657-19-128JB Specifications Volume I.pdf
PDF 9 MB Posted
- Solicitation number
- 36C25521R0027
About this file
This solicitation seeks proposals for a construction project to create an elevator tower and stairwell within Building 23 at the Jefferson Barracks VA Medical Center in St. Louis, Missouri. The project is estimated to cost between $2-5 million and have a duration of 383 calendar days. The North American Industry Classification code is 238220 for commercial and institutional building construction. The solicitation will be posted on January 22, 2021 to beta.SAM.gov and proposals are due on an unspecified date. Award will be made using the lowest price technically acceptable process to a service-disabled veteran-owned small business. The successful contractor must self-perform at least 15% of the general construction labor. Attendance at a pre-solicitation site visit is encouraged. Questions should be emailed to the points of contact by the specified deadline.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C25521R0027.docx | DOCX document | |
| 04Drawings Structural.pdf | ||
| 09Drawings Electrical.pdf | ||
| 07Drawings Plumbing.pdf | ||
| 10Drawings Technology.pdf | ||
| 03Drawings Civil_Part3.pdf | ||
| 02Drawings Hazardous Materials.pdf | ||
| 08Drawings Mechanical.pdf | ||
| 06Drawings Fire Protection.pdf | ||
| 05Drawings Architectural.pdf | ||
| 01Drawings General.pdf | ||
| 657-19-128JB Specifications Volume II.pdf | ||
| 03Drawings Civil_Part1.pdf | ||
| 03Drawings Civil_Part2.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
657-19-128JB | Create Elevator Tower and Stairwell, B23
Jefferson Barracks VA Health Care System Bid Documents | Specifications, Volume I January 22, 2021 spur-design.com
405.842.6100 312 SW 25th Street Oklahoma City, OK 73109
816.214.8730 11020 King Street Overland Park, KS 66210
602.584.5010 4747 S. Lakeshore Drive Tempe, AZ 85282
A Service-Disabled Veteran-Owned Small Business
A 312 SW 25th Street Oklahoma City, OK 73109 P 405.842.6100 E howdy@spur-design.com W spur-design.com
CREATE ELEVATOR TOWER & STAIRWELL, BUILDING 23
Specifications
1/22/2021 1/22/2021 1/22/2021
1/22/2021 1/22/2021
Create Elevator Tower & Stairwell, Building 23
VA 657-19-128JB
Saint Louis VAHCS – St. Louis, MO
Bid Documents
07-15-19
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 07-15
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 12-18
01 32 16.15 Project Schedules (Small Projects – Design/Bid/Build 02-15
01 33 23 Shop Drawings, Product Data, and Samples 05-17
01 35 26 Safety Requirements 02-17
01 42 19 Reference Standards 05-16
01 45 00 Quality Control 03-19
01 45 29 Testing Laboratory Services 11-18
01 45 35 Special Inspections 03-19
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 07-15
01 74 19 Construction Waste Management 09-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 08-17
02 82 11 Traditional Asbestos Abatement 04-19
02 82 13.13 Glovebag Asbestos Abatement 09-15
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 09-15
02 82 13.21 Asbestos Roofing Abatement 09-15
02 83 33.13 Lead-Based Paint Removal and Disposal 08-16
DIVISION 03 – CONCRETE
03 30 00 Cast-in-Place Concrete 07-19
03 49 00 Glass-Fiber Reinforced Concrete (GFRC) 02-20
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 10-17
04 05 16 Masonry Grouting 02-16
04 20 00 Unit Masonry 08-17
