These technical drawings are part of a Department of Veterans Affairs (VA) infrastructure improvement project for the Dayton VAMC (Medical Center), specifically Project 552-19-102 for Correcting Infrastructure Deficiencies in Building 408. The drawings include detailed mechanical, fire suppression, and plumbing system plans across multiple floors, showing new work for sanitary waste and vent systems, fire suppression sprinkler installations, and HVAC system modifications. The documents are prepared by Heapy Engineering and Guidon Design Inc., with a project number 2018-05164, and are dated April 2025.
The technical drawings provide comprehensive diagrams for basement, first floor, second floor, and attic levels, detailing specific infrastructure updates including sanitary waste systems with drain symbols, sewage ejector specifications, trap primers, fire suppression sprinkler layouts, and HVAC system removals and installations. The drawings include precise technical annotations, equipment schedules, piping and ductwork symbols, and general notes outlining installation requirements, coordination protocols, and compliance standards for the renovation project at the VA medical facility.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FD1
FD1
FD1
SE1
2"
2"
2"
3"
3"
3"
4"
4"
SAN
SAN
SAN
SAN
SAN
S A
N
VV
1.5"
2"
FIRST FLOOR
SECOND FLOOR
ATTIC
3" VTR
3"
2"
2"
2"
V V
CO
CO
CO
CO
2"
FLOOR
2"
1.5" VENT
2"
PDCO
1 BASIN (36" DIA x 60" HEIGHT)
2 ANTI-FLOTATION FLANGE
3 BASIN LID - BOLTED & GASKETED.
4 6" SAND BED. LEVEL BASIN.
5 INLET PIPE. SEE FLOOR PLAN FOR NUMBER
AND INVERT(S).
6 DUPLEX CONTROL PANEL. MOUNT 60" AFF TO
TOP OF PANEL.
7 CONNECT TO TOP OF GRAVITY DRAINAGE PIPE.
8 INSTALL PIPE ACCESSORIES IN HORIZONTAL
PORTION OF PIPING.
9 POWER WIRING IN CONDUIT TO CONTROL
PANEL.
10 PUMP
CAPACITY: 15 GPM @ 15 FT. HD.
ELECTRICAL: 230V/ 1PH/ 60 HZ/ 1/2HP
11 CONCRETE FILL. 25 CU FT. MINIMUM EVENLY
DISTRIBUTED AROUND BASIN.
12 PUMP REMOVAL RAIL SYSTEM.
CONTROL INVERTS (BELOW FINISHED FLOOR)
PUMPS OFF 54 IN
LEAD PUMP ON 44 IN
LAG PUMP ON 40 IN
HIGH LEVEL ALARM 36 IN
P D
P D
NOTESV
3"
TRAP PRIMER, WITH DISTRIBUTION
UNIT WHEN SERVING MULTIPLE
DRAINS. LOCATE ABOVE CEILING
IN FINISHED AREAS.
0.5''SUPPLY SHALL BE
OFF TOP OF MAIN
COLD WATER MAIN
T P
T P
WALL
FINISHED CEILING
WHERE APPLICABLE
FLOOR DRAINS
FLOOR
TP
PIPING TO FLOOR DRAINS
SHALL BE RUN BELOW FLOOR,
UNLESS NOTED OTHERWISE.
INSTALL PIPING CONCEALED
IN WALL IN FINISHED AREAS.
INSTALL PIPING TIGHT TO WALL
SURFACE IN UNFINISHED AREAS.
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC.
905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
PROJECT NO. STATE COA FIRM NO.2018-05164 01528
/2
/2
:4
:2
P
M
P501
DETAILS AND SCHEDULES CORRECT
INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OHIO 45428
552-19-102
PHIL WEST, COR
May 2nd, 2025 EWL KMB
BID DOCUMENTS
FULLY SPRINKLERED
DRAIN SCHEDULE
SYMBOL DESCRIPTION
BODY STRAINER / GRATE TOP FINISH
C.I. S.S. C.R. BRASS RD. SQ. ADJUST. FLAT RECESS DOME
NICKLE
BRONZE C.I. C.R. S.S.
FD1 3" MEDIUM DUTY/ DOUBLE DRAINAGE/ VANDAL RESISTANT (TYPE C)/ TRAP PRIMER
CONNECTION
GENERAL NOTES:
A. PROVIDE ROUGH-IN.
B. INSTALL ALL "LOOSE" COMPONENTS.
C. PROVIDE ALL NECESSARY SUPPLIES, STOPS, TRAPS,
FIX. DRAINS, CONTINUOUS WASTE, & ALL INDIRECT WASTE.
