Appendix B_Bridge Inspection Reports.pdf

PDF 29 MB Posted

Attached to
George Washington Memorial Parkway Mount Vernon Trail Reconstruction - VA NP GWMP MVT(4)
Solicitation number
693C73-24-R-000018
Issued by

About this file

The provided document is Appendix B to a Request for Quotes (RFQ) for the reconstruction of the George Washington Memorial Parkway Mount Vernon Trail in Virginia. The RFQ is being issued by the Department of Transportation Federal Highway Administration (FHWA) under Solicitation Number 693C73-24-R-000018. This appendix contains bridge inspection reports for the project area. The RFQ does not provide details on the specific products or services required, response dates, award dates, pricing terms, set-asides, or other key information. This document appears to be a technical appendix to support the overall RFQ requirements, rather than addressing the core scope of work.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-022P

FOUR MILE RUN BRIDGE INSPECTION DATE : 04/18/2023

226 PRIORITY OF IMPROVEMENT C

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

Item No.

Maintenance Recommendations

(GENERALLY NOT FLHP ELIGIBLE)

QTY. UNIT UNIT

COST

PRELIM.

COST

ESTIMATE

222.9

REMOVE TREE LIMBS OVERHANGING APPROACH RAIL AT

NORTHWEST AND SOUTHEAST CORNERS. 1 LS

PRELIM. MAINTENANCE TOTAL :

Item No.

REHABILITATION/RECONSTRUCTION

(TYPICALLY NEEDED WITHIN 5 YEARS)

QTY. UNIT

UNIT

COST

PRELIM. COST ESTIMATES

REHAB RECONSTR

58.7,59.1, 59.2,60.6, 59.7

CLEAN AND PAINT END 10' OF STRUCTURAL

STEEL BENEATH EXPANSION JOINTS. 1 LS

58.3,222.

REPAIR ASPHALT WEARING SURFACE OVER

BRIDGE AND APPROACHES AS NECESSARY. 1 LS

58.3,60.3, REMOVE UNSOUND CONCRETE ON SOUTH

60.4,60. ABUTMENT AND NORTH PIER BEARING SEATS, 1 LS

13 TOP OF BACKWALLS, AND DECK HEADERS AND

PLACE NEW CONCRETE TO ORIGINAL

DIMENSIONS. CLEAN EXPOSED REBAR ON

SOUTH PIER AND COAT WITH APPROVED

SEALANT.

58.2,60.8 CLEAN AND RESEAL VERTICAL JOINTS IN

ABUTMENT WINGWALLS AND PIER WALLS.

CLEAN DEBRIS FROM EXPANSION JOINTS.

1 LS

58.8,60. REPAIR LEAKING UTILITY AND REPLACE DRIP

12 GUARD AND SUPPORTS OVER PEDESTRIAN

TRAIL. REPLACE COVER PLATE ON WEST SIDE

OF NORTH ABUTMENT.

1 LS

222.9 REPLACE DECAYED PORTIONS OF

SOUTHEAST TIMBER RETAINING WALL. 1 LS

58.7 EXTEND DRAINS TO REDIRECT WATER AWAY

FROM BEAMS #8 AND #9. 1 LS

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-022P

FOUR MILE RUN BRIDGE INSPECTION DATE : 04/18/2023

PRIORITY OF IMPROVEMENT226

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

C

36.D INSTALL APPROVED END TREATMENTS.

1 LS

CONTRACT COSTS FOR MOBILIZATION,

TRAFFIC CONTROL, AND CONTINGENCIES 1 LS

PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :

COST ESTIMATE SUMMARY

PRELIM. MAINTENANCE TOTAL :

PRELIM. REHABILITATION TOTAL :

PRELIM. RECONSTRUCTION TOTAL : ..

TOTAL ITEMIZED COSTS:

PRELIMINARY ESTIMATE TOTAL * :

(*Includes typical contract costs for mobilization, traffic control and design/construction engineering: but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for planning purposes only; they should not be used as a complete or final engineers estimate.)

Remarks : Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.

STRUCTURE LOAD RATING STRUCTURE NO. 3300-022P

FOUR MILE RUN BRIDGE INSPECTION DATE: 04/17/2023

TRUCK TYPE

INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)

TONS METRIC TONS TONS METRIC TONS

H 12 11 20 18

HS 22 20 36 33

TYPE 3 26 24 43 39

TYPE 3S2 28 25 47 43

TYPE 3-3 30 27 50 45

DESIGN LOADING: 4 - H 20

CAPACITY MEETS OR EXCEEDS DESIGN LOAD

X CAPACITY IS LESS THAN DESIGN LOAD

X ORIGINAL LOAD RATING CALCULATION APPLICABLE

ORIGINAL LOAD RATING CALCULATION REVISED

DATE OF LOAD RATING CALCULATION: 06/01/2016

LOAD RATING CONTROLLED BY: GIRDER #1 - STEEL FLEXURE

REMARKS: SEE BRIDGE FILE FOR LOAD RATING CALCULATIONS.

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-022P

STRUCTURE IDENTIFICATION

(201) PARK: GEORGE WASHINGTON MEMORIAL PARKWAY

(202) STRUCTURE NAME:..............FOUR MILE RUN BRIDGE

(203) STRUCTURE KIND:............... 1 - BRIDGE

(204) STRUCTURE NUMBER:.........3300-022 P

2 - NATIONAL CAPITAL(205) NPS REGION:

(206) ROUTE CODE NUMBER:

(207) ROAD SECTION NO:............. 022P

(208) NPS ROAD CLASS:............... 7 - URBAN PARKWAY

(209) WITHIN NPS BNDRY?:.......... Yes

(210) OPERATING UNIT:.................PARK

(211) PROJECT NO(S):................... 15757-2

(212) DRAWING NUMBERS:...........NCP190

(21) MAINTAINED BY:......................66 - NATIONAL PARK SERVICE

(22) OWNER:................................... 66 - NATIONAL PARK SERVICE

(1) STATE:

(2) STATE HWY. AGENCY DIST:

(3) COUNTY CODE:

(4) CITY / PLACE CODE:

(5) INVENTORY ROUTE:

(6) FEATURES INTERSECTED:

(7) FACILITY CARRIED:

(8) STATE STRUCTURE NO:

(9) LOCATION:

(10) INV. RTE. - MIN. VERT. CLR:

(11) MILE POINT:

(27) YEAR BUILT:

(106) YEAR RECONSTRUCTED:

(20) TOLL:

(37) HISTORIC DESIGNATION:

513 - VIRGINIA

51013 ARLINGTON

00000

1 6 1 00001 0

FOUR MILE RUN

GWMP

3300022P0000000

2 3 MILES SOUTH OF I-395.

99.99 FT ( 99.99 M)

13.26 (KM PT: 21.34)

3 - ON FREE ROAD

5 - NOT ELIGIBLE

STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE

(43A) MAIN STR. MATERIAL:..........4 - STEEL CONTINUOUS (44A) APPR. STR. MATERIAL:............ 0 - Other

(43B) MAIN STR. TYPE:.................. 02 - STRINGER/MULTI-BEAM OR (44B) APPR. STR. TYPE:.................... 00 - OTHER

GIRDER

(45) NO. OF MAIN SPANS:..............003 (46) NO OF APPROACH SPANS:

(48) MAX. SPAN LENGTH:..............113. FT ( 34.6 M)

(49) STRUCTURE LENGTH:........... 336. FT ( 102.5 M) (108) WEAR SURFACE/PROTECT SYSTEM:

(216A) ABUTMENT #1 FDN:........... 3 - SPREAD FOOTING ON PILES A) TYPE WEARING SURFACE:.. 6 - BITUMINOUS

(216B) ABUTMENT #2 FDN:........... 3 - SPREAD FOOTING ON PILES B) TYPE MEMBRANE:................. 0 - NONE

(217A) PREDOM. PIER FDN:.......... 3 - SPREAD FOOTING ON PILES C) TYPE PROTECTION:.............. 0 - NONE

(217B) SECOND. PIER FDN:.......... 3 - SPREAD FOOTING ON PILES (218) IS SALT USED?.......................... YES

(107) DECK TYPE:.......................... 1 - CONCRETE CAST-IN-PLACE

LOAD RATING AND POSTING

(31) DESIGN LOAD:.........................4 - H 20 (41) LOAD RESTRICTION:.................. A - OPEN

(66) INVENTORY RATING:..............22 METRIC TONS) (70) BRIDGE POSTING:...................... 5 - EQUAL TO OR ABOVE LEGALTONS ( 20

