671-21-143-VA-SA-Replace_2nd_Floor_Roof-Drawings.pdf
PDF 8 MB Posted
- Attached to
- Z2DA--671-24-004 NRM Replace 2nd Floor Roof
- Solicitation number
- 36C25726B0004
About this file
This is a complete set of 100% Construction Documents (final design phase) for the Replace 2nd Floor Roof project at Audie L. Murphy Memorial Veterans Hospital in San Antonio, Texas. The project is identified as Project No. 671-21-143 and is overseen by the Department of Veterans Affairs' Central Texas Veterans Health Care System, with design by WestEast Design Group JV, LLC (Elk Consortium + Texas Registered Architectural Firm).
The construction documents include architectural plans with detailed roof replacement specifications organized by work areas (A, B, C, and D), demolition plans identifying existing systems to be removed, phasing plans for two construction phases, and comprehensive roof details addressing flashings, penetrations, and transitions. Architectural scope includes removal of the existing solar collector steam piping system, demolition of the current 2nd floor roof assembly, and installation of a new TPO (thermoplastic polyolefin) roof system with associated structural supports and waterproofing details. The documents incorporate mechanical, electrical, and plumbing (MEP) coordination requirements, including temporary relocation and support of existing conduits, equipment, and piping to accommodate roof replacement. General notes specify infection control procedures, dust containment using negative air machines, coordination with hospital facilities, and compliance with federal and state construction codes. Alternate bid items include penthouse roof system replacement, document curbs, treating existing nailer and blocking, and existing metal fascia replacement. The project emphasizes sequencing coordination across multiple building areas to maintain hospital operations during construction, with detailed specifications for material standards, safety protocols, and equipment support methodologies throughout the design package.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Asbestos Survey.pdf | ||
| 36C25726B0004 0004.docx | DOCX document | |
| VA AUDIE MURPHY ROOF REPORT Signed.pdf | ||
| 23040-VA-Replace_2nd_Flr_Roof_Uncovering-Field Observation Report-001.pdf | ||
| 36C25726B0004 0003.docx | DOCX document | |
| RFI final 26B0004.docx | DOCX document | |
| 36C25726B0004 0002.docx | DOCX document | |
| 36C25726B0004 0001.docx | DOCX document | |
| S06 Pre-bid sign in sheet.pdf | ||
| ICRA 671-24-004.pdf | ||
| 36C25726B0004_1.docx | DOCX document | |
| PCRA 671-24-004.pdf | ||
| 671-21-143-VA-SA-Replace_2nd_Floor_Roof-Specifications.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PQ
COVER SHEET AND
DRAWING INDEX
GI0.1
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC Elk Consortium +
Texas Registered Architectural Firm
DRAWING INDEX
ARCHITECTURAL ADD ALTERNATES
PROJECT: REPLACE 2ND FLOOR ROOF
PROJECT NO. : 671-21-143
100% CONSTRUCTION DOCUMENTS FINAL
CENTRAL TEXAS VETERANS HEALTH CARE
Department
Veterans Affairs of
SAN ANTONIO, TEXAS
AUDIE L. MURPHY MEMORIAL VETERANS HOSPITAL
7400 MERTON MINTER BLVD.
COORDINATION:
EXISTING CONDITIONS:
1. SPECIFICATIONS
2. DRAWINGS
SITE VICINITY MAPC6
PL
AN
N
OR
TH
TR
UE
N
OR
TH
ABBREVIATIONS
ARCHITECTURAL SYMBOLS LEGEND
CONSTRUCTION SAFETY NOTES
DOCUMENT ORGANIZATION
INFECTION PREVENTION NOTESGENERAL PROJECT NOTES
N.I.C.
SAFETY/SECURITY:
CONSTRUCTION SETS:
CORRESPONDENCE / INSTRUCTIONS:
MISCELLANEOUS:
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC Elk Consortium +
Texas Registered Architectural Firm
ALTERNATE No.1
PENTHOUSE
VON SCHEELE RD.
