6 - Technical Requirements. Edits 12-09-20.pdf

PDF 121 KB Posted

Attached to
Ellicott Slough NWR Lead/Asbestos Abate and Demo
Solicitation number
140F0321Q0007
Issued by

About this file

This document provides technical requirements for abatement, demolition, removal, disposal, and construction projects for the U.S. Fish and Wildlife Service. It outlines quality control and safety standards, as well as procedures for submittals, site access, cleanup, and closeout documents. Key requirements include asbestos and lead abatement, structure demolition and removal, and compliance with all applicable environmental and safety regulations. The contractor must develop schedules, conduct commissioning and training, and submit operation manuals and as-built drawings. Adherence to technical specifications on abatement, demolition methods, and construction activities is mandatory.

View the file

Other files

File Type Posted
Sol_140F0321Q0007_Amd_0001.pdf PDF
Site Photos_0001.pdf PDF
1 - ESNWR. Revised Pricing Schedule. Edits 01-12_0001.xlsx XLSX spreadsheet
Site Visit Minutes. ESNWR. 12-29-20_0001.docx DOCX document
Drawing showing Potential Perimeter Line_0001.pdf PDF
Questions and Responses. 01-12_0001.xlsx XLSX spreadsheet
5 - ESNWR. Revised DIV 01_General Requirements. Edits 01-12_0001.docx DOCX document
3 - ESNWR. Revised SOW. Edits 01-12_0001.docx DOCX document
9 - Site Visit Sign-in Sheet_0001.doc DOC document
4 - ESNWR. Revised Requirements Document. Edits 01-12_0001.doc DOC document
10 - CAD Design Checklist.pdf PDF
3.a. - Lead and Asbestos Survey Report. Harkin's Slough. 10.2.2020.pdf PDF
3 - ESNWR. SOW. Edits 12-08-20.pdf PDF
10 - ESNWR. Beta.SAM Website Instructions to Contractors. 12-09-20.pdf PDF
9 - CAD Standards Manual.pdf PDF
1 - ESNWR. Pricing Schedule. 12-8-20.xlsx XLSX spreadsheet
4 - ESNWR. Requirements Document. Edits 12-08-20.pdf PDF
1 - ESNWR. Pricing Schedule. 12-8-20.pdf PDF
2 - ESNWR. Subcontract List. 12-09-20.pdf PDF
5 - ESNWR. DIV 01_General Requirements. Edits 12-08-20.pdf PDF
8.- Past Performance Questionnaires.pdf PDF
11 - Pre-Work Safety Checklist.pdf PDF
Sol_140F0321Q0007.pdf PDF
7 - Pre-Quote Site Visit. 12-20.pdf PDF
12- DOL Wage Determination.pdf PDF
Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ELLICOTT SLOUGH NATIONAL WILDLIFE REFUGE

WATSONVILLE, CALIFORNIA

TECHNICAL REQUIREMENTS

PART 1.0 GENERAL

1.1 SCOPE

A. This document contains supplemental technical requirements to the Statement of Work for abatement, demolition, removal, disposal, and construction of U.S. Fish & Wildlife Service infrastructure projects in Regions 1, 7, & 8 (Oregon, Washington, Idaho, California, Nevada, Alaska, Hawaii & other Pacific Islands).

B. Provide all management, supervision, field-engineering, quality-control, labor, equipment, materials and supplies necessary to perform work described in the statement of work.

C. Conduct site visits, and working meetings, conference calls, and other activities as necessary to accomplish the work in a timely and efficient manner.

1.2 DEFINITIONS (for the purposes of this document)

A. Commissioning is the act of statically and dynamically testing the operation of equipment and facility systems to ensure they operate as designed and can satisfactorily meet the needs of the facility throughout the entire range of operating conditions.

B. Contracting Officer (CO) is defined as a the USFWS person with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings on behalf of the United States of America.

