This document is a Minute-Memo from the Federal Highway Administration (FHWA) that provides preliminary pavement recommendations for the George Washington Memorial Parkway (GWMP) Mount Vernon Trail (MVT) Reconstruction project in Arlington County, Virginia.
The memo outlines the results of a field assessment conducted by the Eastern Federal Lands Highway Division (EFLHD) pavement engineers on October 19, 2020. It states that the existing 2-4 inch asphalt concrete (AC) pavement trail is in fair to poor condition, exhibiting frequent distresses such as transverse cracking, raveling, edge cracking, and rutting. The memo recommends reconstructing the trail by removing the existing AC pavement and aggregate base, reconditioning the subgrade, and installing new pavement layers with minimum thickness requirements specified. For the bridge approaches at Bridges #31 and #32, the memo similarly recommends removing the existing AC pavement and aggregate base and reconstructing the new bridge approach AC pavement. Photographs of the existing trail conditions are provided as an attachment.
This preliminary pavement recommendation memo supports the development of 30% plans, specifications, and estimates (PS&E) for the NP GWMP MVT(4) project, which involves the horizontal realignment of two bridges and rehabilitation of approximately 2 miles of the Mount Vernon Trail.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 6 Pages
Form FHWA-201 (Rev. 11-67)
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to be retained as file material. Do not prepare carbons. Not to be used in lieu of Form FHWA- 121 for informal correspondence. MINUTE-MEMO
SUBJECT: Preliminary Pavement Recommendations for Project NP-GWMP MVT(4)
TO MESSAGE/COMMENT FROM/DATE
Dan Weston Project Manager
And:
Tiffany Wheeler Highway Design Manager
To support developing 30% PS&E for the project, we’re submitting our preliminary findings and pavement recommendations for project NP GWMP MVT(4). The project site is located along the George Washington Memorial Parkway in Arlington County, VA.
The project consists of horizontal realignment of Bridge #31 and Bridge #32 to eliminate the “T” intersection of the two bridges, replace the bridge deck and railing. The proposed work also includes the rehabilitation of approximately 2 miles of the Mount Vernon Trail south of Theodore Roosevelt Island parking area and along the length of the Columbia Island. This memorandum presents our preliminary recommendations for the trail rehabilitation and improvement based on findings from field assessment performed by Eastern Federal Lands Highway Division (EFLHD). Please note that upon completion of further analyses, the pavement recommendations provided in this memo may be subjected to changes.
EXECUTIVE SUMMARY
The Mount Vernon Trail is an 18-mile paved multi-use trail originally constructed the MVT in the 1970s and 1980s, that stretches from George Washington's Mount Vernon Estate to Theodore Roosevelt Island. It connects with regional trails, including the Potomac Heritage, Custis, Rock Creek, Four Mile Run, and Woodrow Wilson Bridge Trails. The Mount Vernon Trail parallels the parkway between Theodore Roosevelt Island and Mount Vernon.
PAVEMENT CONDITION ASSESSMENT
EFLHD pavement engineers conducted field assessment for the trail on October 19, 2020.
It was observed that the trail varies in width, with the majority of the trail ranging from 8 to 10 feet wide (average of 9 feet), though some areas are as narrow as 6 to 7 feet, including the area of the trail under Arlington Memorial Bridge. The trail consists of an asphalt concrete (AC) pavement ranging from 2 to 4-inches in thickness with an average of 2.5-inches over aggregate base course. Pavement thickness was revealed by lightly excavating along the pavement edges to measure the thickness every 500 to 1000 ft along the trail using manual tools. Chunks of pavements from broken edges measured 3 inches (Photo 5). The existing AC surface course appears in fair to poor condition, exhibiting frequent distresses including medium to high severity transverse cracking and raveling.
Edge cracking and isolated potholes were also observed along with significant rutting mostly related to adjacent tree roots that have extended underneath the paved surface, causing the pavement to heave, crack, and create aesthetic and safety issues as uneven surface developed. Many locations along the trail require shoulder reconditioning to improve drainage, prevent shoulder erosion and pavement edge cracking (Photo 5).
Photos showing existing trail condition are provided in the Attachment.
Our field assessment began at (lat/long) coordinates 38.8951048°, -77.0664011° and ended at coordinates 38.877252°, -77.048119°.