LOADS

(64) OPERATING RATING:..............36 TONS ( 32.7 METRIC TONS)

INSPECTION DATES

(90) INSPECTION DATE: 04/18/2023 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):

(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL:.......... N

(220) SPECIAL STUDY TYPE: 5 - SCOUR INSP. EVERY MONTHS - LAST INSP:

(221) SPECIAL STUDY DATE: (B) UNDERWATER:..................... N

INSP. EVERY MONTHS - LAST INSP:

(C) SPECIAL INSPECTION:........ N

INSP. EVERY MONTHS - LAST INSP:

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-022P

GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA

(16) LATITUDE:................................ 38° 50'28.60" (51) CURB TO CURB WIDTH:............ 66.0 FT ( 20.1 M)

(17) LONGITUDE:............................ 77°02 '50 80" (52) DECK WIDTH:.......................... 93.0 FT ( 28.3 M)

(19) DETOUR LENGTH:.................. 5 MI ( 8 KM) (32) APPR. ROADWAY WIDTH:...... 78 FT ( 23.8 M)

(28A) LANES ON STRUCT:.............04 (213) APPR. PAVEMENT WIDTH:... 78.0 FT ( 23.8 M)

(28B) LANES UNDER STRUCT:......00 LEFT SHOULDER:............... 0 0 FT ( 0 M)

(42A) SERVICE ON:.........................5 - HIGHWAY-PEDESTRIAN RIGHT SHOULDER:.......... 0 0 FT ( 0 M)

(42B) SERVICE UNDER:................. 5 - WATERWAY (33) BRIDGE MEDIAN:.................... 3 - CLOSED MEDIAN WITH NON-

MOUNTABLE BARRIERS

(29) AVG DAILY TRAFFIC:..............18200 (34) SKEW ANGLE:......................... 25 °

(30) YEAR OF ADT:......................... 2007 (35) STRUCTURE FLARED:............ 0 - NO FLARE

(114) FUTURE ADT:.........................20020 (47) TOTAL HORIZ. CLEARANCE:.. 33 FT ( 10.1 M)

(115) YEAR OF FUTURE ADT:........2027 (50) SIDEWALKS

(101) PARALLEL STRUCTURE:......N - NO PARALLEL STRUCTURE LEFT:.................................... 9 0 FT ( 2.7 M)

(38) NAVIGATION CONTROL:.........0 RIGHT:.................................. 0 0 FT ( 0 M)

(39) VERTICAL CLEARANCE:.........0 FT ( 0 M) (214) BRIDGE RAIL TYPE

2 - MOUNTED ON PARAPET(40) HORIZ. CLEARANCE:..............0 FT ( 0 M) RAIL CONFIGURATION:

(111) ABUT OR PIER PROT:...........1 - NAVIGATION PROTECTION NOT MATERIAL:........................... 6 - ALUMINUM

REQUIRED

LATERAL UNDERCLEARANCE: DESIGN TYPE:..................... 1 - CONTINUOUS RAIL

(55) RIGHT:...............................00 FT ( 0 M) (215) BRIDGE RAIL HEIGHT:.......... 3.45 FT ( 1 05 M)

(56) LEFT:................................ 0 FT ( 0 M) (53) MIN. VRT. CLR. OVER DECK: 99.99 FT ( 99.99 M)

(54) MIN. VRT. UNDRCLRANCE:... .00 FT ( 0 M)

CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST

(58) DECK:

(59) SUPERSTRUCTURE:

(60) SUBSTRUCTURE:

(61) CHANNEL:

(62) CULVERT:.................................N

(222) APPROACHES:

(223) RETAINING WALL:.................N

(36) TRAFFIC SAFETY FEAT: 1 1 1 0

(75A) TYPE OF WORK:................... 35 - REHABILITATION - DETERIORATION

(75B) WORK DONE BY:.................. 1 - WORK TO BE DONE BY CONTRACT

(76) IMPROVEMENT LENGTH:....... FT ( 0 M)

(67) STRUCTURAL EVALUATION:

(68) DECK GEOMETRY:

(69) UNDERCLEARANCES:................ N

(71) WATERWAY ADEQUACY:

(72) APPROACH ALIGNMENT:

(113) SCOUR CRITICAL:.................... 5 - SCOUR WITHIN LIMITS OF

FOOTING OR PILES

(225) PURPOSE OF IMPROVEMENT: 2 - REHAB/RECONSTRUCTION

(226) PRIORITY OF IMPROVEMENT: C - MODERATE

(227) MAINTENANCE COST:

(228) REHAB / RECNSTR COST:

(229) CONSTRUCTION COST:

ADDITIONAL INFORMATION

(230) STRUCTURE HISTORY:

2002-EXPANSION JOINTS REPLACED, NEW WEARING SURFACE.

(231) ADDITIONAL CONSIDERATIONS:

2015-UBIV INSP LIMITED TO BEAMS 7-12 DUE TO PEDESTRIAN SIDEWALK ON EAST SIDE

(330) ADDITIONAL CONFIGURATION INFORMATION:

Inspector: Nate Brown Structure Number: 3300022P0000000

Inspection Date: 04/18/2023 Facility Carried: GWMP

Bridge Inspection Report

Pictures

PHOTO 3

Description LOOKING SOUTH TOWARD MOUNT VERNON

PHOTO 4

Description WEST (UPSTREAM) SIDE

Bridge Inspection Report

Pictures

PHOTO 5

Description GENERAL TOPSIDE VIEW LOOKING NORTH

PHOTO 6

Description TYPICAL DETERIORATION OF ASPHALT WEARING SURFACE; NORTHBOUND LANES IN

NORTH APPROACH SHOWN

Bridge Inspection Report

Pictures

PHOTO 7

Description TYPICAL CRACKING OF DECK WEARING SURFACE; SOUTHBOUND LANES NEAR NORTH

ABUTMENT SHOWN

PHOTO 8

Description TYPICAL RUSTING OF PEDESTRIAN BRIDGE RAIL; NORTH SPAN SHOWN

Bridge Inspection Report

Pictures

PHOTO 9

Description OPEN JOINT IN MEDIAN; ALSO NOTE TYPICAL EXPOSED AGGREGATE FINISH

PHOTO 10

Description TYPICAL DEBRIS ACCUMULATION IN EXPANSION JOINTS; SOUTH ABUTMENT JOINT IN

NORTHBOUND LANES SHOWN; ALSO NOTE TYPICAL DETERIORATION OF DECK

HEADERS AND TOP OF ABUTMENT BACKWALLS

Bridge Inspection Report

Pictures

PHOTO 11

Description GUARDRAIL ON EAST SIDE OF SOUTH APPROACH SETTLED AND ROTATED

PHOTO 12

Description TYPICAL MISSING EXPANSION SLEEVES IN RAILS, EAST SIDE AT SOUTH APPROACH

SHOWN

Bridge Inspection Report

Pictures

PHOTO 13

Description TYPICAL VEGETATION GROWTH OVERHANGING ROADWAY; WEST SIDE OF SOUTH

APPROACH SHOWN

PHOTO 14

Description TYPICAL IMPACT DAMAGE TO MEDIAN GUARDRAIL; SOUTH APPROACH SHOWN

Bridge Inspection Report

Pictures

PHOTO 15

Description GENERAL VIEW OF RETAINING WALL AT SOUTHEAST APPROACH

PHOTO 16

Description GENERAL UNDERSIDE VIEW LOOKING SOUTH, NORTH SPAN SHOWN

Bridge Inspection Report

Pictures

PHOTO 17

Description GENERAL VIEW OF NORTH ABUTMENT

PHOTO 18

Description TYPICAL RUSTING AND SECTION LOSS AT BEARINGS; BEARING #8 AT NORTH ABUTMENT

Bridge Inspection Report

Pictures

PHOTO 19

Description TYPICAL RUSTING AND SECTION LOSS ON BOTTOM FLANGE, WEB, AND BEARING

STIFFENERS OF BEAMS AT ABUTMENTS; BEAM #3 AT NORTH ABUTMENT SHOWN

PHOTO 20

Description MISSING UTILITY COVER AT WEST END OF NORTH ABUTMENT

Bridge Inspection Report

Pictures

PHOTO 21

Description RUSTING OF UTILITY DRIP GUARD AND SUPPORT MEMBER BETWEEN BEAMS #2 AND #3

OVER PEDESTRIAN TRAIL IN NORTH SPAN; NOTE HOLES RUSTED THROUGH

PHOTO 22

Description TYPICAL RUSTING OF UTILITY PIPES; UTILITY BETWEEN BEAMS #10 AND #11 IN NORTH

SPAN SHOWN

Bridge Inspection Report

Pictures

PHOTO 23

Description TYPICAL RUSTING OF SCUPPERS; NORTH SPAN SHOWN

PHOTO 24

Description GENERAL VIEW OF NORTH PIER, NORTH FACE

Bridge Inspection Report

Pictures

PHOTO 25

Description DELAMINATION AT TOP OF SOUTH FACE OF NORTH PIER BELOW BEAM #8

PHOTO 26

Description LOOSE SPLICE BOLT ON BOTTOM FLANGE OF BEAM #11 IN CENTER SPAN

Bridge Inspection Report

Pictures

PHOTO 27

Description TYPICAL RUST SCALING OF WEB AND BOTTOM FLANGE OF BEAMS; BEAM #8 IN CENTER

SPAN SHOWN

PHOTO 28

Description TYPICAL TRANSVERSE CRACK WITH EFFLORESCENCE ON UNDERSIDE OF DECK; WEST

OVERHANG IN CENTER SPAN SHOWN

Bridge Inspection Report

Pictures

PHOTO 29

Description SPALL ON NORTH FACE OF SOUTH PIER BELOW BEAM #12

PHOTO 30

Description TYPICAL RUSTING OF METAL STAY-IN-PLACE DECK FORMS WITH SECTION LOSS;

BETWEEN BEAMS #10 AND #11 AT SOUTH ABUTMENT SHOWN

Bridge Inspection Report

Pictures

PHOTO 31

Description TYPICAL RUSTING AND SECTION LOSS ON BOTTOM FLANGE, WEB, AND BEARING

STIFFENERS OF BEAMS AT ABUTMENTS; BEAM #5 AT SOUTH ABUTMENT SHOWN

PHOTO 32

Description DELAMINATION AND SPALLING OF SOUTH ABUTMENT BACKWALL BETWEEN BEAMS #10

AND #11 AROUND UTILITY PENETRATION

Bridge Inspection Report

Pictures

PHOTO 33

Description TYPICAL OVERHANGING BEARING PLATE; BEARING #9 AT SOUTH ABUTMENT SHOWN

PHOTO 34

Description TYPICAL DETERIORATION OF VERTICAL JOINT FILLER MATERIAL AT CENTERLINE OF

ABUTMENTS; SOUTH ABUTMENT SHOWN

Bridge Inspection Report

Pictures

PHOTO 35

Description TYPICAL DETERIORATION OF MASONRY MORTAR JOINTS IN WINGWALLS; SOUTHWEST

WINGWALL SHOWN

PHOTO 36

Description TYPICAL DETERIORATION OF VERTICAL JOINT FILLER MATERIAL AT WINGWALLS;

SOUTHWEST WINGWALL SHOWN

Bridge Inspection Report

Pictures

PHOTO 37

Description UPSTREAM CHANNEL

PHOTO 38

Description DOWNSTREAM CHANNEL

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-042T

MOUNT VERNON BICYCLE TRAIL BRIDGE INSPECTION DATE : 03/07/2023

PRIORITY OF IMPROVEMENT226

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

D

Item No.

Maintenance Recommendations

(GENERALLY NOT FLHP ELIGIBLE)

QTY. UNIT UNIT

COST

PRELIM.

COST

ESTIMATE

59.1

REPLACE BROKEN OR MISSING ANCHOR BOLTS AT BOTH

ABUTMENT BEARINGS. 7 EA

58.10,60.

REMOVE VEGETATION ON AND ALONG EAST WINGWALLS.

TREE OVERHANGING BRIDGE AT SOUTH AND NORTH

END.

1 LS

222.4, 222.6

SEAL MODERATE TRANSVERSE AND LONGITUDINAL

CRACKING OF APPROACH PAVEMENT. 1 LS

58.6

REPLACE SOUTH RAIL POST ON EAST RAIL IN SOUTH

APPROACH. 1 LS

PRELIM. MAINTENANCE TOTAL :

Item No.

REHABILITATION/RECONSTRUCTION

(TYPICALLY NEEDED WITHIN 5 YEARS)

QTY. UNIT

UNIT

COST

PRELIM. COST ESTIMATES

REHAB RECONSTR

PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :

COST ESTIMATE SUMMARY

PRELIM. MAINTENANCE TOTAL :

PRELIM. REHABILITATION TOTAL :

PRELIM. RECONSTRUCTION TOTAL : ..

TOTAL ITEMIZED COSTS:

PRELIMINARY ESTIMATE TOTAL * :

(*Includes typical contract costs for mobilization, traffic control and design/construction engineering: but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for planning purposes only; they should not be used as a complete or final engineers estimate.)

Remarks : Cost estimates assume that recommended actions will be combined with similar work being performed on other

STRUCTURE LOAD RATING STRUCTURE NO. 3300-042T

MOUNT VERNON BICYCLE TRAIL BRIDGE INSPECTION DATE: 03/06/2023

TRUCK TYPE

INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)

TONS METRIC TONS TONS METRIC TONS

H 0 0 0 0

HS 0 0 0 0

TYPE 3 0 0 0 0

TYPE 3S2 0 0 0 0

TYPE 3-3 0 0 0 0

DESIGN LOADING: 7 - PEDESTRIAN

X CAPACITY MEETS OR EXCEEDS DESIGN LOAD

CAPACITY IS LESS THAN DESIGN LOAD

ORIGINAL LOAD RATING CALCULATION APPLICABLE

ORIGINAL LOAD RATING CALCULATION REVISED

DATE OF LOAD RATING CALCULATION:

LOAD RATING CONTROLLED BY:

REMARKS:

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-042T

STRUCTURE IDENTIFICATION

(201) PARK: GEORGE WASHINGTON MEMORIAL PARKWAY

(202) STRUCTURE NAME:..............MOUNT VERNON BICYCLE TRAIL

BRIDGE

(203) STRUCTURE KIND:............... 4 - TRAIL BRIDGE

(204) STRUCTURE NUMBER:.........3300-042 T

2 - NATIONAL CAPITAL(205) NPS REGION:

(206) ROUTE CODE NUMBER:

(207) ROAD SECTION NO:............. 042T

(208) NPS ROAD CLASS:............... 6 - RESTRICTED

(209) WITHIN NPS BNDRY?:.......... Yes

(210) OPERATING UNIT:.................PARK

(211) PROJECT NO(S):................... GWMP-331(1)

(212) DRAWING NUMBERS:

(21) MAINTAINED BY:......................66 - NATIONAL PARK SERVICE

(22) OWNER:................................... 66 - NATIONAL PARK SERVICE

(1) STATE:

(2) STATE HWY. AGENCY DIST:

(3) COUNTY CODE:

(4) CITY / PLACE CODE:

(5) INVENTORY ROUTE:

(6) FEATURES INTERSECTED:

(7) FACILITY CARRIED:

(8) STATE STRUCTURE NO:

(9) LOCATION:

(10) INV. RTE. - MIN. VERT. CLR:

(11) MILE POINT:

(27) YEAR BUILT:

(106) YEAR RECONSTRUCTED:

(20) TOLL:

(37) HISTORIC DESIGNATION:

113 - DISTRICT OF COLUMBIA

11001 DISTRICT OF COLUMBIA

00000

1 6 0 00000 0

BOUNDARY CHANNEL

MOUNT VERNON BICYCLE TRAIL

3300042T0000000

0.1 MILES SOUTH OF SPOUT RUN

PKWY.