D. MAKE ALL FINAL CONNECTIONS.
E. THE P.C. SHALL CONFIRM ALL PIPING CONNECTIONS &
SIZES BEFORE ROUGH-IN.
EQUIPMENT SCHEDULE
MARK DESCRIPTION
SUPPLY WASTE & VENT WASTE SYSTEM
REFER TO
EQUIPMENT
SCHEDULE
NOTES C
O
L D
W A
T E
R
H O
T W
A T
E R
R O
D
I W
A T
E R
T E
M P
E R
E D
W A
T E
R
L A
B A
IR
F
IX
T U
R E
O U
T L
E T
T R
A P
F
IX
T U
R E
D R
A
IN
W A
S T
E -M
IN
IM
U M
V E
N T
-M
IN
IM
U
M
I N
D
IR
E C
T
A
IR
G A
P
A
IR
B R
E A
K
T O
F L
O O
R D
R A
IN
T O
S T
A N
D P
IP
E
S A
N
IT
A R
Y
K
IT
C H
E N
W A
S T
E
A C
ID
W
A S
T E
SE1 DUPLEX SEWAGE EJECTOR/ 230V 1PH 60 HZ/ 1/2HP/ 15GPM
@ 15 FT HD
2" ●
NOT TO SCALEP501
A SANITARY WASTE & VENT DIAGRAM
PIPE SPACE
NOT TO SCALEP501
B SEWAGE EJECTOR (SE1)
REFER TO DETAIL "B" / THIS
SHEET FOR CONTINUATION
NOT TO SCALEP501
C TRAP PRIMER
Revisions: Date:
A1
P1 P1OR
A1
OH
P2
B
P2
GENERAL FLOOR PLAN NOTES
RISER OR STACK NUMBER
DETAIL: B = DETAIL DESIGNATION
P2 = SHEET WHERE DETAIL IS LOCATED
FIRE SUPPRESSION HAZARD CLASSIFICATION AND HAZARD
CLASSIFICATION GROUP
SECTION: 1 = SECTION DESIGNATION
P2 = SHEET WHERE DETAIL IS LOCATED
EQUIPMENT REFERENCE. LETTER DESIGNATION VARIES.
REFER TO SCHEDULES.
EQUIPMENT, DEVICE, OR PLUMBING FIXTURE MARK. LETTER
DESIGNATIONS REFER TO SCHEDULES.
CONNECT TO EXISTING
PLAN NOTE. APPLIES ONLY TO THE SHEET WHICH IT IS SHOWN
UNLESS NOTED OTHERWISE.
DETAIL NOTE. APPLIES ONLY TO THE ASSOCIATED DETAIL.
"UP TO" SYMBOL (ITEM ON FLOOR ABOVE)
10" 10"
ELEV: 8' - 0"ELEV: 8' - 0"
TOE: 3' - 0"
BOE: 0' - 6"
APPROXIMATE DIMENSION ABOVE FINISHED FLOOR TO TOP OR
BOTTOM OF EQUIPMENT, UNLESS NOTED OTHERWISE
APPROXIMATE DIMENSION ABOVE FINISHED FLOOR TO
CENTERLINE OF PIPE, UNLESS NOTED OTHERWISE
FIRE SUPPRESSION SYMBOLS
DOUBLE LINE SINGLE LINE
CONCEALED PENDENT SPRINKLER
FS
PIV
S
FIRE HYDRANT
FLOW SWITCH
GATE VALVE OS&Y
INSTITUTIONAL PENDENT SPRINKLER
PENDENT SPRINKLER
POST INDICATOR VALVE
RECESSED PENDENT SPRINKLER
SIDE WALL SPRINKLER
SUPERVISED VALVE
UPRIGHT SPRINKLER
PIPING SYMBOLS
DOUBLE LINE SINGLE LINE
BOTTOM CONNECTION (45°)
BRANCH TEE CONNECTION (NOTE:
BULLHEAD TEE'S ARE NOT
PERMITTED)
DIRECTION OF PITCH
DROP
ELBOW DOWN
ELBOW UP
EXISTING PIPE TO BE REMOVED
EXISTING PIPE TO REMAIN
FLOW DIRECTION DESIGNATION
PUMP
RISE
TOP CONNECTION (45°)
TOP CONNECTION (90°)
BOTTOM CONNECTION (90°)
DD
RR
SPECIALTY GAS SYMBOLS
AIR OUTLET - LAB TYPE
VC
VC
CARBON DIOXIDE OUTLET - HOSPITAL TYPE
MEDICAL AIR OUTLET - HOSPITAL TYPE
MEDICAL VACUUM INLET - HOSPITAL TYPE
NITROGEN OUTLET - HOSPITAL TYPE
NITROUS OXIDE OUTLET - HOSPITAL TYPE
OXYGEN OUTLET - HOSPITAL TYPE
WAGD INLET - HOSPITAL TYPE
NATURAL GAS OUTLET - LAB TYPE
VACUUM OUTLET - LAB TYPE
VACUUM CLEANING STATION - WALL
VACUUM CLEANING STATION - FLOOR
PLUMBING AND FIRE SUPPRESSION
PIPING DESIGNATIONS
DOMESTIC COLD WATER
DOMESTIC HOT WATER
DOMESTIC HOT WATER RETURN
EXISTING PIPE TO REMAIN
EXISTING PIPE TO BE REMOVED
HOT WATER PIPE (140 DEGS. F.)