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-18
Saint Louis VAHCS – St. Louis, MO
00 01 10-2
05 21 00 Steel Joist Framing 11-18
05 31 00 Steel Decking 02-16
05 36 00 Composite Metal Decking 10-15
05 50 00 Metal Fabrications 08-18
05 51 00 Metal Stairs 10-15
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 13 52 Modified Bituminous Sheet Waterproofing 08-16
07 21 13 Thermal Insulation 10-17
07 22 00 Roof and Deck Insulation 02-16
07 24 00 Exterior Insulation and Finish System 02-16
07 27 26 Fluid-Applied Membrane Air Barrier, Vapor Permeable 02-16
07 40 00 Roofing and Siding Panels 10-15
07 54 23 Thermoplastic Polyolefin (TPO) Roofing 08-16
07 60 00 Flashing and Sheet Metal 07-14
07 71 00 Roof Specialties 10-15
07 72 00 Roof Accessories 10-15
07 81 00 Applied Fireproofing 10-17
07 84 00 Firestopping 02-16
07 92 00 Joint Sealants 10-17
07 95 13 Expansion Joint Cover Assemblies 02-16
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 08-16
08 14 00 Interior Wood Doors 02-16
08 31 13 Access Doors and Frames 02-16
08 41 13 Aluminum-Framed Entrances and Storefronts 08-16
08 44 13 Glazed Aluminum Curtain Walls 03-17
08 71 00 Door Hardware 05-19
08 71 13 Automatic Door Operators 02-16
08 80 00 Glazing 10-15
DIVISION 09 – FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 02-15
09 06 00 Schedule for Finishes 04-15
09 22 16 Non-Structural Metal Framing 06-18
09 29 00 Gypsum Board 06-18
09 30 13 Ceramic/Porcelain Tiling 10-15
09 51 00 Acoustical Ceilings 12-18
09 65 13 Resilient Base and Accessories 02-16
09 65 19 Resilient Tile Flooring 05-18
09 91 00 Painting 01-16
DIVISION 10 – SPECIALTIES
Saint Louis VAHCS – St. Louis, MO
00 01 10-3
10 13 00 Directories 05-15
10 14 00 Signage 10-15
10 26 00 Wall and Door Protection 10-15
10 44 13 Fire Extinguisher Cabinets 08-18
DIVISION 11 – EQUIPMENT
DIVISION 12 – FURNISHINGS
12 93 42.13 Site Furnishings/Site Seating
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components
01-14
DIVISION 14– CONVEYING EQUIPMENT
14 24 00 Hydraulic Elevators 10-18
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-16
22 05 12 General Motor Requirements for Plumbing Equipment 09-15
22 05 23 General-Duty Valves for Plumbing Piping 09-15
22 07 11 Plumbing Insulation 09-15
22 11 00 Facility Water Distribution 09-15
22 13 00 Facility Sanitary and Vent Piping 09-15
22 13 23 Sanitary Waste Interceptors 09-15
22 14 00 Facility Storm Drainage 09-15
22 14 29 Sump Pumps 09-15
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 08-17
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
08-17
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
02-15
23 05 93 Testing, Adjusting, and Balancing for HVAC 02-15
23 07 11 HVAC and Boiler Plant Insulation 02-15
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 08-17
Saint Louis VAHCS – St. Louis, MO
00 01 10-4
23 23 00 Refrigerant Piping 02-15
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 02-15
23 36 00 Air Terminal Units 02-15
23 37 00 Air Outlets and Inlets 02-15
23 40 00 HVAC Air Cleaning Devices 02-12
23 81 00 Decentralized Unitary HVAC Equipment 02-11
DIVISION 25 – INTEGRATED AUTOMATION
25 10 10 Advanced Utility Metering System 02-10
DIVISION 26 – ELECTRICAL
26 05 11 Requirements for Electrical Installations 01-16
26 05 19 Low-Voltage Electrical Power Conductors and Cables 01-17
26 05 26 Grounding and Bonding for Electrical Systems 01-17