W
URZB
ACH R
OAD
M
ER
TO
N
M
IN
TE
R
B
LV
D
MELROSE HOLMGREEN ROAD
LOADING
DOCK
7TH FLOOR ROOF
N.I.C.
N.I.C.
N.I.C.
N.I.C. N.I.C.
N.I.C.
N.I.C.
N.I.C.
REPLACE 2ND FLOOR
ROOF PROJECT
PENTHOUSE ROOF
7TH FLOOR ROOF
2ND FLOOR ROOF
1ST FLOOR
GROUND FLOOR
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC Elk Consortium +
Texas Registered Architectural Firm
2ND FLOOR ROOF PHASING PLANF5VA HOSPITAL CAMPUS MAPF1
PL
AN
N
OR
TH
TR
UE
N
OR
TH
LEGEND
GENERAL NOTES
PHASING LEGEND
N.I.C.
PHASE 1 PHASE 2
N.I.C.
N.I.C.
N.I.C.
N.I.C.
N.I.C.N.I.C.N.I.C.
N.I.C.
N.I.C.
EXISTING ROOF
ACCESS PENTHOUSE
BUILDING ELEVATIONA5
ALTERNATE
No.1
PENTHOUSE
EXISTING ROOF
ACCESS PENTHOUSE
PALLETS WILL BE DISBURSED
THROUGHOUT ROOF TO
MINIMIZE WEIGHT IN ONE AREA
DEMOLITION ROOF PLAN - KEY PLANE1
GENERAL DEMOLITION NOTESLEGEND
GENERAL NOTES FOR THE REMOVAL OF THE
SOLAR COLLECTOR STEAM PIPING SYSTEM
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC Elk Consortium +
DEMOLITION ENLARGED ROOF PLAN - AREA AF1
DEMOLITION LEGEND DEMOLITION KEY NOTES
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
DEMOLITION ENLARGED ROOF PLAN - AREA BF1 DEMOLITION ENLARGED ROOF PLAN - AREA CF5
DEMOLITION KEY NOTESDEMOLITION LEGEND
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
LEGEND
DEMOLITION KEY NOTES
DEMOLITION ENLARGED ROOF PLAN - AREA DF1
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
GENERAL NOTES
ROOF PLAN - NEW WORK - KEY PLANE1
LEGEND
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
ENLARGED ROOF PLAN - NEW WORK - AREA AF1
LEGEND KEY NOTES
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
ENLARGED ROOF PLAN - NEW WORK - AREA BF1 ENLARGED ROOF PLAN - NEW WORK - AREA CF5
LEGEND KEY NOTES
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
ENLARGED ROOF PLAN - NEW WORK - AREA DF1
LEGEND
KEY NOTES
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
METAL WALL PANEL FLASHINGB7
FLASHING AT EXISTING EXPANSION JOINT CURBD4
FASCIA FLASHING SYSTEM AT EXISTING ROOF EDGEB1 FLASHING AT EXISTING SURFACE-MOUNTED FLASHING CONDITIONB4
FLASHING AT EXISTING EQUIPMENT CURBD1
DOOR THRESHOLD FLASHING DETAILF7
FLASHING AT EXISTING LOADING DOCK EXPANSION JOINTD7
FLASHING AT EXISTING ROOF TRANSITIONF4PIPE SUPPORT CURB F1
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
FLASHING AND COMPONENTS AT NEW ROOF DRAINB1 TPO SQUARE TUBE WRAP DETAILB7PLUMBING VENT OR PIPE PENETRATION ROOF DETAIL - TYPICALB4
MEMBRANE - COATED METAL PENETRATION POCKET DETAILD1 JUNCTION BOX FOR SATELLITE WIRING HOOK-UPSD4 INVERTER PAD COLUMN FLASHINGD7