HOT WATER PIPE (180 DEGS. F.)
HOT WATER RETURN PIPE (140 DEGS. F.)
HOT WATER RETURN PIPE (180 DEGS. F.)
ARGON PIPE
COMPRESSED AIR PIPE
MEDICAL CARBON DIOXIDE PIPE
COMBINATION FIRE SUPPRESSION AND DOMESTIC
WATER SERVICE
DIESEL FUEL PIPE
SPRINKLER PIPE (DRY)
FIRE SUPPRESSION (STANDPIPE / SPRINKLER MAIN)
FIRE SERVICE
FUEL OIL FLOW LINE
FUEL OIL GAUGE LINE
FUEL OIL RETURN LINE
FUEL OIL SUPPLY LINE
NATURAL GAS PIPE
GARAGE DRAINAGE PIPE
GAS SERVICE
HYDROGEN PIPE
HELIUM PIPE
MEDICAL INSTRUMENT AIR PIPE
KITCHEN WASTE PIPE
LABORATORY COMPRESSED AIR PIPE
LABORATORY VENT PIPE
LABORATORY VACUUM PIPE
LABORATORY WASTE PIPE
MEDICAL NITROGEN PIPE
MEDICAL COMPRESSED AIR PIPE
MEDICAL-SURGICAL VACUUM PIPE
GASOLINE PIPE (NON-LEAD)
MEDICAL NITROUS OXIDE PIPE
NON-POTABLE
MEDICAL OXYGEN PIPE
(OVERFLOW) SECONDARY STORM DRAINAGE PIPE
PROPANE GAS PIPE
PUMP DISCHARGE PIPE
PRE-ACTION / DELUGE SPRINKLER PIPE
PURE WATER PIPE
SPRINKLER PIPE (WET)
SANITARY DRAINAGE PIPE
SOFT COLD WATER
SPRINKLER DRAIN PIPE
STORM DRAINAGE PIPE
FUEL TANK VENT PIPE
TRAP PRIMER DISCHARGE PIPE
TEMPERED WATER PIPE
SANITARY SEWER VENT
WASTE ANESTHESIA GAS DISPOSAL PIPE
WATER SERVICE
LV
140R
180R
AR
CA
CO2
CWS
DF
DS
F
FS
FOF
FOG
FOR
FOS
G
GD
GS
H2
HE
IA
IV
IW
LA
LV
LW
N2
MA
MV
NG
NO
NPW
O2
OD
P
PD
PS
PW
S
SAN
SCW
SD
STM
T
TP
TW
V
WAGD
WS
INDIRECT VENT PIPE
INDIRECT WASTE PIPE
K
CHECK VALVE
T
P
FOB
FOT
SHUTOFF VALVE (REFER TO SPECIFICATIONS
FOR REQUIRED TYPE BASED ON
APPLICATIONS)
CONCENTRIC PIPE REDUCER
ECCENTRIC PIPE REDUCER
PRESSURE GAUGE
TEMPERATURE GAUGE OR THERMOMETER
UNION
CLEANOUT
STRAINER
STRAINER WITH A BLOW DOWN VALVE AND
HOSE CONNECTION
DRAIN VALVE WITH HOSE END CONNECTION
AUTOMATIC FLOW CONTROLLER WITH P/T
PLUG IN AND OUT
EXPANSION JOINT
PRESSURE REGULATING VALVE
SAFETY RELIEF VALVE. PIPE DISCHARGE AIR
GAPPED TO FLOOR DRAIN UNLESS NOTED
OTHERWISE.