99.99 FT ( 99.99 M)

7 89 (KM PT: 2.4 )

3 - ON FREE ROAD

5 - NOT ELIGIBLE

STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE

(43A) MAIN STR. MATERIAL:..........3 - STEEL (44A) APPR. STR. MATERIAL:............ 0 - Other

(43B) MAIN STR. TYPE:.................. 02 - STRINGER/MULTI-BEAM OR (44B) APPR. STR. TYPE:.................... 00 - OTHER

GIRDER

(45) NO. OF MAIN SPANS:..............001 (46) NO OF APPROACH SPANS:

(48) MAX. SPAN LENGTH:..............131. FT ( 40 M)

(49) STRUCTURE LENGTH:........... 135. FT ( 41.2 M) (108) WEAR SURFACE/PROTECT SYSTEM:

(216A) ABUTMENT #1 FDN:........... 3 - SPREAD FOOTING ON PILES A) TYPE WEARING SURFACE:.. 0 - NONE

(216B) ABUTMENT #2 FDN:........... 3 - SPREAD FOOTING ON PILES B) TYPE MEMBRANE:................. 0 - NONE

(217A) PREDOM. PIER FDN:.......... 6 - N/A C) TYPE PROTECTION:.............. 0 - NONE

(217B) SECOND. PIER FDN:.......... 6 - N/A (218) IS SALT USED?.......................... NO

(107) DECK TYPE:.......................... 1 - CONCRETE CAST-IN-PLACE

LOAD RATING AND POSTING

(31) DESIGN LOAD:.........................7 - PEDESTRIAN (41) LOAD RESTRICTION:.................. A - OPEN

(66) INVENTORY RATING:.............. METRIC TONS) (70) BRIDGE POSTING:...................... 5 - EQUAL TO OR ABOVE LEGALTONS ( 0

LOADS

(64) OPERATING RATING:.............. TONS ( 0 METRIC TONS)

INSPECTION DATES

(90) INSPECTION DATE: 03/07/2023 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):

(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL:.......... Y

(220) SPECIAL STUDY TYPE: 0 - NONE INSP. EVERY 24 MONTHS - LAST INSP: 04/01/2017

(221) SPECIAL STUDY DATE: (B) UNDERWATER:..................... N

INSP. EVERY MONTHS - LAST INSP:

(C) SPECIAL INSPECTION:........ N

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-042T

GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA

(16) LATITUDE:................................ 38° 53'23.64" (51) CURB TO CURB WIDTH:............ 10.5 FT ( 3.2 M)

(17) LONGITUDE:............................ 77°03 '50.40" (52) DECK WIDTH:.......................... 12.0 FT ( 3.7 M)

(19) DETOUR LENGTH:.................. 0 MI ( 0 KM) (32) APPR. ROADWAY WIDTH:...... 10.0 FT ( 3 M)

(28A) LANES ON STRUCT:.............01 (213) APPR. PAVEMENT WIDTH:... 10.0 FT ( 3 M)

(28B) LANES UNDER STRUCT:......00 LEFT SHOULDER:............... 0 0 FT ( 0 M)

(42A) SERVICE ON:.........................3 - PEDESTRIAN-BICYCLE RIGHT SHOULDER:.......... 0 0 FT ( 0 M)

(42B) SERVICE UNDER:................. 5 - WATERWAY (33) BRIDGE MEDIAN:.................... 0 - NO MEDIAN

(29) AVG DAILY TRAFFIC:..............0 (34) SKEW ANGLE:......................... 0 °

(30) YEAR OF ADT:......................... 2013 (35) STRUCTURE FLARED:............ 0 - NO FLARE

(114) FUTURE ADT:.........................2 (47) TOTAL HORIZ. CLEARANCE:.. 10.5 FT ( 3.2 M)

(115) YEAR OF FUTURE ADT:........2033 (50) SIDEWALKS

(101) PARALLEL STRUCTURE:......N - NO PARALLEL STRUCTURE LEFT:.................................... 0 0 FT ( 0 M)

(38) NAVIGATION CONTROL:.........N - NOT APPLICABLE, NO RIGHT:.................................. 0 0 FT ( 0 M)

WATERWAY

(39) VERTICAL CLEARANCE:.........0 FT ( 0 M) (214) BRIDGE RAIL TYPE

(40) HORIZ. CLEARANCE:..............0 FT ( 0 M) RAIL CONFIGURATION:...... 1 - FULL HEIGHT (NO PARAPET)

(111) ABUT OR PIER PROT:...........2 - IN PLACE AND FUNCTIONING MATERIAL:........................... 6 - ALUMINUM

LATERAL UNDERCLEARANCE: DESIGN TYPE:..................... 1 - CONTINUOUS RAIL

(55) RIGHT:...............................00 FT ( 0 M) (215) BRIDGE RAIL HEIGHT:.......... 4 58 FT ( 1.4 M)

(56) LEFT:................................ 0 FT ( 0 M) (53) MIN. VRT. CLR. OVER DECK: 99.99 FT ( 99.99 M)

(54) MIN. VRT. UNDRCLRANCE:... .00 FT ( 0 M)

CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST

(58) DECK:....................................... 7 (67) STRUCTURAL EVALUATION:

(59) SUPERSTRUCTURE:...............7 (68) DECK GEOMETRY:......................N

(60) SUBSTRUCTURE:.......... 7 (69) UNDERCLEARANCES:................ N

(61) CHANNEL:................................7 (71) WATERWAY ADEQUACY:

(62) CULVERT:.................................N (72) APPROACH ALIGNMENT:

(222) APPROACHES:...................... 7 (113) SCOUR CRITICAL:.................... 8 - STABLE FOR SCOUR CONDITIONS

(223) RETAINING WALL:.................N (225) PURPOSE OF IMPROVEMENT: 1 - MAINTENANCE

(36) TRAFFIC SAFETY FEAT: N N N N (226) PRIORITY OF IMPROVEMENT: D - MINOR

(75A) TYPE OF WORK:................... 35 - REHABILITATION - DETERIORATION (227) MAINTENANCE COST:

(75B) WORK DONE BY:.................. 1 - WORK TO BE DONE BY CONTRACT (228) REHAB / RECNSTR COST:

(76) IMPROVEMENT LENGTH:....... FT ( 0 M) (229) CONSTRUCTION COST:

ADDITIONAL INFORMATION

(230) STRUCTURE HISTORY:

STRUCTURE WAS FORMERLY INSPECTED WITH 3300-013P.

(231) ADDITIONAL CONSIDERATIONS:

Inspector: Joe Koenig Structure Number: 3300042T0000000

Inspection Date: 03/07/2023 Facility Carried: MOUNT VERNON BICY

Trail Bridge Inspection Report

Pictures

PHOTO 3

Description LOOKING SOUTH TOWARD MOUNT VERNON

PHOTO 4

Description WEST (DOWNSTREAM) SIDE

Trail Bridge Inspection Report

Pictures

PHOTO 5

Description GENERAL TOPSIDE VIEW LOOKING NORTH

PHOTO 6

Description TYPICAL SCALING OF TOP OF BACKWALL, NORTH END SHOWN

Trail Bridge Inspection Report

Pictures

PHOTO 7

Description TYPICAL CRACKING OF GROUT PADS FOR RAIL POST, EAST RAILING SHOWN

PHOTO 8

Description TYPICAL VIEW OF SCALING ON TOP OF DECK

Trail Bridge Inspection Report

Pictures

PHOTO 9

Description IMPACT DAMAGE TO EAST RAIL SOUTH POST

PHOTO 10

Description SETTLEMENT IN APPROACH PAVEMENT, SOUTH APPROACH SHOWN

Trail Bridge Inspection Report

Pictures

PHOTO 11

Description TYPICAL CRACKING OF APPROACH PAVEMENT, SOUTH APPROACH SHOWN

PHOTO 12

Description GENERAL UNDERSIDE VIEW LOOKING SOUTH

Trail Bridge Inspection Report

Pictures

PHOTO 13

Description TYPICAL TRANSVERSE CRACKING WITH EFFLORESCENCE ON DECK UNDERSIDE, NEAR

NORTH ABUTMENT SHOWN

PHOTO 14

Description SPALLING OF EAST DECK OVERHANG UNDERSIDE AT SOUTH ABUTMENT

Trail Bridge Inspection Report

Pictures

PHOTO 15

Description GENERAL VIEW OF SOUTH ABUTMENT

PHOTO 16

Description SOUTHEAST BEARING PAD SHIFTED NORTH AND LEADS SOUTH; NOTE MISSING ANCHOR

BOLT

Trail Bridge Inspection Report

Pictures

PHOTO 17

Description TYPICAL RUSTING OF CONNECTION HARDWARE FOR CROSS BRACE FRAMES, WEST

GIRDER CONNECTION AT SOUTH ABUTMENT SHOWN

PHOTO 18

Description TYPICAL VERTICAL CRACKING WITH EFFLORESCENCE ON ABUTMENT BACKWALLS, SOUTH ABUTMENT SHOWN

Trail Bridge Inspection Report

Pictures

PHOTO 19

Description VEGETATION GROWTH ON SOUTHEAST WINGWALL

PHOTO 20

Description BROKEN ANCHOR BOLT AT EXTERIOR SIDE OF NORTHWEST BEARING

Trail Bridge Inspection Report

Pictures

PHOTO 21

Description GENERAL VIEW OF NORTH ABUTMENT

PHOTO 22

Description UPSTREAM CHANNEL

Trail Bridge Inspection Report

Pictures

PHOTO 23

STRUCTURE SUMMARY STRUCTURE NO. 3300-046T

MOUNT VERNON TRAIL SOUTH BRIDGE INSPECTION DATE: 03/07/2023

north and south abutments at the time of inspection.

Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-046T

MOUNT VERNON TRAIL SOUTH BRIDGE INSPECTION DATE : 03/07/2023

226 PRIORITY OF IMPROVEMENT D

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

Item No.

Maintenance Recommendations

(GENERALLY NOT FLHP ELIGIBLE)

QTY. UNIT UNIT

COST

PRELIM.

COST

ESTIMATE

58.2

REPLACE EXPANSION JOINT MATERIAL AT BRIDGE ENDS.

1 LS

60.9

BACKFILL AND STABILIZE AREAS OF EROSION AND

UNDERMINING AT ABUTMENTS. 1 LS

58.6

REPLACE RAILING SLEEVES AND REALIGN RAILS AT

SOUTHEAST AND NORTHWEST CORNERS. 1 LS

59.11

REMOVE VEGETATION GROWTH UNDER SPAN #4.

1 LS

PRELIM. MAINTENANCE TOTAL :

Item REHABILITATION/RECONSTRUCTION

UNIT

UNIT PRELIM. COST ESTIMATES

No. (TYPICALLY NEEDED WITHIN 5 YEARS)

QTY. COST

REHAB RECONSTR

222.4 RESURFACE NORTH AND SOUTH APPROACH

PAVEMENT. 1 LS

CONTRACT COSTS FOR MOBILIZATION,

TRAFFIC CONTROL, AND CONTINGENCIES. 1 LS

PRELIM. REHABILITATION/RECONSTRUCTION TOTAL :

of 24

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-046T

MOUNT VERNON TRAIL SOUTH BRIDGE INSPECTION DATE : 03/07/2023

226 PRIORITY OF IMPROVEMENT D

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

COST ESTIMATE SUMMARY

PRELIM. MAINTENANCE TOTAL :

PRELIM. REHABILITATION TOTAL :

PRELIM. RECONSTRUCTION TOTAL : ..

TOTAL ITEMIZED COSTS:

PRELIMINARY ESTIMATE TOTAL * :

(*Includes typical contract costs for mobilization, traffic control and design/construction engineering: but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for planning purposes only; they should not be used as a complete or final engineers estimate.)

Remarks : Cost estimates assume that recommended actions will be combined with similar work being performed on other structures.

The structure will continue to be monitored for additional cracking and settlement.

STRUCTURE LOAD RATING STRUCTURE NO. 3300-046T

MOUNT VERNON TRAIL SOUTH BRIDGE INSPECTION DATE: 03/06/2023

TRUCK TYPE

INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)

TONS METRIC TONS TONS METRIC TONS

H 0 0 0 0

HS 0 0 0 0

TYPE 3 0 0 0 0

TYPE 3S2 0 0 0 0

TYPE 3-3 0 0 0 0

DESIGN LOADING: 7 - PEDESTRIAN

X CAPACITY MEETS OR EXCEEDS DESIGN LOAD

CAPACITY IS LESS THAN DESIGN LOAD

ORIGINAL LOAD RATING CALCULATION APPLICABLE

ORIGINAL LOAD RATING CALCULATION REVISED

DATE OF LOAD RATING CALCULATION:

LOAD RATING CONTROLLED BY:

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-046T

STRUCTURE IDENTIFICATION

(201) PARK: GEORGE WASHINGTON MEMORIAL PARKWAY

(202) STRUCTURE NAME:..............MOUNT VERNON TRAIL SOUTH

BRIDGE

(203) STRUCTURE KIND:............... 4 - TRAIL BRIDGE

(204) STRUCTURE NUMBER:.........3300-046 T

2 - NATIONAL CAPITAL(205) NPS REGION:

(206) ROUTE CODE NUMBER:

(207) ROAD SECTION NO:............. 046T

(208) NPS ROAD CLASS:............... 6 - RESTRICTED

(209) WITHIN NPS BNDRY?:.......... Yes

(210) OPERATING UNIT:.................PARK

(211) PROJECT NO(S):

(212) DRAWING NUMBERS:...........DJAC11

(21) MAINTAINED BY:......................66 - NATIONAL PARK SERVICE

(22) OWNER:................................... 66 - NATIONAL PARK SERVICE

(1) STATE:

(2) STATE HWY. AGENCY DIST:

(3) COUNTY CODE:

(4) CITY / PLACE CODE:

(5) INVENTORY ROUTE:

(6) FEATURES INTERSECTED:

(7) FACILITY CARRIED:

(8) STATE STRUCTURE NO:

(9) LOCATION:

(10) INV. RTE. - MIN. VERT. CLR:

(11) MILE POINT:

(27) YEAR BUILT:

(106) YEAR RECONSTRUCTED:

(20) TOLL:

(37) HISTORIC DESIGNATION:

513 - VIRGINIA

51013 ARLINGTON

00000

1 6 7 00000 0

RAMP GW & CRYSTAL CITY TRAIL

CONN.

MOUNT VERNON TRAIL

3300046T0000000

ADJACENT TO GWMP NEAR REAGAN

NATIONAL AIRPORT.

14.75 FT ( 4.5 M)

(KM PT: 0 )

3 - ON FREE ROAD

5 - NOT ELIGIBLE

STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE

(43A) MAIN STR. MATERIAL:..........2 - CONCRETE CONTINUOUS (44A) APPR. STR. MATERIAL:............ 0 - Other

(43B) MAIN STR. TYPE:.................. 06 - BOX BEAM OR GIRDERS - (44B) APPR. STR. TYPE:.................... 00 - OTHER

SINGLE OR SPREAD

(45) NO. OF MAIN SPANS:..............004 (46) NO OF APPROACH SPANS:

(48) MAX. SPAN LENGTH:..............75 FT ( 22.9 M)

(49) STRUCTURE LENGTH:........... 240. FT ( 73.2 M) (108) WEAR SURFACE/PROTECT SYSTEM:

(216A) ABUTMENT #1 FDN:........... 3 - SPREAD FOOTING ON PILES A) TYPE WEARING SURFACE:.. 0 - NONE

(216B) ABUTMENT #2 FDN:........... 3 - SPREAD FOOTING ON PILES B) TYPE MEMBRANE:................. 0 - NONE

(217A) PREDOM. PIER FDN:.......... 3 - SPREAD FOOTING ON PILES C) TYPE PROTECTION:.............. 0 - NONE

(217B) SECOND. PIER FDN:.......... 0 - UNKNOWN (218) IS SALT USED?.......................... NO

(107) DECK TYPE:.......................... 1 - CONCRETE CAST-IN-PLACE

LOAD RATING AND POSTING

(31) DESIGN LOAD:.........................7 - PEDESTRIAN (41) LOAD RESTRICTION:.................. A - OPEN

(66) INVENTORY RATING:..............0 METRIC TONS) (70) BRIDGE POSTING:...................... 5 - EQUAL TO OR ABOVE LEGALTONS ( 0

LOADS

(64) OPERATING RATING:..............0 TONS ( 0 METRIC TONS)

INSPECTION DATES

(90) INSPECTION DATE: 03/07/2023 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):

(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL:.......... N

(220) SPECIAL STUDY TYPE: 0 - NONE INSP. EVERY MONTHS - LAST INSP:

(221) SPECIAL STUDY DATE: (B) UNDERWATER:..................... N

INSP. EVERY MONTHS - LAST INSP:

(C) SPECIAL INSPECTION:........ N

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-046T

GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA

(16) LATITUDE:................................ 38° 51'22.60" (51) CURB TO CURB WIDTH:............ 12.0 FT ( 3.7 M)

(17) LONGITUDE:............................ 77 02° '46 90 " (52) DECK WIDTH:.......................... 14.0 FT ( 4.3 M)

(19) DETOUR LENGTH:.................. 0 MI ( 0 KM) (32) APPR. ROADWAY WIDTH:...... 14.0 FT ( 4.3 M)

(28A) LANES ON STRUCT:.............00 (213) APPR. PAVEMENT WIDTH:... 14.0 FT ( 4.3 M)

(28B) LANES UNDER STRUCT:......01 LEFT SHOULDER:............... 0 0 FT ( 0 M)

(42A) SERVICE ON:.........................3 - PEDESTRIAN-BICYCLE RIGHT SHOULDER:.......... 0 0 FT ( 0 M)

(42B) SERVICE UNDER:................. 1 - HIGHWAY, WITH OR W/OUT (33) BRIDGE MEDIAN:.................... 0 - NO MEDIAN

PEDESTRIAN

(29) AVG DAILY TRAFFIC:..............0 (34) SKEW ANGLE:......................... 0 °

(30) YEAR OF ADT:......................... 2013 (35) STRUCTURE FLARED:............ 0 - NO FLARE

(114) FUTURE ADT:.........................0 (47) TOTAL HORIZ. CLEARANCE:.. 72 FT ( 21.9 M)