Marc- Olivier Tschibelu Pavement Engineer
Through:
Mohammed Elias Pavement Team Leader
11/16/20
MOHA
MMED
B
ELIAS
Digitally signed by
MOHAMMED
B ELIAS
Date:
2020.11.16 11:35:39 -05'00'
MARC-
OLIVIER
TSCHIBELU
Digitally signed by
MARC-OLIVIER
TSCHIBELU
Date: 2020.11.16 11:38:44 -05'00'
Page 2 of 6 Pages
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to
PAVEMENT RECOMMENDATIONS
Based on our field assessment and the observed existing pavement conditions, we are recommending reconstruction of the trail by removing the existing AC pavement and existing aggregate base, reconditioning the subgrade, including removal of tree roots and other deleterious material then placing the new AC pavement according to the minimum requirements provided below in Table 1. The reconstruction of the AC pavement trail and the bridge approaches will be performed in accordance with the FP-14 Standard Specifications.
Table 1. Mount Vernon Trail Pavement – Reconstruction
Layer Minimum Thickness
(in)
Comments
AC Surface Course 1.5
Asphalt Concrete Pavement, Type 1, 3/8” Nominal Maximum Size
Aggregate (NMSA), Type IV roughness, as per Section 403
Asphalt Tack Coat --- AC Tack Coat per Section 412
AC Base Course 2.5 Asphalt Concrete Pavement, Type 1, 1/2” NMSA, as per Section 403
Aggregate Base Course 4.0 Aggregate Base, Grading C or D, as per Section 301
Geotextile --- Separation and Stabilization Geotextile Class 2 – Type E, as per Section 207
Roadbed Reconditioning --- Roadbed Reconditioning, as per Section 303
Additionally, the shoulders within the limit of the project along the reconstructed trail should be reconditioned to provide adequate drainage and prevent pavement edge cracking.
Page 3 of 6 Pages
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to
Bridge #31 and Bridge #32 paved approaches
Based on our field assessment the bridge approaches are exhibiting minor deformation and moderate to high severity transverse cracking. We are recommending to remove the existing AC pavement and existing aggregate base and reconstruct the new bridge approaches AC pavement according to the minimum requirements provided below in Table 2.
Table 2. Bridge#31 and #32 AC pavement approaches - Reconstruction
Layer Minimum Thickness
(in)
Comments
AC Surface Course 1.5
Asphalt Concrete Pavement, Type 1, 3/8” Nominal Maximum Size
Aggregate (NMSA), Type IV roughness, as per Section 403
Asphalt Tack Coat --- AC Tack Coat per Section 412
AC Base Course 2.5 Asphalt Concrete Pavement, Type 1, 1/2” NMSA, as per Section 403
Aggregate Base Course 4.0 Aggregate Base, Grading C or D, as per Section 301
Geotextile --- Separation and Stabilization Geotextile Class 2 – Type E, as per Section 207
Attachment - Photos showing the trail existing conditions.
Page 4 of 6 Pages
(Rev. 11-67)
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to be retained as file material. Do not prepare carbons. Not to be used in lieu of Form FHWA- 121 for informal correspondence.MINUTE-MEMO
TO MESSAGE/COMMENT FROM/DATE
Photo 1: Root causing sever cracking and AC pavement heaving
Photo 2: Transverse cracking at bridge approach
Page 5 of 6 Pages
(Rev. 11-67)
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to be retained as file material. Do not prepare carbons. Not to be used in lieu of Form FHWA- 121 for informal correspondence.MINUTE-MEMO
TO MESSAGE/COMMENT FROM/DATE
Photo 3: Severe transverse cracking and deformation along trail
Photo 4: Transverse cracking and potholes repaired with cold asphalt patch
Page 6 of 6 Pages
(Rev. 11-67)
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
Use this form in lieu of transmittal slips within Dept. of Trans. When message comment is to be retained as file material. Do not prepare carbons. Not to be used in lieu of Form FHWA- 121 for informal correspondence.MINUTE-MEMO
TO MESSAGE/COMMENT FROM/DATE
Photo 5: Severe AC pavement edge cracking along the trail. Broken asphalt concrete chunks measured 2.5 inches.