C. COR is the Contracting Officer’s Representative who is explicitly designated in writing by the CO.

D. Contractor is the business entity that is contractually-responsible to the USFWS for accomplishment of the project Work.

E. Government means Owner, Contracting Officer, Contracting Officer’s Representative, or U. S. Fish and Wildlife Service.

F. Performance Specifications are specifications that state what the required results will be with measurable or observable criteria for verifying compliance.

G. USFWS or FWS means United States Department of Interior, Fish and Wildlife Service.

1.3 PROJECT LOCATION AND ACCESS

A. Project location(s) is/are described in the project Statement of Work.

B. Some projects may be located in remote areas where construction materials and supplies are limited in quantity and variety, and where opportunities to use local labor may be limited in quantity and specialty. In the Pacific Islands, Hawaii, and Alaska access is primarily by ship or air.

C. Access:

1. The Contractor shall identify suitable access routes to the work site(s) that are agreeable to the USFWS refuge / hatchery project leader and the COR.

2. Identify and comply with any associated use requirements and restrictions.

Verify with Field Station if roads are in “Open” or “Closed” status prior to using.

3. Site access may be difficult in some instances.

D. Any roads, parking lots, trails, and walkways subject to interference by the work shall be kept open in a manner that provides for safe public use.

E. USFWS will occupy the premises during the progress of the work. Cooperate with USFWS to maintain access and availability to the site.

1.4 TECHNICAL PROCEDURES

A. General: Comply with the requirements contained in this document unless explicitly indicated otherwise in a project-specific Statement of Work.

B. Contractor is responsible for the proper performance of the Work and shall correct, at no additional expense, to the Government any errors or omissions in connection with such performance.

C. Land Ownership and Boundary Surveying: Any boundary survey work associated with USFWS projects is within the purview of the USFWS Regional Land Surveyor, who ultimately determines the type and extent of any necessary boundary surveying.

D. Hazardous Materials: Notify COR immediately of any potential hazardous materials discovered on-site.

1.5 SUBMITTALS

A. Obtain transmittal form FWS R1-67 and use for transmitting all submittals.

B. Follow the requirements of the “Region 1, 7, and 8 Engineering Drawings and Computer Aided Drafting Standards Manual”, dated January 2016 or the most recent edition, for the preparation and management of engineering drawings including As-Built drawings.

C. See 48 CFR 52.236-21 (d), (e), (f), (g), “Specifications and Drawings for Abatement, Demolition, and/or Construction”, for requirements of Shop Drawing submittals for (1) the proposed fabrication and assembly of structural elements and (2) the installation (i.e., form, fit, and attachment details) of materials or equipment.

D. Processing Time: Allow the government 14 calendar days for review of submittals.

Time shall commence upon the COR’s receipt of the submittal. Any re-submittal will require another 14 days of review time.

E. Except as indicated below, transmit project-specific submittals electronically in Adobe.pdf to the COR and/or the USFWS designated engineering point-of-contact.

1. Deliver any color renderings, samples, finish samples, and mock ups directly to the USFWS field station and COR. Provide two samples to COR and one to field station, unless separate agreement is made between COR and Contractor.

2. Submit cost proposals as Adobe.pdf and/or Excel.xls to the CO and/or COR as directed.

3. Individual sheets shall be combined into a .pdf file of 5MB maximum. Files too large for electronic or ftp distribution may be mailed or delivered on compact disk or external drives.

1.6 HOUSING AND TEMPORARY FACILITIES

A. Housing for workers and campsites are not available on site unless explicitly indicated otherwise in the Scope of Work.

B. The Contractor shall furnish all temporary facilities and utilities needed including: heat, light, power, water, telephone, sanitary facilities, job offices, material handling equipment, temporary construction aids, and storage enclosures. If suitable USFWS water, electric, or other utility is present at the site, it may be used for construction purposes at no cost, only if it does not adversely impact the operations of the station and field station agrees to permit use.

