6-NS27-101 Shelter for the Homeless- GEK Shower Resurfacing QA.pdf
PDF 49 KB Posted
- Attached to
- Shelter for the Homeless- GEK Shower Resurfacing
- Solicitation number
- NS27-101
- Issued by
- Salt Lake County, Salt Lake City, Utah
About this file
This file is a Questions and Answers document for the Shelter for the Homeless located in Utah regarding a shower resurfacing project at the Geraldine E. King Resource Center. The project involves the application of epoxy coating to shower walls and benches at the facility, which contains 22 showers in the common area and 3 showers in private restrooms. The epoxy will cover only the shower area walls, not entire rooms or ceilings. A mandatory pre-bid conference is scheduled for September 9, 2026 at 1:00 PM at the resource center located at 131 East 700 South, Salt Lake City. Written questions must be submitted through the U3P portal no later than September 14, 2026 at 5:00 PM, and bid submissions will be accepted through the same portal until September 21, 2026 at 5:00 PM. The project must be completed by the end of October 2026.
The work will be classified as "painting" under Davis Bacon prevailing wage requirements, and plumbing services are not required if epoxy installation can proceed without removing fixtures. This specification clarifies that contractors should anticipate Davis Bacon wage rates applicable to painting operations. The Issuing Office for bidding documents is the Shelter for the Homeless, and interested vendors should note that while this posting serves as an advertisement through the Division of Purchasing, the actual procurement is conducted by the shelter organization, and contract awards will not be posted on the Division of Purchasing website but will be announced directly by the shelter.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-STH GEK Showers RFB FINAL 8.24.26.docx | DOCX document | |
| 5-STH GEK Showers RFB Amend1 9.2.26.docx | DOCX document | |
| 4-Shelter the Homeless GEK Wage Determination-Building 8-21-2026.pdf | ||
| 3-STH GEK Floor Plans 2.pdf | ||
| 2-PY25 Pre-Bid Oriention Compliance.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NS27-101 Shelter for the Homeless- GEK Shower Resurfacing Q&A
Q: Will the epoxy cover the ceiling of the showers or just the walls?
A: The epoxy should cover just the walls and shower benches.
Q:Will the epoxy cover the entire room for the private restrooms or only the shower area?
A: Only the shower area walls should be covered with epoxy.
Q: How many showers are there?
A: 22 in the common area and 3 private restroom showers.
Q: Will this be labeled as “painting” for rates under Davis Bacon?
A: Yes
Q: Will a plumbing be required under Davis Bacon?
A: If epoxy can be installed without removing fixtures, a plumber is not required.
Q: What’s the timeline?
A: The project should be completed by the end of October.