30" (762 mm)
6" (1 52 mm)
TPO HEAT WELDED WALKWAY INSTALLATIONF1
6" (1 52 mm)
5" (1 27 mm) M
AX
TPO ADHERED LOOPED LIGHTNING SUPPRESSION MOUNTINGF4 HIGH TEMPURATURE FLASHING AT STEAM PIPE VENTF7
± 2"
± 2"
±2"
± 2"
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
TPO SPLIT PIPE BOOT DETAILB1 TPO POURABLE SEALER POCKET DETAIL- TYPICALB7TPO PREFORMED VENT BOOT DETAIL - TYPICALB4
MEMBRANE - COATED METAL MULTIPLE PENETRATION POCKET DETAILD1 TPO PREMOLDED VENT BOOT FLASHING DETAILD4
± 2"
± 2"
± 2"
± 2"
ROOF EDGE DETAILF1 ROOF-TO-WALL DETAILF3 FLASHING AND EXPANSION JOINT DETAILF4 FLASHING AND EXPANSION JOINT DETAILF7
Drawing Title
Approved: Project Director
Project Title
Date
Location
Checked
Building Number
Project Number
Drawing Number
Drawn
Dwg. ofRevisions: Date
ARCHITECT: 671 -21-143
Management
SEPT. 03, 2024 18
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
100% CD FINALCONSULTANTS:
Office of Facilities
JQ
09/03/2024
Replace 2nd Floor Roof
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC
MEP GENERAL NOTES
& DETAILS
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC Elk Consortium +
Texas Registered Architectural Firm
N O
RT
H
F
LO
RE
S
SA
N
A N
TO
N
IO
, T
EX
A
S
0.
3.
SA
N
A N
TO
N
IO
R G
V
P H
O N
E
TB
PE
F
IR
M R
EG
IS
TR
A
TI
O
N N
O
CONSULTANTS
MEP001
100% CD FINAL
8/22/24
A. PROJECT SCOPE SHALL INCLUDE TEMPORARY SUPPORT AND RAISING OF EXISTING CONDUITS ON ALL ROOFS SHOWN HEREIN AS REQUIRED TO ACCOMMODATE ROOF REPLACEMENT AND RAISING OF EXISTING ROOF INSULATION. CONTRACTOR SHALL MAINTAIN
AND EXTEND EXISTING CONDUCTORS AND CONDUIT AS REQUIRED.
B. GENERAL: EXCEPT FOR ITEMS OR MATERIALS INDICATED TO BE REUSED, SALVAGED, REINSTALLED, OR OTHERWISE INDICATED TO REMAIN OWNER'S PROPERTY, REMOVE DEMOLISHED MATERIALS FROM PROJECT SITE AND LEGALLY DISPOSE OF THEM IN AN EPA-APPROVED LANDFILL. DO NOT ALLOW DEMOLISHED MATERIALS TO ACCUMULATE ON-SITE REMOVE FROM OWNER OCCUPIED AREAS DAILY. REMOVE AND TRANSPORT DEBRIS IN A MANNER THAT WILL PREVENT SPILLAGE ON ADJACENT SURFACES AND
AREAS.
C. TRACE CIRCUITS FEEDING EXISTING TO-REMAIN PORTIONS OF THE BUILDING. DO NOT DEMOLISH CIRCUITS IN THESE AREAS. IF CIRCUITS ARE IN BOTH "TO REMAIN" AND "TO BE REMOVED" AREAS, DEMOLISH BACK TO NEAREST TO-REMAIN J-BOX.
D. DEMOLISH AND REMOVE EXISTING CONSTRUCTION ONLY TO THE EXTENT REQUIRED BY NEW CONSTRUCTION AND AS INDICATED.
COMPLETE SELECTIVE DEMOLITION OPERATIONS ABOVE EACH FLOOR OR TIER BEFORE DISTURBING SUPPORTING MEMBERS ON
THE NEXT LOWER LEVEL.