C. The Contractor is responsible for all temporary connections and disconnections.

PART 2.0 PROJECT EXECUTION

2.1 GENERAL

A. Project work will be accomplished via the project-specific Work Statement to convey the unique aspects of the project.

B. Federally listed illegal drugs are not permitted on the jobsite or any Federal property, regardless of State laws.

2.2 PRE-ABATEMENT AND PRE-DEMOLITION CONFERENCE

A. The Contracting Officer or designated COR will conduct a Pre-Abatement and Pre- Demolition Conference at a convenient time to both the Contractor and the Government.

A draft agenda with topics will be distributed prior to the meeting. The Contractor shall take meeting notes and submit for COR review and approval.

2.3 ABATEMENT AND DEMOLITION SCHEDULE

A. Contractor shall submit for approval an initial practicable graphic Abatement and Demolition schedule in PDF format within 15 days of NTP.

B. For projects under $250,000, the abatement, demolition, and construction schedule may be in Bar-Chart format or more detailed.

C. For projects over $250,000, the abatement, demolition, and construction schedule shall be in Critical Path Method, CPM format.

D. The schedule shall show any long-lead time items and any government-furnished property.

E. Submit updated abatement, demolition, and construction schedules monthly depicting progress of work completed to date.

2.4 PERMITS

A. In addition to the Permits and Responsibilities clause Federal Acquisition Regulation (FAR) 52.236-7, if work includes any ground disturbances meeting Storm water Pollution Prevention Plan (SWPPP) requirements, Contractor shall prepare, submit, and obtain any permits for SWPPP, unless SWPPP documentation is provided by the USFWS in the solicitation phase.

B. Contractor shall obtain all other necessary local, state, or federal permits prior to starting work.

2.5 DAILY REPORTS AND PROGRESS PHOTOS

A. Contractor shall prepare and submit to the COR a daily report for each day physical on-site work is accomplished. The report shall note days and durations of no-work on the project.

B. Contractor shall label and submit to the COR a minimum of two photographs for each day of work, which represents work accomplished for that day. Photos shall contain a date stamp representing the day of work.

2.6 SUSTAINABILITY

A. Products selected by the Contractor for incorporation into the work shall be environmentally friendly, energy efficient, renewable, or other sustainable improvements.

Submit manufacturer’s literature demonstrating sustainability.

2.7 COMPLIANCE DOCUMENTATION

A. The Contractor shall (during normal working hours throughout the duration of the contract) promptly furnish information, and provide reasonable facilities & access for obtaining information respecting: the character of the materials, condition of the work-in-progress, number of workers employed, their pay rate, time worked, inspection reports and test results from sampling and testing laboratories, and similar information.

PART 3.0 ABATEMENT AND DEMOLITION

3.1 GENERAL ABATEMENT AND DEMOLITION REQUIRMENTS

A. Contractor shall provide any necessary supervision, labor, materials, equipment, tools, testing, utilities, transportation, or other, which is necessary for proper execution and completion of the Work, regardless if it is temporary or permanent Work.

B. Security: Effectively secure the work site, staging areas, and materials storage areas.

C. Diligence: Perform all Abatement and Demolition activities efficiently and with the requisite expertise, skill, and competence to satisfy the requirements of the Contract Documents. Contractor shall at all times exercise complete and exclusive control over the means, methods, sequences, and techniques of abatement, demolition, and construction.

D. Supervision: Any time onsite work is underway, provide an onsite Project Manager or Project Superintendent who has a good working knowledge of the project work.

E. Subcontractors: Utilize general contractors and specialty subcontractors who are duly licensed and well qualified to perform the Work consistent with the Contract Documents;

Government may reasonably object to Contractor's proposed selection of workers and business entities.

F. Other Contractors: Coordinate and cooperate with any other contactors working at the project site.

G. USFWS Operations: Schedule and coordinate abatement, demolition, and construction activities so as not to unduly impact ongoing refuge / hatchery operations; USFWS operations have precedence over the construction activities.