(115) YEAR OF FUTURE ADT:........2033 (50) SIDEWALKS

(101) PARALLEL STRUCTURE:......N - NO PARALLEL STRUCTURE LEFT:.................................... 0 FT ( 0 M)

(38) NAVIGATION CONTROL:.........N - NOT APPLICABLE, NO RIGHT:.................................. 0 FT ( 0 M)

WATERWAY

(39) VERTICAL CLEARANCE:.........0 FT ( 0 M) (214) BRIDGE RAIL TYPE

(40) HORIZ. CLEARANCE:..............0 FT ( 0 M) RAIL CONFIGURATION:...... 2 - MOUNTED ON PARAPET

(111) ABUT OR PIER PROT:........... MATERIAL:........................... 3 - CONCRETE/STEEL

LATERAL UNDERCLEARANCE: DESIGN TYPE:..................... 1 - CONTINUOUS RAIL

(55) RIGHT:...............................10.00 FT ( 3.05 M) (215) BRIDGE RAIL HEIGHT:.......... 4 54 FT ( 1 38 M)

(56) LEFT:................................. FT ( 0 M) (53) MIN. VRT. CLR. OVER DECK: 99.99 FT ( 99.99 M)

(54) MIN. VRT. UNDRCLRANCE:... 14.75 FT ( 4.5 M)

CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST

(58) DECK:

(59) SUPERSTRUCTURE:

(60) SUBSTRUCTURE:

(61) CHANNEL:................................N

(62) CULVERT:.................................N

(222) APPROACHES:

(223) RETAINING WALL:.................N

(36) TRAFFIC SAFETY FEAT: N N N N

(75A) TYPE OF WORK:................... 35 - REHABILITATION - DETERIORATION

(75B) WORK DONE BY:.................. 1 - WORK TO BE DONE BY CONTRACT

(76) IMPROVEMENT LENGTH:.......0 FT ( 0 M)

(67) STRUCTURAL EVALUATION:

(68) DECK GEOMETRY:

(69) UNDERCLEARANCES:................ N

(71) WATERWAY ADEQUACY:........... N

(72) APPROACH ALIGNMENT:

(113) SCOUR CRITICAL:.................... N - NOT OVER WATERWAY

(225) PURPOSE OF IMPROVEMENT: 2 - REHAB/RECONSTRUCTION

(226) PRIORITY OF IMPROVEMENT: D - MINOR

(227) MAINTENANCE COST:

(228) REHAB / RECNSTR COST:

(229) CONSTRUCTION COST:

(230) STRUCTURE HISTORY:

(231) ADDITIONAL CONSIDERATIONS:

(330) ADDITIONAL CONFIGURATION INFORMATION:

SPANS #1 AND #4 - 45'; SPANS #2 AND #3 - 75'.

ADDITIONAL INFORMATION

Inspector: Joe Koenig Structure Number: 3300046T0000000

Inspection Date: 03/07/2023 Facility Carried: MOUNT VERNON TRAI

Trail Bridge Inspection Report

Pictures

PHOTO 3

Description LOOKING SOUTH TOWARD MT. VERNON

PHOTO 4

Description WEST SIDE

Trail Bridge Inspection Report

Pictures

PHOTO 5

Description GENERAL TOPSIDE VIEW LOOKING SOUTH

PHOTO 6

Description ASPHALT PATCH ADJACENT TO BACKWALL AT EAST SIDE OF NORTH APPROACH HAS

FAILED; NOTE CRACK IN APPROACH PAVEMENT

Trail Bridge Inspection Report

Pictures

PHOTO 7

Description SETTLEMENT OF NORTH APPROACH PAVEMENT AT NORTH ABUTMENT

PHOTO 8

Description EDGE SPALLS AND HAIRLINE LONGITUDINAL CRACKS IN TOP OF NORTH ABUTMENT

BACKWALL

Trail Bridge Inspection Report

Pictures

PHOTO 9

Description CRACKING OF NORTHEAST WINGWALL MORTAR JOINTS

PHOTO 10

Description MISSING RAIL SLEEVES DUE TO MISALIGNMENT OF RAILS AT WEST SIDE NEAR NORTH

ABUTMENT

Trail Bridge Inspection Report

Pictures

PHOTO 11

Description SPALL IN DECK SURFACE OF NORTH SPAN; NOTE DETERIORATED LANE STRIPING

PHOTO 12

Description TYPICAL VIEW OF FLAKING PAINT ON BRIDGE RAILS, WEST RAILING IN NORTH SPAN

Trail Bridge Inspection Report

Pictures

PHOTO 13

Description RANDOM CRACKING IN DECK SURFACE, NORTH SPAN SHOWN

PHOTO 14

Description TYPICAL VERTICAL CRACKING OF PARAPETS WITH EFFLORESCENCE, WEST PARAPET

OVER SOUTH PIER SHOWN

Trail Bridge Inspection Report

Pictures

PHOTO 15

Description EXPANSION JOINT SEALANT AND ASPHALT DETERIORATED AT SOUTH ABUTMENT

PHOTO 16

Description APPROACH PAVEMENT DETERIORATION AT SOUTH APPROACH ON EAST SIDE ADJACENT

TO BACKWALL; NOTE GAP BETWEEN BRIDGE AND APPROACH PARAPET DUE TO FAILED

PATCH

Trail Bridge Inspection Report

Pictures

PHOTO 17

Description EROSION ALONG SOUTHWEST WINGWALL

PHOTO 18

Description GENERAL UNDERSIDE VIEW OF SPAN #3 LOOKING NORTH

Trail Bridge Inspection Report

Pictures

PHOTO 19

Description TYPICAL RANDOM CRACKING WITH EFFLORESCENCE ON SIDES OF BOX GIRDERS AT

PIERS, WEST SIDE OVER CENTER PIER SHOWN

PHOTO 20

Description TYPICAL RANDOM TRANSVERSE CRACKING WITH STAINING AND EFFLORESCENCE ON

BOX GIRDER UNDERSIDE, WEST SIDE OF SPAN #3 AT MIDSPAN SHOWN

Trail Bridge Inspection Report

Pictures

PHOTO 21

Description DELAMINATION ON EAST SIDE OF BOX GIRDER UNDERSIDE IN SPAN #3

PHOTO 22

Description SPALL ON BOX GIRDER UNDERSIDE IN SPAN #3 ON WEST SIDE

Trail Bridge Inspection Report

Pictures

PHOTO 23

Description GENERAL VIEW OF SOUTH ABUTMENT; NOTE HOMELESS ACTIVITY

PHOTO 24

Description GENERAL VIEW OF SOUTH PIER, SOUTH FACE

Trail Bridge Inspection Report

Pictures

PHOTO 25

Description GENERAL VIEW OF NORTH ABUTMENT

PHOTO 26

Description LEANING EAST BEARING PAD AT NORTH ABUTMENT

STRUCTURE SUMMARY STRUCTURE NO. 3300-047T

MOUNT VERNON TRAIL NORTH BRIDGE INSPECTION DATE: 03/07/2023

of the approach pavement adjacent to the backwall.

Since the previous inspection, erosion and undermining along the east side of the north abutment slope protection has been partially repaired.

Corrective action should be taken as outlined in this report to prevent the possible development of more serious or costly problems in the future.

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-047T

MOUNT VERNON TRAIL NORTH BRIDGE INSPECTION DATE : 03/07/2023

226 PRIORITY OF IMPROVEMENT D

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

Item No.

Maintenance Recommendations

(GENERALLY NOT FLHP ELIGIBLE)

QTY. UNIT UNIT

COST

PRELIM.

COST

ESTIMATE

60.9

REPAIR EROSION AND UNDERMINING ON BOTH SIDES OF

NORTH SLOPE PROTECTION. 1 LS

60.1

REPAIR LOOSE MASONRY STONE AT WEST END OF

SOUTH ABUTMENT. 1 LS

PRELIM. MAINTENANCE TOTAL :

Item REHABILITATION/RECONSTRUCTION

UNIT

UNIT PRELIM. COST ESTIMATES

No. (TYPICALLY NEEDED WITHIN 5 YEARS)

QTY. COST

REHAB RECONSTR

222.4 REPAVE NORTH APPROACH. PATCH POTHOLE

AT SOUTHWEST AND SOUTHEAST CORNER OF

APPROACH PAVEMENT. RESEAL TRANSVERSE

CRACK AT SOUTH APPROACH.

1 LS

223.1 CLEAN AND COAT REBAR WITH APPROVED

PRODUCT AND PATCH SPALLS ON PANELS OF

NORTHEAST RETAINING WALL.

1 LS

58.2 REPLACE DECK EXPANSION JOINT SEALS

WITH PROPERLY SIZED MATERIAL. 1 LS

CONTRACT COSTS FOR MOBILIZATION,

TRAFFIC CONTROL, AND CONTINGENCIES. 1 LS

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-047T

MOUNT VERNON TRAIL NORTH BRIDGE INSPECTION DATE : 03/07/2023

226 PRIORITY OF IMPROVEMENT D

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

COST ESTIMATE SUMMARY

PRELIM. MAINTENANCE TOTAL :

PRELIM. REHABILITATION TOTAL :

PRELIM. RECONSTRUCTION TOTAL : ..

TOTAL ITEMIZED COSTS:

PRELIMINARY ESTIMATE TOTAL * :

(*Includes typical contract costs for mobilization, traffic control and design/construction engineering: but does not include detour bridges, work beyond the bridge limits, or work not listed above. Estimates are approximate and are for planning purposes only; they should not be used as a complete or final engineers estimate.)

Remarks : Cost estimates assume that recommended actions will be combined with similar work being performed on other

STRUCTURE LOAD RATING STRUCTURE NO. 3300-047T

MOUNT VERNON TRAIL NORTH BRIDGE INSPECTION DATE: 03/06/2023

TRUCK TYPE

INVENTORY RATING (NORMAL TRAFFIC) OPERATING RATING (MAXIMUM LOAD)

TONS METRIC TONS TONS METRIC TONS

H 0 0 0 0

HS 0 0 0 0

TYPE 3 0 0 0 0

TYPE 3S2 0 0 0 0

TYPE 3-3 0 0 0 0

DESIGN LOADING: 7 - PEDESTRIAN

X CAPACITY MEETS OR EXCEEDS DESIGN LOAD

CAPACITY IS LESS THAN DESIGN LOAD

ORIGINAL LOAD RATING CALCULATION APPLICABLE

ORIGINAL LOAD RATING CALCULATION REVISED

DATE OF LOAD RATING CALCULATION:

LOAD RATING CONTROLLED BY:

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-047T

STRUCTURE IDENTIFICATION

(201) PARK: GEORGE WASHINGTON MEMORIAL PARKWAY

(202) STRUCTURE NAME:..............MOUNT VERNON TRAIL NORTH

BRIDGE

(203) STRUCTURE KIND:............... 4 - TRAIL BRIDGE

(204) STRUCTURE NUMBER:.........3300-047 T

2 - NATIONAL CAPITAL(205) NPS REGION:

(206) ROUTE CODE NUMBER:

(207) ROAD SECTION NO:............. 047T

(208) NPS ROAD CLASS:............... 7 - URBAN PARKWAY

(209) WITHIN NPS BNDRY?:.......... Yes

(210) OPERATING UNIT:.................PARK

(211) PROJECT NO(S):

(212) DRAWING NUMBERS:...........DJAC11

(21) MAINTAINED BY:......................66 - NATIONAL PARK SERVICE

(22) OWNER:................................... 66 - NATIONAL PARK SERVICE

(1) STATE:

(2) STATE HWY. AGENCY DIST:

(3) COUNTY CODE:

(4) CITY / PLACE CODE:

(5) INVENTORY ROUTE:

(6) FEATURES INTERSECTED:

(7) FACILITY CARRIED:

(8) STATE STRUCTURE NO:

(9) LOCATION:

(10) INV. RTE. - MIN. VERT. CLR:

(11) MILE POINT:

(27) YEAR BUILT:

(106) YEAR RECONSTRUCTED:

(20) TOLL:

(37) HISTORIC DESIGNATION:

513 - VIRGINIA

51013 ARLINGTON

00000

2 6 7 00000 0

RAMP "M"

MOUNT VERNON TRAIL

3300047T0000000

ADJACENT TO GWMP NEAR REAGAN

NATIONAL AIRPORT.

15.75 FT ( 4.8 M)

(KM PT: 0 )

3 - ON FREE ROAD

5 - NOT ELIGIBLE

STRUCTURE DESCRIPTION, FOUNDATION, AND DECK TYPE

(43A) MAIN STR. MATERIAL:..........2 - CONCRETE CONTINUOUS (44A) APPR. STR. MATERIAL:............ 0 - Other

(43B) MAIN STR. TYPE:.................. 06 - BOX BEAM OR GIRDERS - (44B) APPR. STR. TYPE:.................... 00 - OTHER

SINGLE OR SPREAD

(45) NO. OF MAIN SPANS:..............004 (46) NO OF APPROACH SPANS:

(48) MAX. SPAN LENGTH:..............85 FT ( 25.9 M)

(49) STRUCTURE LENGTH:........... 300. FT ( 91.4 M) (108) WEAR SURFACE/PROTECT SYSTEM:

(216A) ABUTMENT #1 FDN:........... 3 - SPREAD FOOTING ON PILES A) TYPE WEARING SURFACE:.. 0 - NONE

(216B) ABUTMENT #2 FDN:........... 3 - SPREAD FOOTING ON PILES B) TYPE MEMBRANE:................. 0 - NONE

(217A) PREDOM. PIER FDN:.......... 3 - SPREAD FOOTING ON PILES C) TYPE PROTECTION:.............. 0 - NONE

(217B) SECOND. PIER FDN:.......... 3 - SPREAD FOOTING ON PILES (218) IS SALT USED?.......................... NO

(107) DECK TYPE:.......................... 1 - CONCRETE CAST-IN-PLACE

LOAD RATING AND POSTING

(31) DESIGN LOAD:.........................7 - PEDESTRIAN (41) LOAD RESTRICTION:.................. A - OPEN

(66) INVENTORY RATING:..............0 METRIC TONS) (70) BRIDGE POSTING:...................... 5 - EQUAL TO OR ABOVE LEGALTONS ( 0

LOADS

(64) OPERATING RATING:..............0 TONS ( 0 METRIC TONS)

INSPECTION DATES

(90) INSPECTION DATE: 03/07/2023 (91) FREQ. OF INSP: 24 MONTHS (92 / 93) CRITICAL FEATURE INSPECTION (CFI):

(219) ADD. STUDIES NEEDED: N - 0 - NONE (A) FRACTURE CRITICAL:.......... N

(220) SPECIAL STUDY TYPE: 0 - NONE INSP. EVERY MONTHS - LAST INSP:

(221) SPECIAL STUDY DATE: (B) UNDERWATER:..................... N

INSP. EVERY MONTHS - LAST INSP:

(C) SPECIAL INSPECTION:........ N

STRUCTURE INVENTORY AND APPRAISAL STRUCTURE NO. 3300-047T

GEOMETRY, TRAFFIC, AND NAVIGATIONAL DATA

(16) LATITUDE:................................ 38° 51'35.60" (51) CURB TO CURB WIDTH:............ 11.2 FT ( 3.4 M)

(17) LONGITUDE:............................ 77°02 '43 90" (52) DECK WIDTH:.......................... 14.0 FT ( 4.3 M)

(19) DETOUR LENGTH:.................. 0 MI ( 0 KM) (32) APPR. ROADWAY WIDTH:...... 10.0 FT ( 3 M)

(28A) LANES ON STRUCT:.............00 (213) APPR. PAVEMENT WIDTH:... 10.0 FT ( 3 M)

(28B) LANES UNDER STRUCT:......01 LEFT SHOULDER:............... 0 0 FT ( 0 M)

(42A) SERVICE ON:.........................3 - PEDESTRIAN-BICYCLE RIGHT SHOULDER:.......... 0 0 FT ( 0 M)

(42B) SERVICE UNDER:................. 1 - HIGHWAY, WITH OR W/OUT (33) BRIDGE MEDIAN:.................... 0 - NO MEDIAN

PEDESTRIAN

(29) AVG DAILY TRAFFIC:..............0 (34) SKEW ANGLE:......................... 0 °

(30) YEAR OF ADT:......................... 2013 (35) STRUCTURE FLARED:............ 0 - NO FLARE

(114) FUTURE ADT:.........................0 (47) TOTAL HORIZ. CLEARANCE:.. 11.2 FT ( 3.4 M)

(115) YEAR OF FUTURE ADT:........2033 (50) SIDEWALKS

(101) PARALLEL STRUCTURE:......N - NO PARALLEL STRUCTURE LEFT:.................................... 0 0 FT ( 0 M)

(38) NAVIGATION CONTROL:.........N - NOT APPLICABLE, NO RIGHT:.................................. 0 0 FT ( 0 M)

WATERWAY

(39) VERTICAL CLEARANCE:.........0 FT ( 0 M) (214) BRIDGE RAIL TYPE

2 - MOUNTED ON PARAPET(40) HORIZ. CLEARANCE:..............0 FT ( 0 M) RAIL CONFIGURATION:

(111) ABUT OR PIER PROT:...........2 - IN PLACE AND FUNCTIONING MATERIAL:........................... 3 - CONCRETE/STEEL

LATERAL UNDERCLEARANCE: DESIGN TYPE:..................... 1 - CONTINUOUS RAIL

(55) RIGHT:...............................4.00 FT ( 1.22 M) (215) BRIDGE RAIL HEIGHT:.......... 4 54 FT ( 1 38 M)

(56) LEFT:................................ 0 FT ( 0 M) (53) MIN. VRT. CLR. OVER DECK: 99.99 FT ( 99.99 M)

(54) MIN. VRT. UNDRCLRANCE:... 15.58 FT ( 4.75 M)

CONDITION AND APPRAISAL DATA, PROPOSED IMPROVEMENTS, AND COST

(58) DECK:....................................... 6 (67) STRUCTURAL EVALUATION:

(59) SUPERSTRUCTURE:...............6 (68) DECK GEOMETRY:

(60) SUBSTRUCTURE:.......... 7 (69) UNDERCLEARANCES:

(61) CHANNEL:................................N (71) WATERWAY ADEQUACY:........... N

(62) CULVERT:.................................N (72) APPROACH ALIGNMENT:

(222) APPROACHES:...................... 5 (113) SCOUR CRITICAL:.................... N - NOT OVER WATERWAY

(223) RETAINING WALL:.................6 (225) PURPOSE OF IMPROVEMENT: 2 - REHAB/RECONSTRUCTION

(36) TRAFFIC SAFETY FEAT: N N N N (226) PRIORITY OF IMPROVEMENT: D - MINOR

(75A) TYPE OF WORK:................... (227) MAINTENANCE COST:

(75B) WORK DONE BY:.................. (228) REHAB / RECNSTR COST:

(76) IMPROVEMENT LENGTH:....... FT ( 0 M) (229) CONSTRUCTION COST:

ADDITIONAL INFORMATION

(230) STRUCTURE HISTORY:

(231) ADDITIONAL CONSIDERATIONS:

(330) ADDITIONAL CONFIGURATION INFORMATION:

SPANS #1 AND #4 - 65'; SPANS #2 AND #3 - 85'.

Inspector: Joe Koenig Structure Number: 3300047T0000000

Trail Bridge Inspection Report

Pictures

PHOTO 3

Description LOOKING SOUTH TOWARD MOUNT VERNON

PHOTO 4

Description EAST SIDE

Trail Bridge Inspection Report

Pictures

PHOTO 5

Description GENERAL TOPSIDE VIEW LOOKING SOUTH

PHOTO 6

Description TYPICAL TRANSVERSE CRACKS AND POPOUT SPALLS ON TOP OF DECK, SPAN #1

Trail Bridge Inspection Report

Pictures

PHOTO 7

Description LONGITUDINAL CRACKS IN NORTH APPROACH PAVEMENT; NOTE AREA OF SETTLEMENT

ON WEST SHOULDER

PHOTO 8

Description TRANSITION BETWEEN APPROACH RAIL AND BRIDGE RAIL AT NORTHWEST CORNER;

NOTE DIFFERENCE IN HEIGHT OF RAILS

Trail Bridge Inspection Report

Pictures

PHOTO 9

Description TYPICAL GAP BETWEEN APPROACH PARAPET AND BRIDGE PARAPET, WEST SIDE OF

NORTH ABUTMENT SHOWN; NOTE GAP BETWEEN EXPANSION JOINT MATERIAL AND

BACKWALL OF NORTH ABUTMENT

PHOTO 10

Description DETERIORATION OF PATCH REPAIR AT NORTHEAST CORNER OF NORTH ABUTMENT

Trail Bridge Inspection Report

Pictures

PHOTO 11

Description SETTLEMENT ALONG NORTH APPROACH PAVEMENT, NORTHWEST CORNER SHOWN

PHOTO 12

Description TYPICAL VERTICAL CRACKING OF PARAPETS WITH EFFLORESCENCE, WEST PARAPET

OVER CENTER PIER SHOWN

Trail Bridge Inspection Report

Pictures

PHOTO 13

Description LONGITUDINAL SAWCUT IN WEST SHOULDER OF NORTH APPROACH

PHOTO 14

Description TRANSVERSE CRACK IN SOUTH APPROACH PAVEMENT; NOTE FAILED CRACK SEALANT

Trail Bridge Inspection Report

Pictures

PHOTO 15

Description POTHOLE ON WEST SIDE OF SOUTH APPROACH PAVEMENT ADJACENT TO SOUTH

ABUTMENT BACKWALL

PHOTO 16

Description EFFECTS OF WINGWALL LEANING TOWARDS THE WEST, OVER SOUTH EXPANSION JOINT

Trail Bridge Inspection Report

Pictures

PHOTO 17

Description GENERAL UNDERSIDE VIEW OF SPAN #2 LOOKING SOUTH

PHOTO 18

Description GENERAL OF NORTH ABUTMENT

Trail Bridge Inspection Report

Pictures

PHOTO 19

Description EROSION AND UNDERMINING ALONG WEST EDGE OF NORTH ABUTMENT SLOPE

PROTECTION

PHOTO 20

Description EROSION AND UNDERMINING ALONG EAST EDGE OF NORTH ABUTMENT SLOPE

PROTECTION

Trail Bridge Inspection Report

Pictures

PHOTO 21

Description DEBRIS ACCUMULATION ON NORTH ABUTMENT BREASTWALL

PHOTO 22

Description TYPICAL STAINING ON GIRDERS UNDER DRAIN PIPES, WEST SIDE OVER NORTH PIER

Trail Bridge Inspection Report

Pictures

PHOTO 23

Description TYPICAL RANDOM CRACKING WITH EFFLORESCENCE OF BOX GIRDER SIDES OVER

PIERS, EAST SIDE OVER NORTH PIER SHOWN

PHOTO 24

Description GENERAL VIEW OF NORTH PIER, NORTH FACE

Trail Bridge Inspection Report

Pictures

PHOTO 25

Description TYPICAL TRANSVERSE CRACKING OF BOX GIRDER UNDERSIDE AT MIDSPAN, EAST SIDE

OF SPAN #4 SHOWN

PHOTO 26

Description VIEW OF LOOSE MASONRY STONE ON WEST SIDE OF SOUTH ABUTMENT BREASTWALL

Trail Bridge Inspection Report

Pictures

PHOTO 27

Description EFFLORESCENCE ON NORTHWEST WINGWALL

PHOTO 28

Description BROKEN RETAINING WALL PANEL WITH EXPOSED REBAR ON EAST SIDE OF NORTH

APPROACH, APPROXIMATELY 75' FROM NORTH ABUTMENT

Trail Bridge Inspection Report

Pictures

PHOTO 29

Description BROKEN RETAINING WALL PANEL WITH EXPOSED REBAR ON EAST SIDE OF NORTH

APPROACH, APPROXIMATELY 150' FROM NORTH ABUTMENT

RECOMMENDATIONS AND ESTIMATED COSTS STRUCTURE NO. 3300-020P

HUMPBACK BRIDGE INSPECTION DATE : 04/17/2023

226 PRIORITY OF IMPROVEMENT D

A (Critical) - Structure is closed, in immediate damage of collapse, or presents a critical safety danger.

B (Major) - Structure is seriously deficient or presents a safety hazard, but can remain open at reduced loads or with frequent inspections.

C (Moderate) - Structure is deficient, functionally obsolete, or requires substantial repairs to prevent a serious deficiency or unsafe condition.

D (Minor) - Structure is generally in good condition. Preventive maintenance may be required.

E (Special) - Structure is under construction or reconstruction.

Item No.

Maintenance Recommendations

(GENERALLY NOT FLHP ELIGIBLE)

QTY. UNIT UNIT

COST

PRELIM.

COST

ESTIMATE

58.5

REPAIR SETTLEMENT OF EAST SIDEWALK AT NORTH

APPROACH. 1 LS

222.4

PATCH POTHOLES IN APPROACH PAVEMENT.

1 LS

61.5

VERIFY…