608460 Bid Items.txt

TXT text file 8 KB Posted

Attached to
608460 HADLEY FAP No. NHP(BRR-ON)-003S(813)X Bridge Replacement, H-01-005, Bay Road (Route 47) ove
Solicitation number
BD-25-1030-0H100-0H002-116001
Issued by
Hampshire County, Massachusetts

About this file

The file is a detailed bid items list for a bridge replacement project issued by the Massachusetts Department of Transportation (MassDOT) Highway Division, specifically for the Bay Road (Route 47) bridge over the Fort River in Hadley, Massachusetts. The project (ID 608460) involves comprehensive bridge infrastructure replacement, with electronic proposal submissions required by Tuesday, June 17, 2025, at 2:00 P.M. The bid items list contains over 150 line items covering a wide range of construction activities, including clearing and grubbing, excavation, drainage structure installation, water pipe work, pavement construction, guardrail installation, environmental management, landscaping, traffic control, and bridge structural components. Bidders must be pre-qualified in the BRIDGE-CONSTRUCTION category and possess a valid MassDOT vendor code and Digital ID obtained at least 14 days before the bid opening.

The project is federally funded with an estimated budget of $6,230,000, requiring a 5% Proposal Guaranty. Contractors must comply with federal and state specifications, including provisions for minority and female participation, non-discrimination guidelines, and Disadvantaged Business Enterprise opportunities. Material cost adjustments are permitted for specific items like hot mix asphalt, Portland cement, diesel fuel, gasoline, and steel, providing financial flexibility. The project includes detailed requirements for environmental health and safety, soil disposal, contaminated groundwater treatment, and comprehensive erosion and sedimentation control. Bidders must demonstrate technical expertise in bridge construction, financial stability, and the ability to meet complex regulatory requirements across multiple domains of civil infrastructure development.

Text of this file

PRO_FILENO = 608460,DESCPT = Bridge Replacement, H-01-005, Bay Road (Route 47) over the Fort River,Location = HADLEY,DB_CONTRACT = 130088

OFF_QUANT,UNITS,DESCPT1,ITEM_NO

"1.000","A","CLEARING AND GRUBBING","101."

"250.000","FT","TREE TRIMMING","102.1"

"16.000","HR","HERBICIDE TREATMENT OF INVASIVE PLANTS","102.3"

"16.000","HR","INVASIVE PLANT MANAGEMENT STRATEGY","102.33"

"10.000","EA","TREE PROTECTION - ARMORING AND PRUNING","102.511"

"145.000","FT","TREE AND PLANT PROTECTION FENCE","102.521"

"1.000","LS","DEMOLITION OF SUPERSTRUCTURE OF BRIDGE NO. H-01-005","114.1"

"150.000","CY","EARTH EXCAVATION","120."

"3.000","CY","CLASS A ROCK EXCAVATION","121."

"15.000","CY","REINFORCED CONCRETE EXCAVATION","127.1"

"81.000","EA","TIMBER PILE - REMOVED AND DISCARDED","127.51"

"515.000","CY","BRIDGE EXCAVATION","140."

"10.000","CY","TEST PIT FOR EXPLORATION","141.1"

"100.000","CY","CLASS B TRENCH EXCAVATION","142."

"1500.000","CY","CHANNEL EXCAVATION","143."

"155.000","CY","CLASS B ROCK EXCAVATION","144."

"2.000","EA","DRAINAGE STRUCTURE REMOVED","146."

"740.000","CY","ORDINARY BORROW","150."

"590.000","CY","GRAVEL BORROW","151."

"235.000","CY","GRAVEL BORROW FOR BRIDGE FOUNDATION","151.1"

"150.000","CY","GRAVEL BORROW FOR BACKFILLING STRUCTURES AND PIPES","151.2"

"80.000","CY","SAND BORROW","154."

"495.000","TON","CRUSHED STONE","156."

"2050.000","SY","FINE GRADING AND COMPACTING - SUBGRADE AREA","170."