3.2 ABATEMENT AND DEMOLITION SAFETY

A. The Contractor shall have the ultimate responsibility for health and safety on the project site at all times, as described in CFR FAR 52.236-13, “Accident Prevention”.

B. The Contractor is responsible for ensuring that all onsite activities, facilities constructed, and equipment conform fully to the standards of the Department of Labor, Occupational

Safety and Health Administration (OSHA) 29 CFR 1926 and 1910, and any supplemental DOI and USFWS policies.

C. Prepare, and submit for government review, a written permit space program for any identified OSHA 29 CFR 1926.1203 identified confined spaces. Also inform employees and post signage per 1926.1203(b)(1).

D. Comply with all applicable Federal, State and local safety requirements. In the event where any safety standard referenced herein conflicts with another, the more stringent shall govern.

E. Initiate and maintain, throughout the performance of this contract, an effective health and safety program that provides adequate policies, procedures, and practices to protect workers from (and allow them to recognize) job-related health and safety hazards.

1. The program shall include provisions for the identification, evaluation, prevention and control of general work site hazards, specific job hazards, and potential hazards that may arise from foreseeable construction methods and conditions, as well as providing a competent person to conduct frequent and regular inspections.

2. Each employee (Contractor or subcontractor) must be instructed in the recognition and avoidance of unsafe conditions and the regulations applicable to the work environment.

F. Provide barricades and warning devices as necessary to safeguard the public, workers, and government personnel. Where project work affects public roads, provide signage in accordance with the current edition of the Manual on Uniform Traffic Control Devices (MUTCD) as published by the US Department of Transportation, Federal Highway Administration.

G. Rollover Protection and Seat Belts: In addition to the Accident Prevention clause Federal

Acquisition Regulation (FAR) 52.236-13 , rollover protection and seat belts required by 29CFR 1926 (OSHA) shall be extended to include equipment regardless of the year of manufacturer.

3.3 ABATEMENT AND DEMOLITION QUALITY ASSURANCE AND QUALITY

CONTROL (QAQC)

A. Designate in writing a single person to oversee and manage on-site quality assurance and quality control activities.

B. The Contractor is responsible for quality assurance and quality control of all project work including any sub-contracted work, and to submit thorough documentation that work fully complies with the project documents and project permits.

C. Quality Assurance and Quality control processes include but are not limited to proactively:

1. Ensuring compliance with the abatement and demolition documents and project permits.

2. Make vertical work plumb and make horizontal work level.

3. Managing specialty subcontractors.

4. Reviewing and processing samples, mock ups, shop drawings and other abatement, demolition, removal, disposal, and construction submittals.

5. Ensuring that the workers have the appropriate expertise and proper equipment to perform the work.

6. Effectively utilizing third-party sampling & testing services (typically for earthwork gradation, compaction, concrete & asphalt testing, welding, pile driving, and other specialty inspections).

7. Initialing timely reviews and corrective actions to substrates prior to proceeding with subsequent work.

8. Timely involvement of industry specialists such as manufacturer representatives.

9. Managing system commissioning.

10. Conceal pipes, ducts, and wiring in finished areas unless otherwise indicated, and maintain headroom clearance of 96” in occupied spaces and 90” in unoccupied spaces.

11. Training USFWS personnel in system operation & maintenance.

12. Timely involvement of local authorities having jurisdiction.

13. Load-Limits: Heavy equipment operated on USFWS roads and parking areas shall comply with highway-legal load limits unless explicitly approved otherwise.

D. Field-verify all dimensions and conditions prior to performing the work. Notify the COR of any conflicts.

E. Improvements shall be constructed in accordance with the product manufacturer’s written instructions and standards.

F. Welding shall be performed by licensed welders and in compliance with American Welding Society recommended practices, structurally sound, and shall be neat in appearance.

G. Electrical work shall comply with the National Electrical Code, or State Code of more stringent, to the satisfaction of the local authority having jurisdiction. And shall be performed by state-licensed (by the state where the project is located) electricians who are licensed in the category of electrical being performed; photo-voltaic and telecommunications /data systems included.