PRESSURE AND TEMPERATURE TEST PLUG
TRAP PRIMER
VACUUM GAUGE WITH STOP
CLEANOUT TO GRADE OR FINISHED FLOOR
END CAP
MIXING FAUCET
PLUG
HOSE BIB
WALL HYDRANT
PLUG VALVE
SHUTOFF VALVE AND BOX
SHUTOFF VALVE ON RISER
V
VB
TP
CO
COMBINATION SHUTOFF AND BALANCING
VALVE (REFER TO SPECIFICATIONS FOR
REQUIRED TYPE BASED ON APPLICATIONS)
BALL VALVE
BUTTERFLY VALVE
GATE VALVE
VALVES AND FITTINGS
DOUBLE LINE SINGLE LINE
SOLENOID VALVE
S
P/T PRESSURE AND TEMPERATURE SAFETY
RELIEF VALVE. PIPE DISCHARGE AIR GAPPED
TO FLOOR DRAIN UNLESS NOTED
OTHERWISE.
FIRE DEPARTMENT VALVE
WATER METERM
ACID VENT PIPEAV
ACID WASTE PIPEAW
ABBREVIATIONS
AAP - AREA ALARM PANEL (MEDICAL GAS)
AC - AIR COMPRESSOR OR AIR CONDITIONER
ACC - ACCESS
ACCU - AIR COOLED CONDENSING UNIT
AD - ACCESS DOOR OR AREA DRAIN
ADB - ACID DILUTION BASIN
ADJ - ADJUSTABLE
AFF - ABOVE FINISHED FLOOR
AFG - ABOVE FINISHED GRADE
ALT - ALTERNATE
AP - ACCESS PANEL
APPROX - APPROXIMATE
AR - AIR RECEIVER OR ARGON
ARCH - ARCHITECT OR ARCHITECTURAL
ASSY - ASSEMBLY
AV - ACID VENT
AW - ACID WASTE
BDD - BACK DRAFT DAMPER
BFP - BACKFLOW PREVENTER
BLDG - BUILDING
BOB - BOTTOM OF BEAM
BOD - BOTTOM OF DUCT
BOE - BOTTOM OF EQUIPMENT
BOF - BOTTOM OF FOOTING
BOG - BOTTOM OF GRILLE
BOP - BOTTOM OF PIPE
BOT - BOTTOM
BT - BATHTUB
BTU - BRITISH THERMAL UNIT
BTUH - BRITISH THERMAL UNIT PER HOUR
BTWN - BETWEEN
CA - COMPRESSED AIR
CB - CATCH BASIN
CBD - COUNTER BALANCED BACKDRAFT DAMPER
CFCI - CONTRACTOR FURNISHED CONTRACTOR
INSTALLED
CFM - CUBIC FEET PER MINUTE
CHS - CHILLED WATER SUPPLY
CHR - CHILLED WATER RETURN
CI - CAST IRON
CK - CLINICAL SINK
CLG - CEILING
CMU - CONCRETE MASONRY UNIT
CO - CLEAN OUT
CO2 - MEDICAL CARBON DIOXIDE
CONN - CONNECT OR CONNECTION
CONTR - CONTRACTOR
COR - CONTRACTING OFFICER'S REPRESENTATIVE
CORR - CORRIDOR
CS - CLINICAL SINK OR COLD SOFT WATER
CTR - CENTER
CU - COPPER
CW - COLD WATER
CWS - COMBINATION WATER SERVICE
OR CONDENSER WATER SUPPLY
CWR - CONDENSER WATER RETURN
D - DEPTH OR DRAIN LINE
DD - DECK DRAIN
DET - DETAIL
DF - DRINKING FOUNTAIN OR WATER COOLER
OR DIESEL FUEL
DFU - DRAINAGE FIXTURE UNIT
DI - DEIONIZED WATER
DIA - DIAMETER
DIM - DIMENSION
DN - DOWN
DS - DOWN SPOUT OR SPRINKLER (DRY)
DT - PERFORATED DRAIN TILE
DWG - DRAWING
EA - EACH
EC - ELECTRICAL CONTRACTOR (DIVISION 26)
EEW - EMERGENCY EYE WASH
EJ - EXPANSION JOINT
ELEC - ELECTRICAL
ELEV - ELEVATOR
EQ - EQUAL
EQUIP - EQUIPMENT
ET - EXPANSION TANK
ETR - EXISTING TO REMAIN
ES - EMERGENCY SHOWER
EQS - EQUIPMENT SUPPLIER
EWC - ELECTRICAL WATER COOLER
