + OPTION 2 +

OPTION 3 + OPTION 4 =

$11,256,207.77

Lee Construction

SCHEDULE A

$4,478,709.00

SCHEDULE B (GOVERNMENT OPTION 1)

$4,888,645.00

SCHEDULE C (GOVERNMENT OPTION 2)

$2,261,891.00

SCHEDULE D (GOVERNMENT OPTION 3)

$2,777,280.00

SCHEDULE E (GOVERNMENT OPTION 4)

$1,919,929.00

SCHEDULE A + OPTION 1 + OPTION 2

$16,326,454.00

BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1) October 7, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days, Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.

BIDDER SCHEDULE TOTAL TOTAL PRICE

Kovilic Construction Company

SCHEDULE A

$3,607,095.00

SCHEDULE B (GOVERNMENT OPTION 1)

$5,581,595.00

SCHEDULE C (GOVERNMENT OPTION 2)

$1,685,830.00

SCHEDULE D (GOVERNMENT OPTION 3)

$1,973,285.00

SCHEDULE E (GOVERNMENT OPTION 4)

$1,017,380.00

SCHEDULE A + OPTION 1 + OPTION 2 +

OPTION 3 + OPTION 4 =

$13,865,185.00

Howard W. Pence

SCHEDULE A

$4,708,768.09

SCHEDULE B (GOVERNMENT OPTION 1)

$4,043,772.52

SCHEDULE C (GOVERNMENT OPTION 2)

$1,675,177.10

SCHEDULE D (GOVERNMENT OPTION 3)

$2,207,034.24

SCHEDULE E (GOVERNMENT OPTION 4)

$1,339,267.50

SCHEDULE A + OPTION 1 + OPTION 2

$13,974,019.45

BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1) October 7, 2025, 2:00 p.m. local time

If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days, Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.

BIDDER SCHEDULE TOTAL TOTAL PRICE

GC Works, Inc.

SCHEDULE A

$3,900,007.81

SCHEDULE B (GOVERNMENT OPTION 1)

$4,051,304.06

SCHEDULE C (GOVERNMENT OPTION 2)

$1,867,142.21

SCHEDULE D (GOVERNMENT OPTION 3)

$2,318,546.33

SCHEDULE E (GOVERNMENT OPTION 4)

$873,358.34

SCHEDULE A + OPTION 1 + OPTION 2 +

OPTION 3 + OPTION 4 =

$13,010,358.75

Engineer’s Estimate

SCHEDULE A

$2,880,000.00

SCHEDULE B (GOVERNMENT OPTION 1)

$5,204,428.50

SCHEDULE C (GOVERNMENT OPTION 2)

$1,475,000.00

SCHEDULE D (GOVERNMENT OPTION 3)

$2,000,000.00

SCHEDULE E (GOVERNMENT OPTION 4)

$925,000.00

SCHEDULE A + OPTION 1 + OPTION 2

OPTION 3 + OPTION 4 =

$12,484,428.50

*EFL is reviewing and verifying all information. This abstract is not indicative to who will receive the award, the low bidder will be contacted once a thorough review has been completed.

Slide Number 1
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1)�October 7, 2025, 2:00 p.m. local time�If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days,�Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1)�October 7, 2025, 2:00 p.m. local time�If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days,�Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1)�October 7, 2025, 2:00 p.m. local time�If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days,�Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1)�October 7, 2025, 2:00 p.m. local time�If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days,�Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.
FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-25-B-000012 Project: NP MACA 12(1), 908(1)�October 7, 2025, 2:00 p.m. local time�If the Government awards the contract as Schedules A + B + C + D + E, the performance period to complete all the contract work will be 674 calendar days. If awarded separately, Schedule A will be 240 calendar days, Schedule B will be 108 calendar days,�Schedule C will be 181 calendar days, Schedule D will be 92 calendar days, and Schedule E will be 53 calendar days.

File details come from the government source that posted it. Updated .