26 05 33 Raceway and Boxes for Electrical Systems 01-18
26 05 41 Underground Electrical Construction 01-17
26 05 73 Overcurrent Protective Device Coordination Study 01-18
26 08 00 Commissioning of Electrical Systems 11-16
26 09 23 Lighting Controls 01-18
26 24 16 Panelboards 01-18
26 27 26 Wiring Devices 01-18
26 29 21 Enclosed Switches and Circuit Breakers 01-17
26 41 00 Facility Lightning Protection 01-17
26 51 00 Interior Lighting 01-18
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 06-15
27 05 26 Grounding and Bonding for Communications Systems 06-15
27 05 33 Raceways and Boxes for Communications Systems 10-18
27 10 00 Control, Communication and Signal Wiring 06-15
27 11 00 Telecommunications Room Fittings 06-15
27 15 00 Communications Structured Cabling 01-16
27 51 16 Public Address and Mass Notification Systems 10-18
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 04-18
28 05 13 Conductors and Cables for Electronic Safety and
Security
10-18
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 13 00 Physical Access Control System 10-11
28 23 00 Video Surveillance 09-11
28 31 00 Fire Detection and Alarm 10-11
Saint Louis VAHCS – St. Louis, MO
00 01 10-5
DIVISION 31 – EARTHWORK
31 20 00 Earthwork 07-16
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 05 23 Cement and Concrete for Exterior Improvements 08-16
32 17 23 Pavement Markings 08-16
32 90 00 Planting 08-16
DIVISION 33 – UTILITIES
33 10 00 Water Utilities 03-17
33 30 00 Sanitary Sewer Utilities 06-13
33 40 00 Storm Sewer Utilities 12-17
DIVISION 34 – TRANSPORTATION – NOT USED
DIVISION 48 – Electrical Power Generation – NOT USED
Saint Louis VAHCS – St. Louis, MO
Bid Documents
07-01-15
00 01 15 - 1
LIST OF DRAWING SHEETS
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
01 - GENERAL
23-GI-001 COVER SHEET
23-GI-002 GENERAL INFORMATION
02 - HAZARDOUS MATERIALS
23-HA-101 REMEDIATION PLAN - FLOOR 00 - PHASE 1
23-HA-102 REMEDIATION PLAN - FLOOR 01 - PHASE 2
23-HA-103 REMEDIATION PLAN - PHASE 3
23-HA-104 REMEDIATION PLAN - PHASE 4
23-HA-105 REMEDIATION PLAN - FLOOR 00 - PHASE 5
23-HA-106 REMEDIATION PLAN - FLOOR 00 - PHASE 6
03 - CIVIL
23-CS-101 TOPOGRAPHIC SURVEY
23-CD-101 DEMOLITION PLAN
23-CI-101 SITE LAYOUT AND PAVING PLAN
23-CG-101 GRADING AND EROSION CONTROL PLAN
23-CU-101 UTILITY PLAN
23-CU-102 UTILITY PROFILES
23-CU-103 UTILITY PROFILES
23-CU-104 SITE DISTURBANCE PLAN
23-CJ-501 CIVIL DETAILS
23-CJ-502 CIVIL DETAILS
04 - STRUCTURAL
23-SG-001 STRUCTURAL GENERAL NOTES
23-SG-002 SNOW DRIFT PLAN, SYMBOLS, AND ABBREVIATIONS
23-SB-101 FOUNDATION PLAN - FLOOR 00
23-SF-101 FRAMING PLAN - FLOOR 01
23-SF-102 FLOOR 01 STAIR AND RAMP DIMENSION PLAN
23-SF-103 FRAMING PLAN - ROOF
23-SB-501 CONCRETE DETAILS
23-SB-502 CONCRETE DETAILS
23-SB-503 CONCRETE DETAILS
23-SF-501 MASONRY DETAILS
Saint Louis VAHCS – St. Louis, MO
Bid Documents
07-01-15
00 01 15 - 2
LIST OF DRAWING SHEETS
23-SF-502 STEEL FRAMING DETAILS
23-SF-503 STEEL FRAMING DETAILS
05 - ARCHITECTURAL
23-AS-101 ARCHITECTURAL SITE PLAN
23-AL-101 LIFE SAFETY PLAN – FLOOR 00
23-AL-111 LIFE SAFETY PLAN – FLOOR
23-AD-101 DEMOLITION PLAN - FLOOR 00
23-AD-111 DEMOLITION PLAN - FLOOR 01
23-AE-001 PARTITION TYPES
23-AE-101 FLOOR PLAN - FLOOR 00
23-AE-111 FLOOR PLAN - FLOOR 01
23-AE-121 ROOF PLAN
23-AE-201 BUILDING ELEVATIONS
23-AE-202 BUILDING ELEVATIONS
23-AE-301 BUILDING SECTIONS
