This document provides an amendment and questions and answers related to a solicitation for pavement rehabilitation work on the Foothills Parkway in the Great Smoky Mountains National Park.
The amendment extends the proposal due date to November 9, 2021 at 2:00 PM EST for Solicitation Number 693C73-22-R-000001. It also provides responses to questions from potential offerors regarding full depth reclamation mix design responsibilities, closure times and locations, water and spoils disposal, and timelines. The questions and answers cover topics such as the FDR depth and mix, closure periods in 2022 and 2023, obtaining water, and disposing of spoils.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
693C7322R000001 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
ASHBURN VA 20147
ATTN: CONSTRUCTION
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
ASHBURN VA 20147
ATTN: ACQUISITIONS
693C73
SUITE E2-3-300
QUANTUM PARK, 22001 LOUDOUN COUNTY PKWY
EASTERN FEDERAL LANDS HIGHWAY DIVISION
FEDERAL HIGHWAY ADMINISTRATION
See Block 1410/25/20210001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
10/06/2021
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project NP-FOOT 8G16, 8H10
The purpose of this Amendment is to:
1) Provide a summary of responses to questions/clarifications asked by potential offerors.
2) The Proposal due date remains November 9, 2021 at 2:00 p.m. EST.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Amendment No. 0001
Info Page 1 of 1
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
EASTERN FEDERAL LANDS HIGHWAY DIVISION
Amendment No. 0001
NP-FOOT 8G16, 8H10
Great Smoky Mountains National Park
Pavement Rehabilitation of Foothills Parkway West (Sections 8G and 8H)
Solicitation: 693C73-22-R-000001
The purpose of this Amendment is to:
1) Provide a summary of responses to questions/clarifications asked by potential offerors.
2) The Proposal due date remains November 9, 2021 at 2:00 p.m. EST.
NP‐FOOT 8G16, 8H10
Questions / Clarifications
Bidders can send written questions or inquiries for clarification to: eflhd.contracts@dot.gov.
Questions can be submitted at any time, but questions submitted within 7 days of the bid opening may not be answered in time for the bidder to properly incorporate the responses into their bids.
The following questions and issues were submitted via email. The Government response or clarification is provided. Due to the repetitive nature of several questions and issues, the wording of the questions may have been revised and some questions have not been included.
The Government’s direct response to the sender may also have been updated below for better clarity.
1. Table 305-1 gives us the Soil-Aggregate-Cement Mix Design Parameters. However, does the FHWA have data from an exploratory report/mix design they can share of the in-situ material PCF and successful cement application rate. For Example – Should the contractor estimate 145 pcf aggregate/soil with 8% cement? Being the job is bid at Square Yards this would be very important information to have. There is not enough time to retrieve samples and run mix design prior to bid date.
Response: The full depth reclamation (FDR) mix design is the contractor’s responsibility.
All available information has been included in GFI package.
2. Typical Sections – Sheet Number B01 states in the notes “11. Mill 3-inches of asphalt pavement. Remove and haul any additional material necessary in order to achieve 8-inches of full depth reclamation with cement and maintain roadway grades to existing field conditions.”
The average pavement cores appear to be approximately 4” with Aggregate Base thickness in the 8” range. Are there any concerns from FHA that we are not going to get deep enough at FDR depth of 8” to incorporate enough of the subgrade material into the FDR to achieve the strength gain requirement if there are not enough fines? Should consideration be given to the FDR depth being extended to 10” – 12” to incorporate more subgrade material?
Response: We believe 8-inch FDR is sufficient, based on the traffic loading considered for this project. The contractor should determine the FDR mix design needs in the field based on existing conditions.
3. Beginning of Section 8G at US 321…Do the curbs stay in place at the “diamond” inside the “horseshoe”? Are we FDR processing the diamond interchange just south of US 321 and the horseshoe?
Response: The curbs at the “diamond” inside the “horseshoe” stay in place. The FDR begins at the pavement change near MP 55.27 at the existing gate west of the interchange with connector roads to Route 73 / U.S. 321.
4. Beginning of Section 8H at US 129…Does the FDR start at US 129 or the Parkway Entrance?
Response: The FDR ends at the pavement change at US 129, just beyond the stop bar.
5. Road Closure – How much are we allowed to close full width at a time? For Example – Can the contractor have full width closure access from FPSWP #1 to US 129? Then once completed with the FDR portion there have full width closure access from Happy Valley Rd. to FPSWP #1?
305.13 Curing states “If approved, allow local automobile traffic on the cement stabilized layer 4 hours after finishing operations are complete. Limit traffic speeds to 20 miles per hour.” The intent for closure vs one lane two-way traffic control is not clear. Please clarify. And is the contractor responsible for damage due to traffic prior to proper curing?
Response: Full closure is subject to the time of year restrictions laid out in the subsection
156.04. Full Closure from Look Rock to U.S. Route 129 (MP 64.55 to MP 72.21) is permitted from March 14, 2022 to May 21, 2022. Full Closure from Walland to Look Rock (MP 55.2 to MP 64.55) is permitted from June 1, 2022 to August 31, 2022 with the exception that school buses must be allowed access after August 2. All work outside these times must be done under single lane closure. The contractor is responsible to fix any damage due to traffic prior to proper curing.
6. Water – This will be a critical path item during FDR. Where can water be obtained from during construction, is there hydrants available to be metered or will the contractor be required/allowed to place storage tank along the route for the FDR?
Response: The contractor is responsible for obtaining water. Water tanks may be staged in any approved staging area. See subsection 156.07(d).
7. Spoils –Is there a designated area to dispose of spoils/over burden material or is the responsibility of the contractor?
Response: The contractor is responsible for disposing of spoils/over burden legally off site.
See Section 203.
8. As we know this project is on a vigorous and tight schedule. We need clarification on SCR Section 156.04. Phase 1 is scheduled to be closed from 3/14/22 to 5/21/22. Phase 2 is scheduled to be closed from 6/1/22 to 8/31/22. If work in Phase 1 is not completed in the specified time frame, can work in Phase 1 resume, and be completed using Phase 2 start date of 6/1/22 and then move operations to Phase 2 once Phase 1 is completed.
Response: Full closure is subject to the time of year restrictions laid out in the subsection
156.04. Full Closure from Look Rock to U.S. Route 129 (MP 64.55 to MP 72.21) is permitted from March 14, 2022 to May 21, 2022. Full Closure from Walland to Look Rock (MP 55.2 to MP 64.55) is permitted from June 1, 2022 to August 31, 2022 with the exception that school buses must be allowed access after August 2. All work outside these times must be done under single lane closure.
9. With 493 days allowed for this project, that will take it into June 2023. There is no mention of full lane closure in 2023. Can we plan to use the same time frame for full lane closure in 2023 to complete work as is stipulated in the SCRs for 2022. Ie., 3/14/23 to 5/21/23 (approx.) and the month of June 2023.
Response: The 493 days allowed includes the time for submittals and review and obtaining permits, not solely for construction operations. No full closures will be permitted in the year 2023. Please refer to Subsection 156.04 and to the response for the above question for time of year restrictions.