E. REMOVED AND SALVAGED ITEMS: CLEAN SALVAGED ITEMS, PACK OR CRATE ITEMS AFTER CLEANING. IDENTIFY CONTENTS OF CONTAINERS. STORE ITEMS IN A SECURE AREA UNTIL DELIVERY TO OWNER. TRANSPORT ITEMS TO OWNER'S STORAGE AREA
DESIGNATED BY OWNER. PROTECT ITEMS FROM DAMAGE DURING TRANSPORT AND STORAGE.
F. REMOVED AND REINSTALLED ITEMS: CLEAN AND REPAIR ITEMS TO FUNCTIONAL CONDITION ADEQUATE FOR INTENDED REUSE.
PAINT EQUIPMENT TO MATCH NEW EQUIPMENT. PACK OR CRATE ITEMS AFTER CLEANING AND REPAIRING. IDENTIFY CONTENTS OF CONTAINERS. PROTECT ITEMS FROM DAMAGE DURING TRANSPORT AND STORAGE. REINSTALL ITEMS IN LOCATIONS INDICATED. COMPLY WITH INSTALLATION REQUIREMENTS FOR NEW MATERIALS AND EQUIPMENT. PROVIDE CONNECTIONS, SUPPORTS, AND MISCELLANEOUS MATERIALS NECESSARY TO MAKE ITEM FUNCTIONAL FOR USE INDICATED.
G. EXISTING ITEMS TO REMAIN: PROTECT CONSTRUCTION INDICATED TO REMAIN AGAINST DAMAGE AND SOILING DURING SELECTIVE DEMOLITION. WHEN PERMITTED BY ARCHITECT, ITEMS MAY BE REMOVED TO A SUITABLE, PROTECTED STORAGE LOCATION DURING SELECTIVE DEMOLITION AND REINSTALLED IN THEIR ORIGINAL LOCATIONS AFTER SELECTIVE DEMOLITION OPERATIONS
ARE COMPLETE.
H. COORDINATE ALL DEMO ACTIVITIES WITH OWNER AND ARCHITECT AND PROVIDE 10 DAYS NOTICE FOR ANY POWER OUTAGES.
I. IT IS THE CONTRACTOR'S RESPONSIBILITY TO HAVE VERIFIED EXISTING JOB-SITE CONDITIONS DURING THE BIDDING PERIOD TO OBTAIN THE SCOPE OF ELECTRICAL WORK INVOLVED AS A RESULT OF ARCHITECTURAL MODIFICATIONS TO THE EXISTING STRUCTURE. THE SCOPE OF THE WORK SHALL INCLUDE MATERIALS AND OUTLETS, CONSISTING OF FIXTURES, DEVICES, EQUIPMENT OR APPARATUS, WHICH MUST BE REROUTED, RELOCATED OR REMOVED EITHER TEMPORARILY OR PERMANENTLY, OR WHICH MUST BE PROVIDED, SO THAT THE INDICATED REMODELING MAY BE ACCOMPLISHED. NOT ALL EXISTING OUTLETS ARE
NECESSARILY INDICATED ON THE DRAWINGS.
J. CONTRACTOR SHALL MAKE SAFE ALL AREAS OF THE EXISTING STRUCTURE WHICH ARE TO BE DEMOLISHED BY DISCONNECTING
FEEDERS AND SERVICES TO DEMO'D AREAS.
I. PROVIDE EMT UNDER ROOF. SECURE TO STRUCTURE WITH BEAM CLAMPS (SINGLE) OR UNISTRUT (MULTIPLE).
J. PROVIDE IMC ON ROOF FROM ROOF HOODS TO DISCONNECTS.
K. PROVIDE RIGID STEEL CONDUIT ON ROOF FROM ROOF HOODS TO DISCONNECTS.
L. PENETRATE ROOFS AS PER ROOFING GUIDELINES AND GANG CONDUIT TOGETHER. SUPPORT ROOFTOP CONDUIT WITH NEOPRENE
BLOCKS WITH INTEGRAL UNISTRUT. SECURE CONDUIT TO BLOCKS ON ROOF.
