This document is a Questions and Answers (Q&A) file for the Wind River Road Slide Reconstruction project (Project No. WA FLAP SKAMAN 92135(1)). The document contains a technical question regarding traffic control and crane operations during pile installation. The contractor asked if they could use the Phase 2 Traffic Control Plan during soldier pile installation, given space constraints for two-way traffic and drill crane operations.

The response confirms that the detour and closure of both northbound lanes can be used during Phase 1 pile installation, with a time limitation of 30 consecutive days. An updated plan sheet showing a new Phase 1A configuration will be added in Amendment A001. The document is dated 1/12/26 and provides specific details about traffic management and construction logistics for the road reconstruction project.

View the file

Other files

File Type Posted
Bid Tabulation_Wind River Road Slide Reconstruction.pdf PDF
BidSum_WA FLAP SKAMAN 92135(1).pdf PDF
QandA_01-29-2026.pdf PDF
Amendment A006.pdf PDF
QandA_01-28-2026.pdf PDF
QandA_01-27-2026-3.pdf PDF
Amendment A005.pdf PDF
Amendment A004.pdf PDF
QandA_01-27-2026-2.pdf PDF
Amendment A004.pdf PDF
QandA_01-27-2026.pdf PDF
QandA_01-26-2026.pdf PDF
Amendment A003.pdf PDF
QandA_01-23-2026.pdf PDF
Amendment A002.pdf PDF
Interested Vendors list.pdf PDF
QandA_01-22-2026.pdf PDF
QandA_01-14-2026.pdf PDF
Amendment A001.pdf PDF
waa-skaman92135-1_Project-Name-Change.pdf PDF
GM 16-24 Prelim Geotech Memo WA FLAP SKAMAN 92135-1.pdf PDF
waa-skaman92135-1_WindRiverRoad_SupplementalGeotechReport.pdf PDF
waa-skaman92135-1_construction-limits.pdf PDF
waa-skaman92135-1_XYZ_final.pdf PDF
waa-skaman92135-1_plan_IFB.pdf PDF
waa-skaman92135-1_Physical Data.zip ZIP file
waa-skaman92135-1_proposed-alignment.pdf PDF
waa-skaman92135-1_XYZ_base.pdf PDF
WFLHD Construction Contract Administration.pdf PDF
IFB 69056725B000013.pdf PDF
waa-skaman92135-1_xs.pdf PDF
waa-skaman92135-1_clearing_limits.pdf PDF
waa-skaman92135-1_Earthwork.pdf PDF
waa-skaman92135-1_construction-staking-notes.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No.WA FLAP SKAMAN 92135(1) Project:Wind River Road Slide Reconstruction

# General Technical Question Answer Date

1 x

There is not enough horizontal room for 2 way traffic and the drill crane to install the soldier piles. The drill crane requires 25 feet from back of pile hole to the counterbalance of the machine and then an estimated 2 feet for a jersey barrier to be place between machine and traffic. Please see attached drawing. Can the contractor use Phase 2 Traffic Control Plan, Sheet 1 of 2, during the installation of the piles?

Yes, the detour and closure of both northbound lanes can be used during pile installation in Phase 1. Use of the detour during Phase 1 will be limited to 30 consecutive days. An updated plan sheets show a new Phase 1A which includes this configuration will be added in Amendment A001.

1/12/26

Check General or Technical

File details come from the government source that posted it. Updated .