23-AE-401 WALL SECTIONS
23-AE-411 VERTICAL CIRCULATION
23-AE-412 VERTICAL CIRCULATION
23-AE-413 TEMPORARY CORRIDOR
23-AE-501 BUILDING DETAILS
23-AE-601 INTERIOR ELEVATIONS
23-AC-101 REFLECTED CEILING PLAN - FLOOR 00
23-AC-111 REFLECTED CEILING PLAN - FLOOR 01
23-AF-101 FINISH FLOOR PLANS
23-AP-601 DOOR & WINDOW SCHEDULES
06 - FIRE PROTECTION
23-FG-001 FIRE PROTECTION LEGEND
23-FX-101 FIRE PROTECTION PLAN - FLOOR 00
23-FX-111 FIRE PROTECTION PLAN - FLOOR 01
07 - PLUMBING
23-PG-001 PLUMBING LEGEND
23-PL-101 PLUMBING WASTE PLAN - FLOOR 00
23-PL-111 PLUMBING WASTE PLAN - FLOOR 01
23-PP-101 PLUMBING SUPPLY PLAN - FLOOR 00
23-PP-111 PLUMBING SUPPLY PLAN - FLOOR 01
23-PP-121 PLUMBING PLAN - ROOF
23-PJ-501 PLUMBING DETAILS
23-PJ-502 PLUMBING DETAILS
Saint Louis VAHCS – St. Louis, MO
Bid Documents
07-01-15
00 01 15 - 3
LIST OF DRAWING SHEETS
23-PJ-601 PLUMBING SCHEDULES
08 - MECHANICAL
23-MG-001 MECHANICAL LEGEND
23-MD-101 MECHANICAL PIPING DEMOLITION PLAN - FLOOR 00
23-MH-101 MECHANICAL HVAC PLAN - FLOOR 00
23-MH-111 MECHANICAL HVAC PLAN - FLOOR 01
23-MH-121 MECHANICAL HVAC PLAN - ROOF
23-MP-101 MECHANICAL PIPING PLAN - FLOOR 00
23-MP-111 MECHANICAL PIPING PLAN - FLOOR 01
23-MJ-501 MECHANICAL DETAILS
23-MJ-601 MECHANICAL SCHEDULES
23-MK-701 MECHANICAL CONTROLS
23-MK-702 MECHANICAL CONTROLS
09 - ELECTRICAL
23-EG-000 ELECTRICAL LEGEND
23-ED-101 ELECTRICAL LIGHTING DEMOLITION PLAN - FLOOR 00
23-ED-102 ELECTRICAL POWER DEMOLITION PLAN - FLOOR 00
23-ED-111 ELECTRICAL LIGHTING DEOMOLITION PLAN - FLOOR 01
23-ED-112 ELECTRICAL POWER DEMOLITION PLAN - FLOOR 01
23-EL-101 ELECTRICAL LIGHTING FLOOR PLAN - FLOOR 00
23-EL-111 ELECTRICAL LIGHTING FLOOR PLAN - FLOOR 01
23-EP-101 ELECTRICAL POWER FLOOR PLAN - FLOOR 00
23-EP-111 ELECTRICAL POWER FLOOR PLAN - FLOOR 01
23-EJ-101 ELECTRICAL EQUIPMENT FLOOR PLAN - FLOOR 00
23-EJ-111 ELECTRICAL EQUIPMENT FLOOR PLAN - FLOOR 01
23-EJ-121 ELECTRICAL EQUIPMENT FLOOR PLAN - ROOF
23-EK-501 ELECTRICAL DETAILS
23-EK-601 ELECTRICAL ONE-LINE DIAGRAM AND LIGHT FIXTURE SCHEDULE
23-EK-602 ELECTRICAL SCHEDULES
10 - TECHNOLOGY
23-TG-000 TECHNOLOGY LEGEND
23-TD-101 TECHNOLOGY DEMOLITION PLAN - FLOOR 00
23-TD-102 TECHNOLOGY DEMOLITION PLAN - FLOOR 01
23-TY-101 TECHNOLOGY FLOOR PLAN - FLOOR 00
23-TY-102 TECHNOLOGY FLOOR PLAN - FLOOR 01
23-TJ-501 TECHNOLOGY DETAILS AND SCHEDULES
- - - END - - -
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18 i
SECTION 01 00 00
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1.1 SAFETY REQUIREMENTS
1.2 GENERAL INTENTION
1.3 STATEMENT OF BID ITEM(S)
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
1.5 CONSTRUCTION SECURITY REQUIREMENTS
1.6 OPERATIONS AND STORAGE AREAS
1.7 ALTERATIONS
1.8 DISPOSAL AND RETENTION
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
1.10 RESTORATION
1.11 PHYSICAL DATA
1.12 LAYOUT OF WORK
1.13 AS-BUILT DRAWINGS
1.14 WARRANTY MANAGEMENT
1.15 USE OF ROADWAYS
1.16 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT
1.17 TEMPORARY TOILETS
1.18 AVAILABILITY AND USE OF UTILITY SERVICES
1.19 TESTS
1.20 INSTRUCTIONS
1.21 GOVERNMENT-FURNISHED PROPERTY
1.22 RELOCATED EQUIPMENT AND ITEMS
1.23 CONSTRUCTION SIGN
1.24 SAFETY SIGN
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing assemblies, and furnish labor and materials and perform work for the new addition of an elevator & stair tower as required by drawings and specifications.