M. PROVIDE SEALTITE WITH WP FITTINGS TO MECHANICAL EQUIPMENT, MAX DISTANCE 48”. DO NOT USE CONDUITS.
N. PROVIDE INDIVIDUAL DISCONNECTS FOR ALL SMOKE FIRE DAMPERS AND VAV'S. NO EXCEPTIONS.
O. FIRESTOP ALL CONDUIT PENETRATIONS IN RATED WALLS. SEE ARCHITECTURAL FOR WALL RATINGS. CONTRACTOR SHALL BE
RESPONSIBLE FOR DAMAGE TO SHEET ROCK AND REPAIR.
P. PROVIDE NEMA 3R DISCONNECTS FOR ALL EXTERIOR LOCATIONS AND NEMA 1 DISCONNECTS FOR ALL INTERIOR, DRY LOCATIONS.
Q. POWER AND DATA REQUIREMENTS FOR HVAC CONTROLLERS ARE SHOWN ON POWER SHEETS.
R. ALL EQUIPMENT CONNECTION POINTS ARE DIAGRAMATIC IN NATURE. ELECTRICAL CONTRACTOR SHALL COORDINATE WITH EQUIPMENT INSTALLER FOR EXACT POINT OF CONNECTION. EXTEND FEEDERS IN CONDUIT AS REQUIRED.
ELECTRICAL GENERAL NOTES:
A. CONTRACTOR SHALL CONFORM TO HOSPITAL'S INFECTION CONTROL PROCEDURES WHILE PERFORMING THIS WORK.
CARE SHOULD BE TAKEN TO CONTAIN ALL CONSTRUCTION DUST WITHIN THE REMODELED AREA SO THAT IT DOES NOT TRAVEL TO OTHER AREAS AND INTO THE BUILDING HVAC SYSTEM. PROVIDE NEGATIVE AIR MACHINE AS REQUIRED TO ACCOMPLISH THIS. ALL WORK SHALL BE AS PER THE GUIDELINES ESTABLISHED BY THE
ENVIRONMENTAL SAFETY AND HEALTH DEPARTMENT.
B. COORDINATE DEMOLITION WORK WITH ELECTRICAL AND OTHER DISCIPLINES AS REQUIRED.
C. EQUIPMENT LOCATIONS ARE SHOWN APPROXIMATELY. VERIFY ALL DIMENSIONS AND LOCATIONS AT JOB SITE.
D. IT IS THE CONTRACTOR'S RESPONSIBILITY TO HAVE VERIFIED EXISTING JOBSITE CONDITIONS DURING THE BIDDING PERIOD, SO THEY WILL HAVE DISCOVERED THE FULL SCOPE OF WORK INVOLVED WITH THE MODIFICATION OF THIS EXISTING SPACE. THE SCOPE OF THE WORK SHALL INCLUDE ALL MATERIALS FOR A COMPLETE INSTALLATION INCLUDING DEVICES, EQUIPMENT, OR APPARATUS WHICH MUST BE REROUTED, RELOCATED, OR REMOVED EITHER TEMPORARILY OR PERMANENTLY, OR WHICH MUST BE PROVIDED TO ACCOMMODATE THE INDICATED REMODELING.
NOT ALL EXISTING CONDITIONS ARE NECESSARILY INDICATED ON THE DRAWINGS.
E. WHEN AN EQUIPMENT IS IDENTIFIED TO BE REMOVED, THE OWNER HAS FIRST RIGHT OF REFUSAL BEFORE DISPOSING
OF THAT EQUIPMENT. PROVIDE A MINIMUM OF ONE WEEKS NOTICE PRIOR TO DEMOLITION.
