Amendment A001.pdf
PDF 154 KB Posted
- Solicitation number
- 69056725B000002
About this file
This document is an Amendment (A001) to a federal solicitation issued by the Department of Transportation Federal Highway Administration for the OR FLAP DOT 126(1), Blue Pool Safety and Access Enhancement Project.
The amendment revises the FAR Clause 52.236-4, Physical Data, within the contract clauses. It provides additional details and site information, including geotechnical data, design data, and environmental information files that have been posted with the solicitation. The amendment extends the offer due date, but does not change the contract/order number or other core terms and conditions of the original solicitation. Contractors must acknowledge receipt of this amendment prior to the specified offer due date.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A001 11/05/2024 N/A OR FLAP DOT 126(1)
Blue Pool Safety and Access Enhancement Project
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056725B000002
9B. DATED (SEE ITEM 11)
10/22/2024
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A
N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
(__ ) is extended, ( x ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D OTHER (Specify type of modification and authority)
N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
OR FLAP DOT 126(1), Blue Pool Safety and Access Enhancement Project
Amendment A001 is issued to revise the following:
CONTRACT CLAUSES
Page C-93. Revises FAR Clauses 52.236-4, Physical Data.
ENCLOSURES: C-93
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
C-93
Contract Clauses Project: OR FLAP DOT 126(1), Blue Pool Safety and Access Enhancement Project conditions which can affect the work or its cost, including but not limited to (1) conditions bearing upon transportation, disposal, handling, and storage of materials; (2) the availability of labor, water, electric power, and roads; (3) uncertainties of weather, river stages, tides, or similar physical conditions at the site; (4) the conformation and conditions of the ground; and (5) the character of equipment and facilities needed preliminary to and during work performance. The Contractor also acknowledges that it has satisfied itself as to the character, quality, and quantity of surface and subsurface materials or obstacles to be encountered insofar as this information is reasonably ascertainable from an inspection of the site, including all exploratory work done by the Government, as well as from the drawings and specifications made a part of this contract. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from responsibility for estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expense to the Government.
(b) The Government assumes no responsibility for any conclusions or interpretations made by the Contractor based on the information made available by the Government. Nor does the Government assume responsibility for any understanding reached or representation made concerning conditions which can affect the work by any of its officers or agents before the execution of this contract, unless that understanding or representation is expressly stated in this contract.
52.236-4 Physical Data (Apr 1984)
Data and information furnished or referred to below is for the Contractor’s information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by: N/A..
(b) Weather conditions: N/A.
(c) Transportation facilities: N/A.
(d) Geotechnical data, design data, and environmental information consisting of the following, will be posted with the solicitation.
1) GM 15-24_OR DOT 126(1) Blue Pool Safety_REVISED.pdf
2) ora-dot126-1_ali.pdf
3) ora-dot126-1_ali_MAIN02.xml
4) ora-dot126-1_boulder_grouping.pdf 5)4) ora-dot126-1_control.xlsx 6)5) ora-dot126-1_Breaklinesf.dxf 7)6) ora-dot126-1_ew.pdf 8)7) ora-dot126-1_ter_Existing.xml 9)8) ora-dot126-1_ter_MAIN02.xml, ora-dot126-1_ter_MAIN02_subgrade.xml 10)9) ora-dot126-1_ter_ParkingLot.xml 11)10) ora-dot126-1_ter_ParkingLot_subgrade.xml 12)11) ora-dot126-1_xs_MAIN02.pdf 13)12) ora-dot126-1_romtec.pdf (includes two documents; Romtec Blue Pool
Trailhead Double Kiosk Instructions.pdf & Romtec Restroom Model 1009 Instructions.pdf)
14)13) ora-dot126-1_1200-CA_cover.pdf 15)14) OR FLAP DOT 126(1) OR_CompiledESCP_8.12.24.pdf (including 1200-CA cover)
52.236-5 Material and Workmanship (Apr 1984)
(a) All equipment, material, and articles incorporated into the work covered by this contract shall be new and of the most suitable grade for the purpose intended, unless otherwise specifically provided in this
Revised by Amendment A001