6923G521R0002A00003.pdf

PDF 192 KB Posted

Attached to
Concrete Diffuser Replacements Federal contract opportunity
Solicitation number
6923G521R0002
Issued by
Department of Transportation Saint Lawrence Seaway Development Corporation

About this file

This document provides details of a two-phase solicitation for design-build services to replace concrete diffusers at the Eisenhower Lock in Massena, New York. The Saint Lawrence Seaway Development Corporation is requesting qualification proposals in Phase I to shortlist approximately five firms to compete in Phase II for the design and construction contract. Interested firms should submit capability proposals by October 22, 2020 demonstrating experience in similar projects. Phase II will involve a request for proposals from the shortlisted firms to complete the replacement of up to six diffusers below the downstream sill over two winter seasons, with estimated costs between $5-10 million. The contract type will be firm-fixed price. The scope of work includes all design and construction services to replace the diffuser structures.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

1 2

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

6923G521R0002

9B. DATED (SEE ITEM 11)

10/02/2020

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6923G521R0002A00003 10/16/2020

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

SLS Contracting Office 180 Andrews Street Massena, NY 13662, US

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.

is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

This amendment serves to include questions asked by prospective offerors and the answers provided by the Contracting Officer’s Representative.

1. Q: Can you provide hydraulic flow information for use in design of the new diffusor structure(s)?

A: The SLSDC does not have any hydraulic flow data specific to the diffusers. The normal operating head is about 45 feet. The design flow is no less than 22,000,000 gallons in seven (7) minutes.

Continued on Pages 2 (Q &A)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

6923G521R0002A00003

(Questions and Answers)

2. Q: What is the intended process and time frame for review of the Contractors Design

Submission by SLSDC?

A: As part of the first factor in the first phase solicitation requires the submittal of a conceptual design that shall, “include general materials and construction methods. The offeror shall explain the benefits of the conceptual design. The conceptual design shall not be a detailed design.” More details on the submittal process for a final design will be furnished with the second phase of the solicitation.

3. Q: After approval of the project design what is the intended process for review and approval of materials and shop drawings? Will this be completed by the contractors designer or will it require dual review and approval by the SLSDC?

A: See the response to #2 above. More details on the submittal process for a final design and construction will be furnished with the second phase of the solicitation.

4. Q: Will construction inspection services fall under the DB contractor or will SLSDC be providing these services?

A: The Contractor will be responsible for completing the work in accordance with the applicable design and quality control requirements. The SLSDC may choose to have internal or third party constructions inspection services for the completion of the work. However, the presence, or lack of presence, of an inspection does not alleviate the Contractor from this responsibility.