F. PROVIDE ALL NECESSARY CLEAR PATH TO MOVE DEMOLISHED EQUIPMENT OUT OF THE FACILITY AS WELL TO BRING NEW EQUIPMENT INTO THE BUILDING. MODIFY EXISTING PIPING, DUCTWORK CONDUITS, AS REQUIRED TO COMPLETE
THE DEMOLITION.
G. THE "EXISTING" MECHANICAL SYSTEMS INDICATED ON THIS SHEET ARE BASED ON THE INFORMATION AVAILABLE AND MAY BE INCOMPLETE AND INACCURATE. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO VERIFY ACTUAL CONDITIONS AND MAKE SUITABLE ADJUSTMENTS AS NECESSARY TO ACCOMMODATE NEW WORK, AT NO EXTRA COST TO THE OWNER. CONDITIONS DIFFERENT TO THOSE INDICATED SHALL BE INCORPORATED INTO THE CONSTRUCTION DOCUMENTS. NOTE THAT ANY UNCOVERED SYSTEMS MUST BE CAREFULLY IDENTIFIED PRIOR TO
MODIFICATIONS.
H. CONTRACTOR SHALL COORDINATE WORK WITH ALL TRADES AND INCLUDE ANY MODIFICATIONS NEEDED TO
ACCOMMODATE THEIR WORK.
MECHANICAL GENERAL DEMOLITION NOTES:
A. COORDINATE DEMOLITION WORK WITH ELECTRICAL AND OTHER DISCIPLINES AS REQUIRED.
B. FIXTURE LOCATIONS ARE SHOWN APPROXIMATELY. VERIFY ALL DIMENSIONS AND LOCATIONS AT JOB SITE.
C. IT IS THE CONTRACTOR'S RESPONSIBILITY TO HAVE VERIFIED EXISTING JOBSITE CONDITIONS DURING THE BIDDING PERIOD, SO THEY WILL HAVE DISCOVERED THE FULL SCOPE OF WORK INVOLVED WITH THE MODIFICATION OF THIS EXISTING SPACE. THE SCOPE OF THE WORK SHALL INCLUDE ALL MATERIALS FOR A COMPLETE INSTALLATION INCLUDING DEVICES, EQUIPMENT, OR APPARATUS WHICH MUST BE REROUTED, RELOCATED, OR REMOVED EITHER TEMPORARILY OR PERMANENTLY, OR WHICH MUST BE PROVIDED TO ACCOMMODATE THE INDICATED REMODELING.
NOT ALL EXISTING CONDITIONS ARE NECESSARILY INDICATED ON THE DRAWINGS.
D. WHEN AN FIXTURE IS IDENTIFIED TO BE REMOVED, THE OWNER HAS FIRST RIGHT OF REFUSAL BEFORE DISPOSING
OF THAT FIXTURE. PROVIDE A MINIMUM OF ONE WEEKS NOTICE PRIOR TO DEMOLITION.
E. THE "EXISTING" PLUMBING SYSTEMS INDICATED ON THIS SHEET ARE BASED ON THE INFORMATION AVAILABLE AND MAY BE INCOMPLETE AND INACCURATE. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO VERIFY ACTUAL CONDITIONS AND MAKE SUITABLE ADJUSTMENTS AS NECESSARY TO ACCOMMODATE NEW WORK, AT NO EXTRA COST TO THE OWNER. CONDITIONS DIFFERENT TO THOSE INDICATED SHALL BE INCORPORATED INTO THE CONSTRUCTION DOCUMENTS. NOTE THAT ANY UNCOVERED SYSTEMS MUST BE CAREFULLY IDENTIFIED PRIOR TO
MODIFICATIONS.
F. CONTRACTOR SHALL COORDINATE WORK WITH ALL TRADES AND INCLUDE ANY MODIFICATIONS NEEDED TO
ACCOMMODATE THEIR WORK.
G. CONTRACTOR TO COORDINATE THE SHUT-DOWN ON ANY EXISTING SYSTEM(S) WITH THE FACILITIES DIRECTOR OF
MAINTENANCE.
