This document contains a request for qualifications for a two-phase design-build construction procurement. The Saint Lawrence Seaway Development Corporation is seeking to replace up to six concrete diffusers at the Eisenhower Lock over two winter seasons. In Phase I, interested firms must submit qualification proposals by October 22, 2020 demonstrating their capability to successfully execute the design-build contract. Approximately five highly qualified firms will be selected to compete in Phase II. Phase II proposals will include technical and cost proposals for the design and construction of the diffuser replacements, with an estimated cost between $5-10 million. The contract type will be firm-fixed-price. The first season's work must be completed by March 8, 2021, and the second season's work by March 7, 2022. Firms must be registered in the System for Award Management to be eligible for award.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 6923G521R0002A00006.pdf | ||
| 6923G521R0002A00005.pdf | ||
| Site Map Indicating Concrete Spoil Area.pdf | ||
| 326-CSG-36-1 Dewatering and Drainage Pumps.pdf | ||
| 326-C-20-25 Filling and Emptying Culverts Details.pdf | ||
| 6923G521R0002A00004.pdf | ||
| 326-C-20-130 Frames Covers Location Plan.pdf | ||
| SLS-326-300 vicinity_locality (1).pdf | ||
| DiffusersRFP-6923G521R0002.pdf | ||
| Wage Determination.pdf | ||
| 6923G521R0002A00003.pdf | ||
| 6923G521R0002A00002.pdf | ||
| SLSDC Concrete Diffusers Replacement_ReferencePhotos.pdf | ||
| 6923G521R0002A00001.pdf | ||
| 326-C-20-22 Lower Sill Reinforcement.pdf | ||
| 326-C-20-21 Lower Sill Plan-Elevation-Section.pdf | ||
| 326-C-20-1 Lock General Plan Elevations-Sections.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6923G521R0002
Phase I www.greatlakes-seaway.com
Contracting Office
180 Andrews Street, Massena, NY 13662
Phone: (315)764-3252
Eisenhower Lock Concrete Diffusers Replacement
Project Title: Design-Build for Concrete Diffuser Replacement
No: 6923G521R0002 Posted Date: 10/02/2020 Phase I Proposal Due Date: October 22, 2020 1:00pm(ET)
This Request for Qualifications for the two-phase design-build construction procurement (FAR 36.303) of the Concrete Diffuser Replacement project. The time and date set forth within is for the receipt of proposals for Phase I only. Phase II will be issued by amendment to no more than five (5) of the most highly qualified successful Offerors determined during the Phase I evaluation.
All inquiries concerning Phase I must be submitted in writing via email to jason.brockway@dot.gov no later than October 22, 2020 1:00pm ET.
All required proposals for Phase I shall be submitted by email no later than October 22, 2020 1:00pm
ET, to jason.brockway@dot.gov.
Please ensure all correspondence includes the solicitation number, 6923G521R0002, in the subject line.
The applicable NAICS code is 237990 and this procurement is for Full and Open Competition.
The Range of Magnitude is expected to be between $5 million and $10 million.
Proposed Contract Type: Firm-Fixed Price.
NOTE: PROSPECTIVE CONTRACTORS ARE REQUIRED TO REGISTER IN THE SYSTEM FOR AWARD
MANAGEMENT (SAM) DATABASE PRIOR TO AWARD OF A CONTRACT AT www.sam.gov.
180 Andrews Street
Massena, N.Y. 13662
Tel.: (315) 764-3200 mailto:jason.brockway@dot.gov mailto:jason.brockway@dot.gov http://www.sam.gov/
1. General Overview and Scope
1.1. Scope of Work Overview
This scope of work shall provide all design and construction services required to complete the replacement of diffuser structures (diffusers) at Eisenhower Lock located in Massena, New
York. The St. Lawrence Seaway Development Corporation (SLSDC) intends to replace up to six (6) concrete diffusers (water manifolds) below the downstream sill at Eisenhower Lock over two winter seasons. The SLSDC is soliciting the project requirements in a two-phase design-build solicitation.
The diffusers are geometrically complex reinforced concrete hydraulic structures which are a critical part of the lock structure as they are required to dissipate large forces from the release of lock chamber water and reduce downstream turbulence which is needed for vessel navigation safety. These structures are original to the construction of the lock and after over sixty years of operation are near the end of their service life. Replacement of these structures will require a complex design. The design must entail specifics on how to demolish the existing diffusers while protecting the integrity of the adjacent lock structures, and install the replacement diffuser structures.
Access to the work areas is restrictive in that the diffusers are about 40-feet below the adjacent lock wall surfaces thus temporary access means will be required. The diffusers are normally submerged in about 35-feet of water, and the work can only be done when the lock is out of service and mostly dewatered which is during the annual winter navigation shutdown period from early January through early March. The work area will not be completely dewatered by the
SLSDC and therefore, the Contractor will need to address additional dewatering needed to maintain access to the diffuser structures during winter weather conditions to complete this scope of work.
The base requirement would be to complete three (3) diffusers in the first year’s winter shutdown period with an option for the other three (3) diffusers in the second year.
Generally, the Contractor’s responsibilities shall include, but will not be limited to, the following:
a. Complete the design and construction of the Project in accordance with the specifications.
b. To furnish and provide all labor, materials and equipment, as necessary to complete the
Project.
1.2. General Overview of the Procurement Process
This is a two-phase design-build construction procurement. In Phase One, interested offerors shall submit proposals, demonstrating their capability to successfully execute the design-build construction contract resulting from this solicitation. The SLSDC will evaluate the Phase One submittals in accordance with the criteria described herein and select the most highly qualified offerors – no more than five – to compete for the design-build contract in Phase Two. In Phase
Two, the selected most highly qualified offerors from Phase One shall submit technical and cost proposals in accordance with the criteria described herein.
2. Submittal Requirements for Phase One
Submittals will be evaluated in Phase One to determine up to five of the most highly qualified offerors. Each proposal will undergo an evaluation utilizing the factors defined below. Phase
One does NOT involve a pricing submission or evaluation of price.
a. Factor 1 – Technical Approach
b. Factor 2 – Technical Qualifications
c. Factor 3 – Past Performance
2.1. Factor 1 – Technical Approach
The Technical Approach shall describe the offeror’s approach to the design and construction of the project. As a minimum, it shall include the following:
Collaborative Approach for Design-Build
a. Describe interactions within the offeror’s team and with SLSDC during the design.
Specifically describe a plan to meet submittal requirements, changes, and quality control.
b. Describe the construction team management and quality control plan for the construction.
c. Describe the role and interaction of the design team with the construction team during construction.
Planning and Scheduling
a. Describe the offeror’s time control capabilities and systems to be used to develop and manage the schedule for the design and construction of the project.
b. Provide information on how you will handle schedule progress reviews, updates, changes, and documentation.
Quality Control
a. Describe the offeror’s quality control capabilities and systems to be used to maintain quality control for the design and construction of the project.
b. Provide information on how you will handle internal and external requests for information, shop drawings, submittal reviews, progress meetings, site visits, contract completion, closeout, as-builts, and completion documentation.
Conceptual Design
Offerors shall submit a conceptual design to include general materials and construction methods. The offeror shall explain the benefits of the conceptual design. The conceptual design shall not be a detailed design. The attached reference drawings (326-C-20/1, 326-C-
20/21 and 326-C-20/22) show the general layout and elevations of the diffusers. These should be used as reference to gain familiarity of the structures when developing the conceptual design.
2.2. Factor 2 – Technical Qualifications
The Technical Qualifications shall include an organizational chart including a description of the firm(s) involved, their relative roles and responsibilities, and any contractual arrangements (i.e.
joint ventures) that will be established to constitute the offeror’s design-build team. As a minimum, it shall also include the following:
Key Project Personnel Capabilities and Experience
Key project personnel capabilities and experience information shall be submitted for the key personnel identified below (minimum qualifications listed):
a. Project Manager – two (2) years of substantial documented experience in design-build services.
b. Engineer of Record (EOR) – licensed professional engineer in New York State.
For other key project personnel, provide a consolidated list with name, position, title, description of project responsibility, and any applicable professional qualifications.
2.3. Past Performance
The offeror shall have completed at least two (2) projects of similar scope and complexity within the past ten (10) years. References shall be provided. Each reference shall include the name and address of the client, a brief but detailed description of the work performed and a contact person with valid contact information (phone number and email).
3. Submittal Requirements for Phase Two
After the SLSDC has evaluated the Phase One submittals and SLSDC selects up to five of the most highly qualified offerors, they will be invited to compete for the design-build contract by completing the Phase Two submittals. A more detailed description of the design-build scope of work and requirements will be provided to the selected offerors in order for them to provide the required Phase Two technical and cost submittals. Offerors providing Phase One submittals shall not provide Phase Two submittals with their Phase One submittals. The following description of the Phase Two submittal requirements is for “informational purposes only” during Phase One of this solicitation.
3.1. Technical Proposal Requirements
Technical Proposals shall include sufficient information so that a proper evaluation can be made with respect to the requirements outlined in the scope of work. As a minimum, Technical Proposals shall include the following:
a. Discussion of the understanding of the scope of work.
b. Detailed discussion of project approach and steps to be taken to accomplish the work.
c. Detailed Work Plan including scheduled sequencing of key activities and project milestones.
3.2. Cost Proposal Requirements
Cost Proposals shall be detailed and include all costs to complete the scope of work. All travel and meals shall be reimbursed per the requirements of the Government Travel Regulations. The
SLSDC intends to evaluate offers and award a contract without discussions with offerors.
Therefore, the offeror’s initial offer should contain the offeror’s best terms from a cost and technical perspective. However, the SLSDC reserves the right to conduct discussions with offerors if deemed necessary by the Contracting Officer.
3.3. Evaluation of Proposals
The SLSDC will make the Phase Two award to the responsible offeror whose offer conforms to the requirements and on the evaluation factors listed below:
a. Technical Proposal
b. Cost Proposal
c. Past Performance
4. Overall Project Schedule
The overall project schedule is as follows
a. Release Phase One of the solicitation: October 2, 2020 (on or about)
b. Pre-proposal inquiries due: October 19, 2020 10:00am ET
c. Phase One submissions due: October 22, 2020 1:00pm ET
d. Release Phase Two of the solicitation to selected firms: October 26, 2020 (on or about)
e. Phase Two proposals due: November 12, 2020 (on or about)
f. Award: November 17, 2020 (on or about)
g. Lock dewatered for first season’s work: January 11, 2021 (on or about)
h. Required completion for first season’s work: March 8, 2021 (on or about)
i. Lock dewatered for second season’s work: January 10, 2022 (on or about)
j. Required completion for second season’s work: March 7, 2020 (on or about)