H. Telecommunication (included telephone, data, radio, TV, similar) systems shall comply with the USFWS Regional 1, 7, and/or 8 Telecommunication standards, which will be provided upon request.

3.4 NOXIOUS WEED / SPECIES / PATHOGEN CONTROL

A. Wash any equipment (and transport trucks) at an approved site prior to entering the project area. This is particularly important when transporting material or equipment from relatively distant areas.

B. Ensure and submit documentation that any straw bales and seed mixes are certified “weed-free”; and if feasible, are from the local area; submit documentation.

C. Any floating silt screens or similar construction aids shall be brand new (unused) or have been newly washed and disinfected; submit documentation.

D. Comply with any other specific protocol required by the station to minimize potential introduction of invasive species such as rodents or plants that could be transported by equipment, materials, personnel or food products.

3.5 ENVIRONMENTAL PROTECTION

A. General: Comply with all applicable federal, state, and local environmental laws and regulations. This condition applies to, but is not limited to, laws and regulations governing noise levels, air and water quality standards, erosion control, surface runoff, and cultural resources.

B. Cultural Resources: Immediately stop work if paleontological, archaeological or historical remains (including burials or skeletal material) are encountered, until work is permitted to resume by written order from the Contracting Officer. Notify the Inspector, COR, or Contracting Officer immediately. The Contracting Officer will notify the Regional Archaeologist so the provisions of 36 CFR 800.7 (Resources Discovered During Construction) and other relevant laws are followed. Work in other areas may proceed as approved by the Contracting Officer.

C. Temporary Erosion and Sedimentation Control: Provide effective erosion control measures to prevent soil erosion and discharge of soil-bearing water runoff at the earliest feasible stage of construction. Regularly inspect and maintain the measures in effective working order. Promptly stop work in area(s) of any ineffective erosion control measures. Follow SWPPP if part of contract.

D. Tree and Plant Protection: Install temporary fencing located outside the drip line of trees to protect from damage from construction operations. Protect the tree root systems from damage, flooding, and erosion.

E. Vegetable-Based Hydraulics: Unless explicitly approved otherwise, dedicated onsite equipment operating near or over water bodies (or sensitive habitat) shall be equipped with vegetable-base hydraulic fluids. Consider alternates such as propane, electric, or air pneumatics.

F. Dust: Utilize effective means to prevent generation of wind borne dust (typically watering or application of other approved dust control measures) and to prevent sediment from leaving the work site and/or entering storm sewers and water bodies. Method must be approved by the COR.

G. Damage: Protect adjacent vegetation, property, structures, and improvements from damage.

H. Hazardous Materials: Perform any hazardous materials work in strict accordance with governing hazardous materials regulations. Workers shall be knowledgeable and well trained in the handling of project-specific hazardous materials.

I. Spill Control: Provide effective spill containment measures at the earliest feasible stage of construction. Regularly inspect and maintain the measures in effective working order.

3.6 WORK LIMITS & CLEARING LIMITS

A. Work Limits: Unless approved otherwise, confine all construction equipment and disturbance with the work limits that typically include out-to-out top edge of access roads, parking areas, and staging areas.

B. Clearing Limits: Unless approved otherwise, remove all trees, shrubs, and similar vegetative matter and deleterious material within 10 feet beyond the footprint of the Work; and as shown on the drawings.

3.7 CLEANUP

A. In addition to the Clean Up clause Federal Acquisition Regulation (FAR) 52.236-12, on a Daily basis, keep the work site and staging areas reasonably free from trash and construction waste/debris. Legally dispose waste materials from Government’s property.

Recycle if applicable.

B. Upon Substantial Completion of the Work, promptly remove any debris, materials, equipment, and tools, temporary facilities; and restore any areas disturbed by the Work to their preconstruction condition.

