This is a plumbing construction bid form for College Township's renovation of its Municipal Building located in Centre County, Pennsylvania. The project encompasses plumbing work including fixture demolition and installation of new sinks, urinals, and toilets, with coordination required among the general contractor, mechanical contractor, and electrical contractor. Sealed bids will be received through PennBid until November 11, 2026 at 2:00 PM, with a non-mandatory pre-bid conference and site tour scheduled for October 28, 2026 at 11:00 AM at the Municipal Building. Bid documents will be available for download beginning October 12, 2026 at 9:00 AM, and all requests for information must be submitted by October 30, 2026 at 5:00 PM. Township Council will review bids and may award the contract at its meeting on December 3, 2026 at 7:00 PM, with all bidders notified of results on or after November 16, 2026. The base bid is valid for 90 days, and an alternate for renovating second-floor restrooms is available. Upon notice of intent to award, the successful bidder must submit required payment and performance bonds, along with insurance certificates within 10 days.
The contract requires submission of a construction schedule within 10 business days of award and execution of a formal contract agreement within 15 days. A bid bond with corporate surety approved by the Township Solicitor in an amount equal to 10 percent of the bid price is required with each submission. The successful bidder must provide a performance bond equal to at least 100 percent of the total contract price within 10 calendar days of written notice of acceptance. The contractor must begin work immediately upon receipt of notice to proceed and complete all work within the timeframe specified in the contract documents. Township Council reserves the right to reject any or all bids and to accept any portion of any bid submitted.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2-00 53 10 NON COLLUSION.docx | DOCX document | |
| 12-2026-10-12 College Twp Bid Set Specs Vol 2.pdf | ||
| 4-00 41 01 GC bid.doc | DOC document | |
| 7-00 53 20 Waiver of Liens.doc | DOC document | |
| 10-00 30 04 - Mechanical Construction (MC) Bid Breakdown Form.xlsx | XLSX spreadsheet | |
| 9-00 30 06 - Electrical Construction (EC) Bid Breakdown Form.xlsx | XLSX spreadsheet | |
| 8-00 30 08 - Plumbing Construction (PC) Bid Breakdown Form.xlsx | XLSX spreadsheet | |
| 3-00 41 00 bid doc checklist.doc | DOC document | |
| 1-00 41 02 MC bid.doc | DOC document | |
| 13-2026-10-12 College Twp Bid Set.pdf | ||
| 11-00 30 02 - General Construction (GC) Bid Breakdown Form.xlsx | XLSX spreadsheet | |
| 5-00 41 03 EC bid.doc | DOC document | |
| 14-2026-10-12 College Twp Bid Set Specs Vol 1.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Kimmel Architecture
College Township
Renovations to the Municipal Building
SECTION 00 41 04 - FORM FOR BIDCONTRACT #4 - PLUMBING CONSTRUCTION
A. The undersigned, having carefully examined the premises and the Drawings and Project Manual, and having fully informed himself as to all laws, ordinances, and regulations affecting the work, will furnish all labor and materials and perform all work required for the construction of:
College Township
Renovations to the Municipal Building
Centre County, PA
In accordance with the Drawings and Specifications prepared by Kimmel Architecture & CJL Engineering. for the Contract Price specified below, subject to additions and deductions according to the terms of the Project Manual.
B. This bid includes addenda numbered (if none, so state).
C. The proposed Contract Price (Base Bid) is________________________________________dollars.
Base bid valid for 90 days and as per the Bid Advertisement.
D. The proposed price for the following Alternates:
Alternate #P1 – RENOVATE SECOND FLOOR RESTROOMS
This is an add alternate to renovate the second-floor restrooms. This work for the Plumbing Contractor includes the following. Demolition of existing plumbing fixtures and installation of new sinks, urinals and toilets. PC shall coordinate related work with the GC, MC & EC. Work is shown in further detail on the drawings.
Alternate #P1: ADD __________________________________________ dollars
E. Unit Prices:
a. None F. Upon opening of bids, the apparent low bidder will be notified by the Owner of the intent of the Owner to award the Contract to the low bidder. If the undersigned is notified of such intent, he agrees to submit the required payment and performance bonds in satisfactory form. The undersigned agrees to provide the necessary insurance certificate within 10 days of notice of intent to award the Contract.
G. The undersigned agrees, if awarded the Contract, to begin work immediately upon receipt of the notice to proceed. Notice will not be issued to the Contractor until after the Contractor has delivered the necessary certificate of insurance to the Owner. The Contractor agrees to complete the entire work to the satisfaction and approval of the Owner and Architect within the contracted time frame as described in Section 00 52 30 – Time to Complete.
H. If the Owner accepts this proposal, the undersigned agrees to submit, within ten (10) business days, a Construction Schedule as specified in Section 01 32 00 of these construction documents.
I. The undersigned agrees, that if he is selected as a Contractor, he will within 15 days, Saturdays, Sundays and Legal Holidays excluded, after presentation thereof by the Owner, execute a contract in accordance with terms of this bid.
J. The Contractor in charge of the General Construction of this project shall have direct control and management of all the construction operations and shall be responsible for the satisfactory overall performance of all his suppliers and subcontractors, as well as coordination of work performed.
K. The undersigned hereby certifies that he is able to furnish labor that can work in harmony with all other elements of labor employed or to be employed on the work.
L. In the event that changes are required in the work, including increases or decreases in the amount of items shown in the contract drawings, that adjustment shall be made according to Article 12 of the General Conditions of the Contract for Construction.
M. The undersigned agrees that time is of the essence in this Contract and that great energy and diligence shall characterize all operations carried out under this Contract.
By: __________________________________________ Date: ________________________________
(Signature)
(Name and Title)
(Name of Organization)
(Business Address)
(Corporate Seal)
Note: If the bidder is a corporation, indicate State of incorporation under signature and affix corporate seal; if a partnership, give full names and residential addresses of all partners; and if an individual, give residential address if different from business address.
END OF SECTION 00 41 04