B. Visits to the site by Bidders may be made only by appointment with the
Medical Center Engineering Officer.
C. Offices of Spur Design, as Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.
D. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. ITEM I, GENERAL CONSTRUCTION: Work includes general construction, temporary construction, alterations, walks, grading, drainage, necessary partial removal of existing structures and certain other items, including electrical, mechanical, technology and electronic
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -2 security necessary to construct a new stair and elevator tower at
Building 23. Existing fiber-optic lines and supports are to be protected and remain in-place during construction throughout the entire construction period. The construction period is estimated to be 485 days.
B. ITEM II, ALTERNATE NO.1: Items I above, except omit Glass Fiber
Reinforced Concrete (GFRC) Panel System and replace with Exterior
Insulation Finish System (EIFS). Note that reveals & panel modules shall maintain similar appearance in finish texture & profiles by area.
The construction period is estimated to be 475 days.
C. ITEM III, ALTERNATE NO. 2: Items I & II above, except omit TPO roofing and replace with modified bituminous roofing system. The construction period is estimated to be 475 days.
D. ITEM IV, ALTERNATE NO. 3: Items I, II & III above, except omit all ceiling finishes. All lighting, HVAC and related ceiling-mounted items to be suspended from structure. The construction period is estimated to be 459 days.
E. ITEM V, ALTERNATE NO. 4: Items I, II, III & IV above, except omit aluminum storefront windows, Type A, at north and east elevations.
Infill shall be typical wall construction & finishes with no indication of window opening. The construction period is estimated to be 457 days.
F. ITEM VI, ALTERNATE NO. 5: Items I, II, III, IV & V above, except omit budget requirement to provide landscape planting elements. The construction period is estimated to be 457 days.
G. ITEM VII, ALTERNATE NO. 6: Items I, II, III, IV, V & VI above, except omit budget requirement to provide irrigation system and related components. The construction period is estimated to be 457 days.
H. ITEM VIII, ALTERNATE NO. 7: Items I, II, III, IV, V, VI & VII above, except omit sod material, installation, and watering, and replace with hydroseeding in broadcast spray application throughout designated areas. The construction period is estimated to be 457 days.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -3
I. ITEM IX, ALTERNATE NO. 8: Items I, II, III, IV, V, VI, VII, & VIII above, except mot wall tile to head-height of Level 01 windows, and replace with 4’-0” wainscot-height tile finish throughout. The construction period is estimated to be 447 days.
J. ITEM X, ALTERNATE NO. 9: Items I, II, III, IV, V, VI, VII, VIII & IX above, except omit wall tile and provide paint finish to all exposed
CMU interior wall areas. The construction period is estimated to be 442 days.
K. ITEM XI, ALTERNATE NO. 10: Items I, II, III, IV, V, VI, VII, VIII, IX &
X above, except omit the painted super graphic at the stair-side wall of the Floor 00 Lobby. The construction period is estimated to be 441 days.
L. ITEM XII, ALTERNATE NO. 11: Items I, II, III, IV, V, VI, VII, VIII, IX, X & XI above, except omit luxury vinyl tile (LVT) flooring, and replace with sealed concrete. The construction period is estimated to be 439 days.
M. ITEM XIII, ALTERNATE NO. 12: Items I, II, III, IV, V, VI, VII, VIII, IX, X, XI & XII above, except omit the foundation, walls, roof, and associated items required for the Utility Chase 004. Any utility lines currently utilizing this space shall be routed to follow the existing fiber lines remaining in place. The construction period is estimated to be 439 days.
N. ITEM XIV, ALTERNATE NO. 13: Items I, II, III, IV, V, VI, VII, VIII, IX, X, XI, XII & XIII above, except omit the temporary corridor and associated elements for alternate routing from the existing Connecting
Corridor to Building 23. The construction period is estimated to be 419 days.
