Additonal QUESTIONS And Answers 3.4.21.pdf

PDF 210 KB Posted

Attached to
Solicitation for Energy Efficiency upgrades to Buildings 305, 27, and 28 at the William J. Hughes Technical Center
Solicitation number
692M15-21-R-00015
Issued by

About this file

This document contains additional questions and answers regarding a solicitation for energy efficiency upgrades to multiple buildings at the William J. Hughes Technical Center. The upgrades include replacing skylight, storefront, curtain wall, and entrance systems at three buildings. The contractor must provide internal structural steel reinforcement as required and engage a professional structural engineer to supervise curtain wall design. Load requirements specified include wind, seismic, and snow criteria. The period of performance is 330 calendar days from notice to proceed. A mandatory site visit was scheduled for February 9, 2021 and proposals are due by February 25, 2021. Questions must be submitted by February 15, 2021.

View the file

Other files

File Type Posted
SF30 for Amendment 005.pdf PDF
Amendment 005 to SIR_692M15-21-R-00015.pdf PDF
Question 29_Combined Cubicle Layout BLDG 305_27_28.pdf PDF
Questions and Answers.pdf PDF
Amendment 004 to SIR_692M15-21-R-00015.pdf PDF
SF30 for Amendment 0004.pdf PDF
Amendment 003_ Site Visit Sign in Sheet.pdf PDF
Amendment 002 to SIR_692M15-21-R-00015.pdf PDF
SF30 for Amendment 001.pdf PDF
Amendment 00001 to SIR_692M15-21-R-00015.pdf PDF
Amendment 00001 to Attachment 14_BLDG 305_Drawings_2 OF 3.pdf PDF
Attachment 3_SF-25A Payment Bond Form.doc DOC document
Attachment 15_BLDG 305_ Drawings_3 OF 3.pdf PDF
Attachment 5_Daily Construction Inspection Report-6900-3.doc DOC document
Attachment 2_SF-25 Performance Bond Form.pdf PDF
Attachment 6_End of Day Check List.docx DOCX document
Attachment 8__Key Personnel Qualifications and Experience - IIP Comments (002)_response.docx DOCX document
Attachment 13_BLDG 305_Drawings_1 OF 3.pdf PDF
Attachment 1_SF-24 Bid Bond.pdf PDF
Attachment 14_BLDG 305_Drawings_2 OF 3.pdf PDF
Attachment 9_Corporate Experience_Final.docx DOCX document
Attachment 11_Project_Combined SPECIFICATIONS.pdf PDF
Attachment 12_BLDG 27 and 28 _Drawings.pdf PDF
Attachment 10_Subcontracting Plan_FInal.docx DOCX document
Energy Efficency SIR_692M15-21-R-00015.pdf PDF
Attachment 7_Site Safety Daily Inspection Report.docx DOCX document
Attachment 4_Department Of Labor General Wage Determination.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION #36:

Regarding your response to RFI #30, you stated Kawneer would provide the internal steel to support the

CW and the Sloped glazing. Kawneer has informed us they cannot provide this. Please clarify if the government is requiring the contractor to provide a third‐party structural engineer to design the curtain wall? Is it the intention of the government to have this portion of the project become design build?

(Section 08 44 00 – Curtain Wall and Glazed Assemblies)

In support of a design‐build, the contractor will acquire a third party engineer to assist with the design and constructability of a complete Curtain Wall and Glazing Assembly. The following will apply:

Section 08 44 00 ‐ Curtain Wall and Glazed Assemblies

Paragraph 1.2 ‐ ADD at the end of submittal SD‐05 the text “Design Analysis; G”

Paragraph 1.2 ‐ ADD at the end of submittal SD‐07 the text “Engineer Qualifications; G”

Paragraph 1.3.4.1 – ADD subparagraph “1.3.4.1.a” to read as follows:

a. Design curtain wall and its structural support framing components under direct supervision of a Professional Structural Engineer experienced in design of this work.

Paragraph 1.5 – ADD to the end of the first paragraph text to read as follows:

‐ Provide internal structural steel members for reinforcement of aluminum extrusions as required.

QUESTION #37:

Are there specific load requirements regarding this project and the above Question #1?

The following load requirements should be used by the Curtain Wall / Skylight designer for all skylight systems:

Design Loads

Wind Load:

‐ Basic Wind Speed=140

‐ Exposure Category=C

‐ Risk Category=III

Seismic Load:

‐ Sds=0.151

‐ Sd1=0.081

‐ Site Class=D

‐ Seismic Design Category=B

‐ Importance Factor=1.25

Snow Load:

‐ Ground Snow Load=20 psf

‐ Exposure Category=C

‐ Importance Factor=1.1

QUESTION #38:

SOW – Section C.1 para “i” – Vestibule Additions – Line item #17 states all work pertaining to the

Vestibule additions must be received as a separate line item. Please advise if the bid sheet will be revised to reflect this requirement?

Amendment 005 updates section B.1 PRICES/COSTS and provides an additional breakdown of the base bid to allow for the offer amount of the Vestibule Additions.