"1.000","LS","ENVIRONMENTAL HEALTH AND SAFETY PROGRAM","180.01"

"350.000","HR","PERSONAL PROTECTION LEVEL C UPGRADE","180.02"

"150.000","HR","LICENSED SITE PROFESSIONAL SERVICES","180.03"

"95.000","TON","DISPOSAL OF UNREGULATED SOIL","181.11"

"175.000","TON","DISPOSAL OF REGULATED SOIL - IN-STATE FACILITY","181.12"

"690.000","TON","DISPOSAL OF REGULATED SOIL - OUT-OF-STATE FACILITY","181.13"

"45.000","TON","DISPOSAL OF HAZARDOUS WASTE","181.14"

"1.000","LS","INSPECTION AND TESTING FOR ASBESTOS","182.1"

"100.000","FT","REMOVAL OF ASBESTOS","182.2"

"500.000","GAL","TREATMENT OF CONTAMINATED GROUNDWATER","183.1"

"500.000","LB","DISPOSAL OF GRANULAR ACTIVATED CARBON","183.2"

"85.000","TON","DISPOSAL OF TREATED WOOD PRODUCTS","184.1"

"2.000","EA","CATCH BASIN","201."

"1.000","EA","MANHOLE","202."

"1.000","EA","DROP INLET, TYPE C","208."

"1.000","EA","FRAME AND COVER","221."

"2.000","EA","FRAME AND GRATE - MASSDOT CASCADE TYPE","222.1"

"1.000","EA","FRAME AND GRATE - MASSDOT DROP INLET","222.2"

"2.000","EA","FRAME AND GRATE (OR COVER) REMOVED AND STACKED","223.1"

"3.000","CY","REMOVAL OF DRAINAGE STRUCTURE SEDIMENT","227.3"

"50.000","FT","REMOVAL OF DRAINAGE PIPE SEDIMENT","227.31"

"100.000","FT","12 INCH CORRUGATED METAL PIPE 16 GAGE","230.112"

"100.000","FT","12 INCH REINFORCED CONCRETE PIPE CLASS III","241.12"

"1.000","EA","12 INCH REINFORCED CONCRETE PIPE CHECK VALVE","241.121"

"10.000","SY","STONE FOR PIPE ENDS","258."

"5.000","SY","HOT MIX ASPHALT WATERWAY","280."

"250.000","FT","12 INCH DUCTILE IRON WATER PIPE (RUBBER GASKET)","302.12"

"210.000","FT","12 INCH DUCTILE IRON WATER PIPE (MECHANICAL JOINT)","303.12"

"2400.000","LB","DUCTILE IRON FITTINGS FOR WATER PIPE","309."

"400.000","FT","8 INCH WATER MAIN REMOVED AND STACKED","315.08"

"3.000","EA","12 INCH GATE AND GATE BOX","350.12"

"1.000","EA","8 INCH GATE BOX","357.08"

"2.000","EA","12 INCH GATE BOX","357.12"

"2.000","EA","12 INCH COUPLING","371.12"

"215.000","FT","12 INCH WATER PIPE INSULATION","373.12"

"1.000","EA","3/4 INCH AIR RELEASE VALVE","379.075"

"2000.000","SY","RECLAIMED PAVEMENT FOR BASE COURSE AND/OR SUB-BASE","403."

"340.000","SY","PAVEMENT FINE MILLING","415.2"

"9400.000","LB","CALCIUM CHLORIDE FOR ROADWAY DUST CONTROL","440."

"6.500","MGL","WATER FOR ROADWAY DUST CONTROL","443."

"290.000","TON","SUPERPAVE INTERMEDIATE COURSE - 12.5 (SIC -12.5)","450.31"

"650.000","TON","SUPERPAVE BASE COURSE - 37.5 (SBC - 37.5)","450.42"

"210.000","TON","SUPERPAVE BRIDGE SURFACE COURSE - 9.5 (SSC-B - 9.5)","450.60"

"45.000","TON","SUPERPAVE BRIDGE PROTECTIVE COURSE - 9.5 (SPC-B - 9.5)","450.70"

"30.000","TON","HMA FOR PATCHING","451."

