This document is a 2026 Public Right-of-Way Bureau Specification and Detail summary prepared by the City of Lancaster, Pennsylvania, outlining revisions to curb and sidewalk specifications and street details for municipal construction projects. The specification updates address multiple infrastructure elements including standard sidewalk width increases from 48 inches to 60 inches, revised drainage requirements for downspout disconnection via trench drain or pipe through the curb during sidewalk replacement, clarification on expansion requirements around utilities, and modifications to driveway apron detectable warning surface requirements. Street detail revisions include the addition of standard utility trench repair details, base repair cross sections with 1-foot cutback specifications, and updated pavement marking details requiring thermoplastic materials. The document also introduces new sections addressing tree root trimming guidance, obstruction management requiring additional sidewalk width, and monument box detail relocation for clarity.
The specification revisions reflect current municipal engineering practices and regulatory compliance standards. Notable changes include the removal of deicing chemical usage requirements, eliminating the need for replaceable detectable warning surfaces on driveway aprons, revised downspout drain detail showing pipe placement below sidewalk rather than concrete encasement, and discretionary pavement compaction testing requirements at the Bureau of Engineering's determination. These specifications establish uniform standards for municipal curb, sidewalk, and street construction projects undertaken by the City of Lancaster, Pennsylvania, ensuring consistency and compliance across public right-of-way improvements.
View the file
Other files
Show 40 more
Latest 50 of 61 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2026 Public Right-of-Way Bureau Specification and Detail, Summary of Changes
(for information purposes only, not inclusive of all revisions)
• Curb and Sidewalk Specifications o Standard sidewalk width was revised from 48in to 60in throughout the document.
o Revised section 7, Drainage, to require downspout disconnection via trench drain or pipe thru the curb whenever sidewalk is replaced from the right-of-way line to the curb.
o Provided clarification on expansion around utilities, expansion will no longer be required on smaller utilities: water valves/sewer vent stacks/etc. Note that expansion is still required around utility poles, hydrants, etc.
o Specifications revised to recommend that deicing chemicals not be used, City is no longer making this a requirement.
o Section 36, Obstructions, was revised to require additional sidewalk around obstructions such as utility poles that would narrow the existing sidewalk below minimum allowable widths. A detail was added to clarify this intent.
o Section 37, Driveway Aprons, Detectable Warning Surfaces (truncated dome mats) are no longer required to be replaceable.
o Section 48, Trimming of Tree Roots, was added to provide guidance on when tree roots may be trimmed as a result of curb and sidewalk work.
• Curb and Sidewalk Details o Detail 5, Sheet 1 was added to show a sidewalk addition as a result of an obstruction in the sidewalk.
o Monument box detail was moved to Sheet 3 for clarity.
o Detail 10, Sheet 2, Sidewalk Downspout Drain was revised to show the pipe below the sidewalk, the previous detail showed encasement of the pipe in concrete.
o Detail 2, Sheet 3 was revised to remove requirement that DWS mats be replaceable.
• Street Details o Detail 1, Sheet 1 was added to show a standard utility trench repair o Detail 2, Sheet 1 was added to show the base repair cross section, specifically including the standard 1ft cutback.
o Note 6, Sheet 1 was revised to include that pavement compaction testing will be required at the discretion of the Bureau of Engineering.
o Pavement marking details on Sheet 2 were updated to be consistent with current practices.
o Note 1, Sheet 2 was revised to require that all markings be made of thermoplastic.
o Details for ‘Type 1’ and ‘Type 2’ crosswalks were removed from Sheet 2. Detail 1 was revised to create a uniform crosswalk style.