EXH - EXHAUST AIR
EXP - EXPANSION
EXT - EXTERIOR
EX - EXISTING
F - FIRE SUPPRESSION (STANDPIPE/SPRINKLER
MAIN)
FCE - FIRE CONTROL EQUIPMENT
FCO - FLOOR CLEANOUT
FD - FLOOR DRAIN
FDC - FIRE DEPARTMENT CONNECTION
FDV - FIRE DEPARTMENT VALVE
FF - FINISHED FLOOR ELEVATION
FHC - FIRE HOSE CABINET
FLR - FLOOR
FM - FORCE MAIN
FOB - FLAT ON BOTTOM
FOF - FUEL OIL FLOW
FOG - FUEL OIL GAUGE
FOR - FUEL OIL RETURN
FOS - FUEL OIL SUPPLY
FOT - FLAT ON TOP
FPM - FEET PER MINUTE
FR - FIRE RISER
FS - FLOOR SINK OR FIRE SERVICE
FSC - FIRE SUPPRESSION CONTRACTOR
(DIVISION 21)
FT - FEET
FTG - FOOTING
G - GAS OR NATURAL GAS
GA - GAUGE
GAL - GALLON
GALV - GALVANIZED
GC - GENERAL TRADES CONTRACTOR
GD - GARAGE DRAINAGE
GPM - GALLONS PER MINUTE
GS - GAS SERVICE
GW - GREASE WASTE
H2 - HYDROGEN
HB - HOSE BIBB
HC - HVAC CONTRACTOR (DIVISION 23)
HD - HUB DRAIN
HE - HELIUM
HG - REFRIGERANT HOT GAS
HP - HORSEPOWER OR HIGH POINT
HPC - HIGH PRESSURE CONDENSATE RETURN
HPS - HIGH PRESSURE STEAM SUPPLY
HPW - HIGH PURITY WATER
HPWR - HIGH PURITY WATER RETURN
HR - HOSE REEL
HT - HEAT TRACE
HTR - HEATER
HVAC - HEATING, VENTILATING, AND AIR
CONDITIONING
HW - HOT WATER
HWR - HEATING HOT WATER RETURN
HWS - HEATING HOT WATER SUPPLY
IA - MEDICAL INSTRUMENT AIR
ID - INSIDE DIAMETER
INV - INVERT ELEVATION
IN - INCHES
IV - INDIRECT VENT
IW - INDIRECT WASTE
JS - JANITOR SINK
K - KITCHEN WASTE
KEC - KITCHEN EQUIPMENT CONTRACTOR
L - LENGTH
LA - LABORATORY COMPRESSED AIR
LAV - LAVATORY
LBS - POUNDS
LCW - LABORATORY COLD WATER
LEC - LABORATORY EQUIPMENT CONTRACTOR
LHW - LABORATORY HOT WATER
LHWR - LABORATORY HOT WATER RETURN
LPC - LOW PRESSURE CONDENSATE RETURN
LPS - LOW PRESSURE STEAM SUPPLY
LV - LABORATORY VACUUM OR LABORATORY
VENT
LW - LABORATORY WASTE
MA - MEDICAL COMPRESSED AIR
MAP - MASTER ALARM PANEL (MEDICAL GAS)
MAX - MAXIMUM
MB - MOP BASIN
MC - MECHANICAL CONTRACTOR (DIVISION 23)
MEZZ - MEZZANINE
MFR - MANUFACTURER
MH - MANHOLE
MIN - MINIMUM OR MINUTE
MISC - MISCELLANEOUS
MTD - MOUNTED
MTG - MOUNTING
MPC - MEDIUM PRESSURE CONDENSATE RETURN
MPS - MEDIUM PRESSURE STEAM SUPPLY
MU - WATER MAKE-UP
MV - MEDICAL SURGICAL VACUUM
N2 - MEDICAL NITROGEN
N/C - NORMALLY CLOSED
NG - GASOLINE (NON-LEAD)
NIC - NOT IN CONTRACT
N/O - NORMALLY OPEN
NO - MEDICAL NITROUS OXIDE
NOM - NOMINAL
NPW - NON-POTABLE WATER
NPT - NATIONAL PIPE THREAD
NTS - NOT TO SCALE
02 - MEDICAL OXYGEN
OA - OUTDOOR AIR
OD - OUTSIDE DIAMETER OR OVERFLOW DRAIN
OFCI - OWNER FURNISHED CONTRACTOR
INSTALLED
OFOI - OWNER FURNISHED OWNER INSTALLED