H. THE EXISTING WET-PIPE FIRE SPRINKLER SYSTEM WITHIN THIS PROJECT SHALL BE MODIFIED AS NECESSARY TO
ACCOMMODATE ARCHITECTURAL CHANGES.
I. ALL WORK SHALL CONFORM TO ALL STATE AND LOCAL CODES, RULES AND REGULATIONS, AND ORDINANCES.
J. PLUMBING PLANS ARE DIAGRAMMATIC ONLY. THEY ARE INTENDED TO INDICATE CAPACITY, SIZE, LOCATION, DIRECTION AND GENERAL ARRANGEMENT. WHERE NOT SPECIFICALLY SHOWN ON PLANS, CONTRACTOR SHALL APPLY PROFESSIONAL STANDARDS SUCH AS THAT OF THE AMERICAN SOCIETY OF PLUMBING ENGINEERS.
K. WORK SHALL INCLUDE ALL LABOR, MATERIALS, PERMITS AND OTHER COSTS AS ARE NECESSARY FOR THE INSTALLATION OF A COMPLETE AND SATISFACTORY OPERATIONAL PLUMBING AND SANITARY SYSTEM. EQUIPMENT SHALL BE INSTALLED IN SUCH A MANNER AS TO MAINTAIN ITS LISTING AND THE MANUFACTURER'S GUARANTEES
AND WARRANTIES.
L. THIS CONTRACTOR SHALL COORDINATE WITH THE OTHER TRADES TO INSURE THAT EACH TRADE SHALL HAVE SUFFICIENT SPACE TO INSTALL THEIR EQUIPMENT (DUCTWORK, PIPING, ELECTRICAL, ETC.), ALONG WITH THE
PLUMBING WORK.
M. WHERE THE TERM "PROVIDE" IS USED, IT SHALL MEAN "FURNISH AND INSTALL". THE CONTRACTOR SHALL COORDINATE HIS WORK WITH ALL THE OTHER TRADES PRIOR TO THE FABRICATION, PURCHASE AND/OR
INSTALLATION OF THE WORK.
N. UNLESS NOTED, ALL MATERIALS SHALL BE NEW, COMPLETE, INCLUDE MANUFACTURER'S WARRANTY, AND BE U.L.
APPROVED IF APPLICABLE. ALL WORK SHALL PRESENT A NEAT MECHANICAL APPEARANCE WHEN COMPLETED.
O. FIELD VERIFY ALL DIMENSIONS. CONTRACTOR SHALL VERIFY ELEVATION OF UTILITY CONNECTIONS ON SITE PRIOR TO COMMENCING WORK. FINAL CONNECTION TO SITE UTILITIES SHALL BE BY THE PLUMBING CONTRACTOR.
P. PLUMBING SYSTEM INSTALLER SHALL PROVIDE ALL STRUCTURAL MEMBERS, SUPPORT BRACKETS, FLASHING, HARDWARE, ETC., REQUIRED TO INSTALL A COMPLETE SYSTEM.
Q. DRAIN WASTE AND VENT PIPING SHALL BE PVC SCH. 40 WHEN INSTALLED BELOW GRADE OR UNDER CONCRETE
SLABS. DRAIN WASTE AND VENT PIPING INSTALLED ABOVE GRADE SHALL BE PVC SCH. 40.
R. ALL SANITARY PIPING CHANGES OF DIRECTION 45 DEGREES OR MORE SHALL BE ACCOMPLISHED BY USING 45
DEGREE 1/8 BEND ELBOWS UNLESS OTHERWISE NOTED.
S. ALL MODEL NUMBERS INDICATED ARE PROVIDED TO ESTABLISH THE QUALITY LEVEL AND FEATURES REQUIRED.
LISTED MANUFACTURERS AND OTHER PRIOR APPROVED EQUALS MAY BE SUBSTITUTED WHEN PROVIDED WITH EQUAL FEATURES, EITHER STANDARD OR AS ACCESSORIES. SUBSTITUTED AIR DEVICES AND PLUMBING FIXTURES
MUST BE SIMILAR IN APPEARANCE TO THE ITEMS SPECIFICALLY INDICATED.