"375.000","GAL","ASPHALT EMULSION FOR TACK COAT","452."

"2330.000","FT","HMA JOINT SEALANT","453."

"5.000","TON","TEMPORARY ASPHALT PATCHING","472."

"375.000","FT","GRANITE CURB TYPE VA4 - STRAIGHT","504."

"4.000","EA","GRANITE CURB TYPE VA4 - SPLAYED END","504.2"

"75.000","FT","GRANITE TRANSITION CURB FOR PEDESTRIAN CURB RAMPS - STRAIGHT","509."

"2.000","EA","GRANITE CURB INLET - STRAIGHT","514."

"24.000","FT","CURB REMOVED AND DISCARDED","594."

"1.000","EA","CURB INLET REMOVED AND DISCARDED","595."

"680.000","FT","GUARDRAIL, TL-3 (SINGLE FACED)","620.13"

"6.000","EA","GUARDRAIL TANGENT END TREATMENT, TL-3","627.83"

"4.000","EA","TRANSITION TO BRIDGE RAIL","628.24"

"340.000","FT","HIGHWAY GUARD REMOVED AND DISCARDED","630.2"

"650.000","FT","TEMPORARY FENCE","657."

"1700.000","FT","TEMPORARY FENCE REMOVED AND RESET","657.5"

"12.000","EA","SILT SACK","697.1"

"160.000","SY","GEOTEXTILE FABRIC FOR TEMPORARY SOIL PROTECTION","698.31"

"10.000","SY","CEMENT CONCRETE SIDEWALK","701."

"20.000","SY","CEMENT CONCRETE PEDESTRIAN CURB RAMP","701.2"

"30.000","TON","HOT MIX ASPHALT SIDEWALK OR DRIVEWAY","702."

"2.000","EA","MAIL BOX REMOVED AND RESET","715.1"

"1.000","LS","SCHEDULE OF OPERATIONS (TYPE B) - FIXED PRICE $48000","722.2"

"45.000","MO","ENGINEER'S FIELD OFFICE AND EQUIPMENT (TYPE A)","740."

"1.000","LS","MOBILIZATION","748."

"255.000","CY","LOAM FOR ROADSIDES","751."

"5.000","CY","COMPOST BLANKET","751.7"

"105.000","SY","WETLAND RESTORATION","755.45"

"1.000","LS","CONSTRUCTION PERIOD POLLUTION PREVENTION AND EROSION AND SEDIMENTATION CONTROL PLAN","756.1"

"1865.000","SY","SEEDING","765."

"5.000","LB","PART SHADE ROADSIDE MIX","765.451"

"2.000","LB","WETLAND MIX - PART SHADE","765.555"

"1840.000","SY","NATIVE SEEDING AND ESTABLISHMENT","765.635"

"1430.000","FT","SEDIMENT CONTROL BARRIER","767.121"

"100.000","FT","SEDIMENT BARRIER - COIR LOG","767.122"

"860.000","FT","PAVEMENT MILLING MULCH UNDER GUARD RAIL","769."

"2.000","EA","MAPLE - RED 2-2.5 INCH CALIPER","776.523"

"10.000","EA","BIRCH - RIVER HERITAGE 8-10 FOOT CLUMP","778.164"

"6.000","EA","BLUEBERRY - HIGHBUSH 2-3 FEET / #3","789.633"

"28.000","EA","DOGWOOD - REDOSIER 18-24 INCH / #1","790.631"

"15.000","EA","DOGWOOD - SILKY 2-3 FEET / #3","790.719"

"23.000","EA","ELDERBERRY 2-3 FEET / #2","791.033"

"10.000","EA","VIBURNUM - ARROWWOOD 3-4 FEET / #5","795.013"

"20.000","EA","WINTERBERRY - MALE 24-30 INCH / #3","795.153"

"8.000","EA","WITCH HAZEL - SPRING BLOOMING 2-3 FEET / #3","795.189"

"1.000","LS","PORTABLE SOLAR POWERED TRAFFIC SIGNAL SYSTEM","816.71"

"150.000","DAY","TRAFFIC CONES FOR TRAFFIC MANAGEMENT","851.1"

"560.000","SF","SAFETY SIGNING FOR TRAFFIC MANAGEMENT","852."

