QandA_07-15-2026.pdf

PDF 191 KB Posted

Attached to
MT FLAP BLACKF 12(1) & MT NP GLAC 12(2), FLAP & FLTP Rehabilitation of Two Medicine Road
Solicitation number
69056726B000005
Issued by

About this file

This is a Questions and Answers (Q&A) document for federal highway construction projects MT FLAP BLACKF 12(1) and MT NP GLAC 12(2) concerning the FLAP and FLTP Rehabilitation of Two Medicine Road.

The document addresses four technical inquiries submitted by contractors between July 2 and July 15, 2026. Question 1 requests an extension of the fixed completion date to November 24, 2027, to allow additional time for finalization, cleanup, and demobilization after paving completion; the Government approved an extension to November 12, 2027 via Amendment A001. Question 2 requests relaxation of aggregate source quality standards (soundness of coarse aggregate to 25% loss and Liquid Limit to 35); the Government declined and directed bidders to comply with solicitation documents as written. Question 3 addresses Standard Construction Requirement (SCR) 637.02 regarding residential housing unit placement 14 days prior to construction start, noting that units will be 12-16 weeks out from the Notice to Proceed on September 14, 2026; the Government indicated this requirement will be clarified in Amendment A002 to align housing placement with the 2027 on-site construction season start. Question 4 requests clarification and modification of SCR 108.01(a)(1) concerning work suspension requirements between Appistoki Creek Bridge and Two Medicine General Store from September 7 through May 25; the Government confirmed this language will be removed via Amendment A002.

View the file

Other files

File Type Posted
BidTab_FLAP and FLTP Rehabilitation of Two Medicine Road.pdf PDF
BidSum_FLAP and FLTP Rehabilitation of Two Medicine Road.pdf PDF
QandA_07-28-2026.pdf PDF
Amendment A004.pdf PDF
QandA_07-27-2026.pdf PDF
QandA_07-24-2026.pdf PDF
Amendment A003.pdf PDF
QandA_07-23-2026.pdf PDF
QandA_07-22-2026.pdf PDF
QandA_07-20-2026.pdf PDF
QandA_07-16-2026.pdf PDF
Amendment A002.pdf PDF
Amendment A001.pdf PDF
QandA_07-02-2026.pdf PDF
IFB 69056726B000005.pdf PDF
mta-blackf12-1_glac12-2_plans IFB.pdf PDF
Physical Data_2_MT FLAP BLACKF 12(1) .zip ZIP file
Physical Data_3_MT FLAP BLACKF 12(1) .zip ZIP file
Physical Data_1_MT FLAP BLACKF 12(1) .zip ZIP file
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.MT FLAP BLACKF 12(1) & MT NP GLAC 12(2)

Project FLAP & FLTP Rehabilitation of Two Medicine Road

# General Technical Question Answer Date

1 X

Would FHWA consider extending the fixed completion date to 11/24/27 to give us more time finalizing work, cleanup, and de-mob after paving is completed?

The Govenement will extend the fixed completion date to 11/12/2027 (NOT

11/24/2026) in Amendment A001.

7/2/26

2 X

The closest available aggregate source to the project does not meet source quality standards on a couple metrics. Would FHWA consider relaxing the soundness of course aggregate standard to 25% loss? Would FHWA consider relaxing the LL standard to 35?

No. Please bid per the solicitation documents.

7/15/26

3 X

SCR 637.02 states that residential housing units need to be on site no later than 14 days before starting construction. Currently I am being told those units are 12-16 weeks out. With NTP on

09/14/26 we don’t think its possible to have the units on site 14 days prior to construction.

Would FHWA please remove that requirement?

This will be addressed under Amendment

A002. The intent is to have the residential housing in place 14-days prior to the start of the 2027 on-site construction season.

7/15/26

Check General or Technical

4 X

Please clarify SCR 108.01(a)(1) “Suspend work between Appistoki creek bridge and Two

Medicine General Store between September 7 and May 25 (dates inclusive);” Is the intent to perform all work in this area between May 25, 2027 and September 7, 2027? It seems like it would be more appropriate to perform this work before Memorial Day or after Labor Day to limit the construction impacts.

This will be addressed under Amendment

A002. SCR 108.01(a)(1) “Suspend work between Appistoki creek bridge and Two

Medicine General Store between

September 7 and May 25 (dates inclusive);”

will be removed from this section.

7/15/26

File details come from the government source that posted it. Updated .