6-Attachment B Construction Scope of Work - ADA Compliant (Revision 1).pdf

PDF 124 KB Posted

Attached to
JH27-113 Turpin and Dour Miller Water Control Structures for Farmingtion Bay WMA
Solicitation number
JH27-113
Issued by
Davis County, Utah

About this file

This is a Construction Scope of Work document prepared by the State of Utah Division of Wildlife Resources for the Turpin and Dour Miller Water Control Structures project at Farmington Bay Waterfowl Management Area. The project requires the provision of one new water control structure and the installation of an existing water control structure at the Farmington Bay WMA located at 1325 W. Glover Lane, Farmington, Utah. A mandatory site visit is scheduled for September 24, 2026, at 10:00 AM, with an anticipated duration of one to three hours. The contract term is up to three months, and the contract will be awarded to the lowest cost responsive and responsible vendor. Vendors must guarantee their pricing for project completion.

The scope of work document outlines the construction specifications and technical requirements for both water control structures. Pricing terms require vendors to submit fixed prices that remain guaranteed throughout the contract period. The project is being procured through an Invitation for Bid (IFB) process conducted by the State of Utah Division of Purchasing and the Division of Wildlife Resources, with the expectation of a single contract award. All interested bidders are required to attend the mandatory site visit to familiarize themselves with project conditions and site-specific requirements before submitting proposals.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION SCOPE OF WORK

Miller & Turpin Units Improvements

Scope of Work and Contractor Responsibilities The selected Construction Contractor shall provide all necessary equipment, labor, personnel, and specified materials required to properly and successfully complete all work elements described and/or implied in the construction plan set, technical specifications, and any other documents included in the official bid package. All work shall be performed in accordance with best management practices and established industry standards, ensuring high-quality workmanship throughout the project.

The Contractor shall comply fully with all technical and administrative requirements outlined in the bid documents and associated materials.

The Scope of Work shall include, but is not limited to, the following components:

1. Mobilization

Mobilization shall include the legal and orderly transportation of all required equipment, materials, and personnel to and from the project site. This includes the provision of all resources, necessary transport-related permits to move equipment, materials, or personnel to start and carry out the construction activities as specified in the construction plans, details, and project documents. Mobilization also includes the legal and correct demobilization of equipment, materials, and personnel at the completion of the project.

2. Site Preparation

Site preparation shall consist of all tasks necessary to prepare the project area for construction activities. This may include, but is not limited to:

• Clearing and Grubbing: Clearing and grubbing in accordance with the construction plans, notes, or documents.

• Temporary Access: Temporary access road construction.

• Grading: Grading and contouring as needed to support the required scope of work.

• Demolition: Demolition and removal of existing man-made structures or materials found on site.

• Dewatering and Remediation: Dewatering and soil remediation, as required to support construction activities.

3. Construction Activities

Construction shall include, but is not limited to, the following work elements:

• Water Control Structures: Installation of precast concrete water control structures and associated piping.

• Erosion Control: Implementation of erosion control measures.

• Earthwork: Execution of required earthwork, including the placement of compacted fill, grading, and backfilling in accordance with the construction plans, notes, or documents.

• Project Completion: Completion of all additional tasks and components necessary to fulfill the project requirements as outlined in the approved plans, technical details, and specifications.

CONSTRUCTION SCOPE OF WORK
Scope of Work and Contractor Responsibilities
1. Mobilization
2. Site Preparation
3. Construction Activities

File details come from the government source that posted it. Updated .