T. ALL WORK SHALL BE PERFORMED IN A WORKMANLIKE MANNER. CLEAN THE SITE DAILY AND REMOVE FROM THE
PREMISES ANY DIRT AND DEBRIS CAUSED BY THE WORK INCLUDED IN THIS CONTRACT.
U. INSTALL CAST IRON PIPE IN ALL PLENUM RATED SPACES.
PLUMBING GENERAL NOTES:
MEP OVERALL PLAN
1 MEP OVERALL PLAN
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC Elk Consortium +
Texas Registered Architectural Firm
N O
RT
H
F
LO
RE
S
SA
N
A N
TO
N
IO
, T
EX
A
S
0.
3.
SA
N
A N
TO
N
IO
R G
V
P H
O N
E
TB
PE
F
IR
M R
EG
IS
TR
A
TI
O
N N
O
CONSULTANTS
MEP100
100% CD FINAL
8/22/24
PLUMBING KEYED NOTES:
1 MEP ENLARGED DEMOLITION ROOF PLAN - AREAS B&C
MEP ROOF REPLACEMENT
PLAN - AREAS B&C
Audie L. Murphy Memorial Veterans Hospital 7400 Merton Minter BLVD., San Antonio, Texas
200 E. Grayson Street, Suite 207 San Antonio, Texas 78215 210.530.0755 www.westeastdesign.com
WestEast Design Group JV, LLC Elk Consortium +
Texas Registered Architectural Firm
N O
RT
H
F
LO
RE
S
SA
N
A N
TO
N
IO
, T
EX
A
S
0.
3.
SA
N
A N
TO
N
IO
R G
V
P H
O N
E
TB
PE
F
IR
M R
EG
IS
TR
A
TI
O
N N
O
CONSULTANTS
MEP102
100% CD FINAL
8/22/24
ELECTRICAL KEYED NOTES:
PLUMBING KEYED NOTES:
| Sheets and Views |
| 671-21-143-GI0.1 Cover Sheet and Drawing Index-GI0.1 |
| 671-21-143-GI0.2 Document Organization and General Notes-GI0.2 |
| 671-21-143-GI0.3 Campus Map and Demolition Phasing Plan-GI0.3 |
| 671-21-143-GI0.4 Tapered Roof Layout-GI0.4 |
| 671-21-143-AD1.0 Demo Roof Plan-Key Plan-AD1.0 |
| 671-21-143-AD1.1 Demo Roof Plan-Area A-AD1.1 |
| 671-21-143-AD1.2 Demo Roof Plan-Areas B and C-AD1.2 |
| 671-21-143-AD1.3 Demo Roof Plan-Area D-AD1.3 |
| 671-21-143-A1.0 Roof Plan-New Work-Key Plan-A1.0 |
| 671-21-143-A1.1 Roof Plan-New Work-Area A-A1.1 |
| 671-21-143-A1.2 Roof Plan-New Work-Areas B and C-A1.2 |
| 671-21-143-A1.3 Roof Plan-New Work-Area D-A1.3 |
| 671-21-143-A2.0 Roof Details-A2.0 |
| 671-21-143-A2.1 Roof Details-A2.1 |
| 671-21-143-A2.2 Roof Details-A2.2 |
| 671-21-143-A2.3 Roof Details-A2.3 |
| 2024-08-22 VA CT Roof Replacement MEP Sealed.pdf |
| MEP-MEP001 |
| MEP-MEP001 |
| MEP-MEP100 |
| MEP-MEP100 |
| MEP-MEP101 |
| MEP-MEP101 |
| MEP-MEP102 |
| MEP-MEP102 |
File details come from the government source that posted it. Updated .