O. ITEM XV, ALTERNATE NO. 14: Items I, II, III, IV, V, VI, VII, VIII IX, X, XI, XII, XIII & XIV above, except omit the temporary corridor and associated elements for alternate routing from the existing Connecting
Corridor to Building 23, and replace with wood-framed canopy/ramp connection between the connecting corridor and Building 23. The construction period is estimated to be 439 days.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -4
1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR
A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.
1.5 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give two week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
C. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -5 including tool boxes and parked machines and take any emergency action.
2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71
00, DOOR HARDWARE and coordinate.
D. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -6
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
E. Motor Vehicle Restrictions
1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.
2. A limited number of (2 to 5) permits shall be issued for General
Contractor and its employees for parking in designated areas only.
1.6 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways, or use temporary roadways constructed by the Contractor when and as authorized by the Contracting
Officer. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -7
Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workers are subject to rules of Medical Center applicable to their conduct.
F. Execute work so as to interfere as little as possible with normal functioning of the Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two workdays. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR or Utility Company involved.
H. Phasing:
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -8
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To ensure such executions, Contractor shall furnish the COR with a schedule of approximate phasing on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing to ensure accomplishment of this work in successive phases mutually agreeable to
Medical Center Director, COR and Contractor, as follows:
Phase I: Mobilization, Excavation, Site Demolition, Building Demolition
Phase II: Foundation Work, Site Work
Phase III: General Exterior and Interior Construction
I. Building No. 23 will be occupied during performance of work; but immediate areas of alterations will be vacated.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -9
Veterans Affairs so that Medical Center operations will continue during the construction period.
2. Immediate areas of alterations not mentioned in preceding
Subparagraph 1 will be temporarily vacated while alterations are performed.
J. Construction Fence: Before construction operations begin, Contractor shall provide a chain link construction fence, 2.1m (seven feet) minimum height, around the construction area indicated on the drawings.
Provide gates as required for access with necessary hardware, including hasps and padlocks. Fasten fence fabric to terminal posts with tension bands and to line posts and top and bottom rails with tie wires spaced at maximum 375mm (15 inches). Bottom of fences shall extend to 25mm
(one inch) above grade. Remove the fence when directed by COR.
K. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
1. Contractor shall maintain a minimum temperature of 4 degrees C (40 degrees F) at all times, except as otherwise specified.
2. Contractor shall maintain in operating condition existing fire protection and alarm equipment. In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from
Contractor's employee or watchman.
L. Utilities Services: Maintain existing utility services for Medical
Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services.
Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -10
1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems may be interrupted without prior approval of the COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR
COMMUNICATIONS INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR
ELECTRONIC SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 21 days in advance of proposed interruption and 48 hour notice for “hot” work permit. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of the Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 21 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the Contractor.
M. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -11 be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from.
N. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
2. Method and scheduling of required cutting, altering and removal of existing roads, walks and entrances must be approved by the COR.
O. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.7 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR and a representative of VA Supply Service, of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by all three, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of the building.
2. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment, venetian blinds, shades, etc., required by drawings to be either reused or relocated, or both.
3. Shall note any discrepancies between drawings and existing conditions at site.
4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -12
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR and/or Supply Representative, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by
Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE
CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR 52.243-4 and VAAR
852.236-88).
C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workers in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -13
1.8 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from the Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND
IMPROVEMENTS
A. The Contractor shall preserve and protect all structures, equipment, and vegetation (such as trees, shrubs, and grass) on or adjacent to the work site, which are not to be removed and which do not unreasonably interfere with the work required under this contract. The Contractor shall only remove trees when specifically authorized to do so, and shall avoid damaging vegetation that will remain in place. If any limbs or branches of trees are broken during contract performance, or by the careless operation of equipment, or by workers, the Contractor shall trim those limbs or branches with a clean cut and paint the cut with a tree-pruning compound as directed by the Contracting Officer.
B. The Contractor shall protect from damage all existing improvements and utilities at or near the work site and on adjacent property of a third party, the locations of which are made known to or should be known by
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -14 the Contractor. The Contractor shall repair any damage to those facilities, including those that are the property of a third party, resulting from failure to comply with the requirements of this contract or failure to exercise reasonable care in performing the work. If the
Contractor fails or refuses to repair the damage promptly, the
Contracting Officer may have the necessary work performed and charge the cost to the Contractor.
(FAR 52.236-9)
C. Refer to Section 01 57 19, TEMPORARY ENVIRONMENTAL CONTROLS, for additional requirements on protecting vegetation, soils, and the environment. Refer to Articles, "Alterations", "Restoration", and
"Operations and Storage Areas" for additional instructions concerning repair of damage to structures and site improvements.