3.8 MATERIAL & EQUIPMENT TRANSPORTATION, HANDLING, AND STORAGE

A. Contactor shall have a representative on site to receive material deliveries, and the contractor shall remain responsible for all material deliveries whether or not their representative is on site at the time of delivery or not.

B. Government-owned equipment is not available for Contractor’s use to accomplish any Work, and Government buildings and other facilities are not available for storage of Contractor’s materials, equipment, and tools.

C. Transport, handle, and store materials and equipment in accordance with the manufacturer’s written instructions, and in a secure manner.

D. Store products that are subject to damage by the elements, under cover in a weathertight enclosure above ground, with ventilation adequate to prevent condensation. Protect liquids from freezing.

E. Promptly remove from the project site any materials or equipment that are damaged or are otherwise unsuitable.

3.9 TESTING

A. Third-Party Sampling & Testing: On projects that entail third-party sampling and testing, the Contractor shall provide and pay for the services of an accredited independent construction materials testing laboratory meeting the minimum requirements of ASTM E239-11c.

B. When work involves any of the below items, provide third-party Testing Lab Services:

1. Soils classification, gradation, and/or compaction.

2. Concrete strength, air-content, slump, and similar

3. Structural welds

4. Asphalt

5. Pile-driving

6. Other, as noted in other sections.

3.10 COMMISSIONING & TRAINING

A. Provide industry-certified Commissioning Specialist(s) (preferably firms recommended by the systems manufacturers) to oversee and/or perform system commissioning; to include start-up, adjustment, balancing, measurement and documentation that systems function within the manufacturer’s and designer’s prescribed operating parameters.

B. Include the commissioning documentation in (and submit) the Operation & Maintenance Manuals.

C. Training: After the systems are fully functional and are operating properly, thoroughly familiarize the local USFWS staff with the improvements and train them to be proficient in overall system operation and maintenance.

D. Tools and Spare Parts: Deliver to the project site all specialty tools, valve handles, fan belts, filters, spare parts, keys and similar devices such that the USFWS staff is able to operate and maintain the work.

3.11 FINAL WALK THOUGH

A. Submit a preliminary list of unfinished work and notify the COR at least ten (10) calendar days prior to the anticipated date of completion of all work.

B. The COR will perform final walk through as promptly as practicable.

C. The time required for such walk through and for making any corrections as a result thereof shall be included in the contract performance time.

D. The Contractor representative responsible for the work shall be present at the final walk through and shall submit a preliminary list of unfinished work.

3.12 AS-BUILT PERFORMED RECORD DRAWINGS (see also Closeout Documents)

A. Maintain one set of working drawings and specifications for record purposes, on the project site while work is in progress.

B. Clearly and accurately record the as-performed work in red; include modifications and clarifications.

C. Record swing-tie distances from permanent points to any underground items.

3.13 CLOSEOUT DOCUMENTS

A. Operation and Maintenance Manuals:

1. Submit 3 copies of Operation and Maintenance manual (two paper copies to the USFWS field station and one electronic Adobe.pdf to the USFWS Regional Office Engineering).

2. Include complete parts lists keyed to suppliers; name, address, websites, email and telephone numbers for each.

3. Include fully executed manufacturer’s standard material, product, and equipment warranties.

4. Include systems commissioning documentation in (and submit) the Operation & Maintenance Manuals.

B. Submit any requested regulatory-agency clearance documents indicating the work complies with their requirements such as finalized plumbing/gas/electrical inspections.

C. After completion of the work and prior to final payment, submit a properly executed by the Contractor Release of Claims, Form DI-137, releasing claims against the United States arising out of this contract, other than claims specifically excepted from the operation of the release.

D. Record Drawings:

1. Submit a full size paper-copy set of red-lined drawings and complete set of specifications that clearly indicates the as-performed work.

2. Scan the full size paper-copy set of red-lined drawings and submit a .pdf to the

COR.

END

File details come from the government source that posted it. Updated .