Results of Bid Opening - Project TN NP GRSM 21(1).pdf
PDF 117 KB Posted
- Solicitation number
- 693C73-24-B-000016
About this file
This document is the results of a bid opening for a federal construction project solicitation. The solicitation is for the rehabilitation of the Cosby Government Quarters and Ranger Station Access Road in Great Smoky Mountains National Park, located in Cocke County, Tennessee. The project consists of asphalt paving, drainage improvements, shoulder and ditch work, signage replacement, pavement markings, culvert work, and turf establishment. The total project is expected to cost between $2,000,000 and $5,000,000, and is set aside for certified small business concerns only. Bids were received from five companies, with the lowest total bid being $3,997,070 from Central Southern Construction Corp. The government's estimate for the total project was $4,900,000. The project has multiple schedules/options, and if all schedules are awarded, the construction activities must be completed by May 20, 2025. The solicitation number is 693C73-24-B-000016, and the bid opening was held on August 29, 2024.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Federal Highway Administration Eastern Federal Lands Highway Division
Bid Opening for
Great Smoky Mountains National Park
PROJECT: TN NP GRSM 21(1)
SOLICITATION NO. 693C73-24-B-000016
August 29, 2024, at 2:00 p.m.
Ashburn, VA
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
BID OPENING for SOLICITATION NO. 693C73-24-B-000016 Project: TN NP GRSM 21(1)
August 29, 2024, 2:00 p.m. local time
BIDDERS BID TOTALS TOTAL PRICE
Bluegrass Contracting Corporation SCHEDULE A
$4,196,620.00
SCHEDULE B (GOVERNMENT OPTION 1)
$1,597,295.00
SCHEDULE C (GOVERNMENT OPTION 2)
$605,115.00
SCHEDULE D (GOVERNMENT OPTION 3)
$475,725.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$6,874,755.00
Bryant’s Land & Development Industries, Inc.
SCHEDULE A
$3,553,136.18
SCHEDULE B (GOVERNMENT OPTION 1)
$1,347,860.92
SCHEDULE C (GOVERNMENT OPTION 2)
$614,584.24
SCHEDULE D (GOVERNMENT OPTION 3)
$590,712.68
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$6,106,294.02
If the Government awards the contract as Schedules A+B+C+D, then all construction activities at the project site must be completed by no later than May 20, 2025.
If Schedules A+B+C+D are not awarded at the same time, the period of performance will not change.
BID OPENING for SOLICITATION NO. 693C73-24-B-000016 Project: TN NP GRSM 21(1)
August 29, 2024, 2:00 p.m. local time
BIDDERS BID TOTALS TOTAL PRICE
Central Southern Construction Corp. SCHEDULE A
$2,709,250.00
SCHEDULE B (GOVERNMENT OPTION 1)
$650,600.00
SCHEDULE C (GOVERNMENT OPTION 2)
$317,745.00
SCHEDULE D (GOVERNMENT OPTION 3)
$319,475.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$3,997,070.00
Eclipse Co., LLC SCHEDULE A
$4,523,303.12
SCHEDULE B (GOVERNMENT OPTION 1)
$1,467,299.70
SCHEDULE C (GOVERNMENT OPTION 2)
$679,419.65
SCHEDULE D (GOVERNMENT OPTION 3)
$678,897.53
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$7,348,920.00
Estes Bros. Const., Inc. SCHEDULE A
$3,396,019.15
SCHEDULE B (GOVERNMENT OPTION 1)
$1,816,745.00
SCHEDULE C (GOVERNMENT OPTION 2)
$590,660.81
SCHEDULE D (GOVERNMENT OPTION 3)
$896,327.45
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$6,699,752.41
If the Government awards the contract as Schedules A+B+C+D, then all construction
BID OPENING for SOLICITATION NO. 693C73-24-B-000016 Project: TN NP GRSM 21(1)
August 29, 2024, 2:00 p.m. local time
BIDDERS BID TOTALS TOTAL PRICE
Pigott Asphalt and Sitework, LLC SCHEDULE A
$4,008,685.24
SCHEDULE B (GOVERNMENT OPTION 1)
$1,425,125.00
SCHEDULE C (GOVERNMENT OPTION 2)
$580,125.00
SCHEDULE D (GOVERNMENT OPTION 3)
$974,000.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$6,987,935.24
Engineer’s Estimate
SCHEDULE A
$2,900,000
SCHEDULE B (GOVERNMENT OPTION 1)
$1,270,000.00
SCHEDULE C (GOVERNMENT OPTION 2)
$360,000.00
SCHEDULE D (GOVERNMENT OPTION 3)
$370,000.00
SCHEDULE A + OPTION 1 + OPTION 2 + OPTION 3 =
$4,900,000.00
If the Government awards the contract as Schedules A+B+C+D, then all construction
| Slide Number 1 |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-24-B-000016� Project: TN NP GRSM 21(1)�August 29, 2024, 2:00 p.m. local time � |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-24-B-000016� Project: TN NP GRSM 21(1)�August 29, 2024, 2:00 p.m. local time � |
| �FEDERAL HIGHWAY ADMINISTRATION�EASTERN FEDERAL LANDS HIGHWAY DIVISION�BID OPENING for SOLICITATION NO. 693C73-24-B-000016� Project: TN NP GRSM 21(1)�August 29, 2024, 2:00 p.m. local time � |