"9.000","EA","PORTABLE BREAKAWAY BARRICADE TYPE III","853.1"

"630.000","FT","TEMPORARY BARRIER REMOVED AND RESET","853.21"

"310.000","FT","TEMPORARY BARRIER (TL-3)","853.23"

"140.000","FT","TEMPORARY BARRIER - LIMITED DEFLECTION (TL-3)","853.33"

"8.000","DAY","TRUCK MOUNTED ATTENUATOR","853.403"

"2.000","EA","TEMPORARY IMPACT ATTENUATOR (TL-3) REMOVED AND RESET","853.501"

"2.000","EA","TEMPORARY IMPACT ATTENUATOR UNIDIRECTIONAL, NON-REDIRECTIVE (TL-3)","853.53"

"50.000","DAY","TEMPORARY ILLUMINATION FOR WORK ZONE","853.8"

"8000.000","FT","TEMPORARY PAVING MARKINGS - 6 INCH (PAINTED)","854.016"

"3320.000","SF","PAVEMENT MARKING REMOVAL","854.1"

"50.000","DAY","ARROW BOARD","856."

"1610.000","DAY","REFLECTORIZED DRUMS WITH SEQUENTIAL FLASHING WARNING LIGHTS","859.1" "1550.000","FT","6 INCH REFLECTORIZED WHITE LINE (POLYUREA) (RECESSED)","866.206" "1550.000","FT","6 INCH REFLECTORIZED YELLOW LINE (POLYUREA) (RECESSED)","867.206"

"2.000","EA","TRAFFIC SIGN REMOVED AND RESET","874.2"

"14.000","CY","4000 PSI, 1.5 INCH, 565 CEMENT CONCRETE","901."

"35.000","LB","STEEL REINFORCEMENT FOR STRUCTURES","910."

"900.000","FT","STEEL PILE HP 12 X 84","942.124"

"730.000","FT","STEEL PIPE PILE 24 INCH OUTSIDE DIAMETER","943.24"

"1.000","EA","SHORT DURATION LOAD TEST","948.1"

"5.000","EA","DYNAMIC LOAD TEST PREPARATION","948.4"

"5.000","EA","DYNAMIC LOAD TEST BY CONTRACTOR","948.41"

"26.000","EA","PILE SHOES","948.5"

"1080.000","SF","TEMPORARY EARTH SUPPORT SYSTEMS","950.11"

"720.000","CY","RIPRAP","983.2"

"165.000","CY","STREAMBED RESTORATION","983.521"

"1.000","LS","CONTROL OF WATER - STRUCTURE NO. H-01-005","991.1"

"1.000","LS","TEMPORARY WALKWAY STRUCTURE","993.5"

"1.000","LS","BRIDGE STRUCTURE, BRIDGE NO. H-01-005","995.01"

Other files

File Type Posted
A00844-608460.pdf PDF
HADLEY-608460-130088-A-1.pdf PDF
A00828-608460.pdf PDF
A00820-608460.pdf PDF
A00841-608460.pdf PDF
608460 - Bid Tabulations.pdf PDF
608460 - Notice to Contractors.pdf PDF
A00804-608460.pdf PDF
A00819-608460.pdf PDF
HADLEY-608460-130088-A-2.pdf PDF
A00834-608460.pdf PDF
A00801-608460~1.pdf PDF
Link to Bid Opening 9-3-2025~2.pdf PDF
A00826-608460.pdf PDF
BIDS OPENED - Wednesday - September 3-2025.pdf PDF
A00802-608460.pdf PDF
A00846-608460.pdf PDF
A00810-608460.pdf PDF
A00831-608460.pdf PDF
608460 - Updated Plan Holders List.pdf PDF
A00875-608460.pdf PDF
A00808-608460.pdf PDF
A00818-608460.pdf PDF
A00811-608460.pdf PDF
608460 - Plan Holders List~1.pdf PDF
A00829-608460.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .