QandA_07-02-2026.pdf
PDF 57 KB Posted
- Attached to
- MT FLAP BLACKF 12(1) & MT NP GLAC 12(2), FLAP & FLTP Rehabilitation of Two Medicine Road
- Solicitation number
- 69056726B000005
About this file
This is a Questions and Answers document for Project No. MT FLAP BLACKF 12(1) & MT NP GLAC 12(2), relating to the FLAP & FLTP Rehabilitation of Two Medicine Road.
The document contains one technical question and answer. A contractor inquired whether the Federal Highway Administration (FHWA) would extend the fixed completion date to 11/24/27 to allow additional time for finalizing work, cleanup, and demobilization after paving completion. The Government responded that the fixed completion date will be extended to 11/12/2027 (not 11/24/2026) through Amendment A001. The question was answered on 7/2/26.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No.MT FLAP BLACKF 12(1) & MT NP GLAC 12(2) Project FLAP & FLTP Rehabilitation of Two Medicine Road
# General Technical Question Answer Date
1 X
Would FHWA consider extending the fixed completion date to 11/24/27 to give us more time finalizing work, cleanup, and de-mob after paving is completed?
The Govenement will extend the fixed completion date to 11/12/2027 (NOT 11/24/2026) in Amendment A001.
7/2/26