1.10 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -15
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.11 PHYSICAL DATA
A. Data and information furnished or referred to below is for the
Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by IMEG Corp.
(FAR 52.236-4)
B. Subsurface conditions have been developed by core borings and test pits.
C. A copy of the soil report will be made available for inspection by bidders upon request to the Engineering Officer at the VA Medical
Center, and shall be considered part of the contract documents.
D. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations. Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to Department of
Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.
1.12 LAYOUT OF WORK
A. The Contractor shall lay out the work from Government established base lines and bench marks, indicated on the drawings, and shall be responsible for all measurements in connection with the layout. The
Contractor shall furnish, at Contractor's own expense, all stakes, templates, platforms, equipment, tools, materials, and labor required
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -16 to lay out any part of the work. The Contractor shall be responsible for executing the work to the lines and grades that may be established or indicated by the Contracting Officer. The Contractor shall also be responsible for maintaining and preserving all stakes and other marks established by the Contracting Officer until authorized to remove them.
If such marks are destroyed by the Contractor or through Contractor's negligence before their removal is authorized, the Contracting Officer may replace them and deduct the expense of the replacement from any amounts due or to become due to the Contractor.
(FAR 52.236-17)
B. Establish and plainly mark center lines for each building and corner of column lines and/or addition to each existing building, and such other lines and grades that are reasonably necessary to properly assure that location, orientation, and elevations established for each such structure and/or addition, are in accordance with lines and elevations shown on contract drawings.
C. Following completion of general mass excavation and before any other permanent work is performed, establish and plainly mark (through use of appropriate batter boards or other means) sufficient additional survey control points or system of points as may be necessary to assure proper alignment, orientation, and grade of all major features of work. Survey shall include, but not be limited to, location of lines and grades of footings, exterior walls, center lines of columns in both directions, major utilities and elevations of floor slabs:
1. Such additional survey control points or system of points thus established shall be checked and certified by a registered land surveyor or registered civil engineer. Furnish such certification to the COR before any work (such as footings, floor slabs, columns, walls, utilities and other major controlling features) is placed.
D. During progress of work, and particularly as work progresses from floor to floor, Contractor shall have line grades and plumbness of all major form work checked and certified by a registered land surveyor or registered civil engineer as meeting requirements of contract drawings.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -17
Furnish such certification to the COR before any major items of concrete work are placed.
E. Whenever changes from contract drawings are made in line or grading requiring certificates, record such changes on a reproducible drawing bearing the registered land surveyor or registered civil engineer seal, and forward these drawings upon completion of work to COR.
F. Upon completion of the work, the Contractor shall furnish the COR one electronic copy nd reproducible drawings at the scale of the contract drawings, showing the finished grade on the grid developed for constructing the work. These drawings shall bear the seal of the registered land surveyor or registered civil engineer.
G. The Contractor shall perform the surveying and layout work of this and other articles and specifications in accordance with the provisions of
Article "Professional Surveying Services".
1.13 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR’s review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.14 WARRANTY MANAGEMENT
A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit two sets of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -18
Government receives all warranties to which it is entitled. The plan must be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term “status” as indicated below must include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase must be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work. The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer. Include in the warranty management plan, but not limited to, the following:
1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.
2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.
3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.
4. A list for each warranted equipment item, feature of construction or system indicating:
a. Name of item.
b. Model and serial numbers.
c. Location where installed.
d. Name and phone numbers of manufacturers and suppliers.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -19
e. Name and phone numbers of manufacturers or suppliers.
f. Names, addresses and phone numbers of sources of spare parts.
g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties must be indicated with separate warranty expiration dates.
h. Starting point and duration of warranty period.
i. Summary of maintenance procedures required to continue the warranty in force.
j. Cross-reference to specific pertinent Operation and Maintenance manuals.
k. Organizations, names and phone numbers of persons to call for warranty service.
l. Typical response time and repair time expected for various warranted equipment.
5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.
6. Procedure and status of tagging of all equipment covered by extended warranties.
7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.
B. Performance Bond: The Performance Bond must remain effective throughout the construction period.
1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.
Saint Louis VAHCS – St. Louis, MO
Bid Documents
12-01-18
01 00 00 -20
2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.
3. Following oral or written…