P - PROPANE GAS
PC - PLUMBING CONTRACTOR (DIVISION 22)
OR PUMPED CONDENSATE RETURN
PD - PUMP DISCHARGE OR PARAPET DRAIN
PIV - POST INDICATOR VALVE
PLBG - PLUMBING
PS - PRE-ACTION/DELUGE SPRINKLER
PRESS - PRESSURE
PRV - PRESSURE REGULATING VALVE
PSF - POUNDS PER SQUARE FOOT
PSI - POUNDS PER SQUARE INCH
PSV - PRESSURE SUSTAINING VALVE
PSIG - POUNDS PER SQUARE INCH GAUGE
PW - PURE WATER
RA - RETURN AIR
RAD - RADIUS
RCP - REINFORCED CONCRETE PIPE
RD - ROOF DRAIN
REC - RECESSED
REQD - REQUIRED
RI - ROUGH IN
RL - REFRIGERANT LIQUID
ROS - REVERSE OSMOSIS WATER SUPPLY
ROR - REVERSE OSMOSIS WATER RETURN
RPM - REVOLUTIONS PER MINUTE
RS - REFRIGERANT SUCTION
RV - RELIEF VALVE
S - SPRINKLER (WET)
SA - SHOCK ARRESTOR OR SUPPLY AIR
SAN - SANITARY OR SANITARY DRAIN
SCH - SCHEDULE
SCW - SOFT COLD WATER
SD - SPRINKLER DRAIN OR SUBSOIL DRAIN
SH - SHOWER
SHT - SHEET
SK - SINK
SPEC - SPECIFICATIONS
SQ - SQUARE
SR - SUPPLY RISER
SS - SANITARY STACK (SOIL OR WASTE) OR
STAINLESS STEEL
STD - STANDARD
STM - STORM OR STORM DRAINAGE
STRUC - STRUCTURAL OR STRUCTURE
SUC - SITE UTILITY CONTRACTOR
T - FUEL TANK VENT
TD - TRENCH DRAIN
TEMP - TEMPERATURE
TOB - TOP OF BEAM
TOD - TOP OF DUCT
TOE - TOP OF EQUIPMENT
TOF - TOP OF FOOTING
TOJ - TOP OF JOIST
TOP - TOP OF PIPE
TOS - TOP OF SLAB OR TOP OF STEEL
TF - TRAP FILLER
TP - TRAP PRIMER OR TRAP PRIMER
DISCHARGE
TW - TEMPERED WATER
TYP - TYPICAL
UR - URINAL
UNO - UNLESS NOTED OTHERWISE
V - VENT OR SANITARY SEWER VENT
VAC - VACUUM
VC - VACUUM CLEANING
VCV - VACUUM CLEANING VALVE
VE - VACUUM EXHAUST
VEL - VELOCITY
VIB - VALVE IN BOX
VOL - VOLUME
VP - VACUUM PUMP
VS - VENT STACK
VTR - VENT THROUGH ROOF
VR - VENT RISER
W/ - WITH
W/O - WITHOUT
W - WASTE
WAGD - WASTE ANESTHESIA GAS DISPOSAL
WC - WATER CLOSET
WCO - WALL CLEANOUT
WH - WALL HYDRANT OR WATER HEATER
WIV - WALL INDICATOR VALVE
WS - WATER SERVICE
YCO - YARD CLEANOUT
ZVC - ZONE VALVE CABINET
PIPE RISER
NOTE:
ALL SYMBOLS OR ABBREVIATIONS MIGHT NOT
NECESSARILY BE USED ON THIS PROJECT.
FIRE SUPPRESSION DESIGN NOTES
A PROVIDE A COMPLETE FIRE SUPPRESSION SPRINKLER SYSTEM IN THE
RENOVATED AREA.
B COORDINATE WORK WITH VAMC, PHASING PLAN AND OTHER TRADES. OFFSET
AND/OR RELOCATE EXISTING SERVICES TO ACCOMMODATE NEW WORK OF
OTHER TRADES.
C DESIGN SERVICES SHALL FOLLOW ALL VA STANDARD DESIGN PRACTICES,
DETAILS, SPECIFICATIONS AND SITE SPECIFIC COR REQUIREMENTS AS WELL
AS WORK SHOWN ON THESE DOCUMENTS. ALL DEVIATIONS FROM
AFOREMENTIONED REQUIREMENTS SHALL BE APPROVED BY THE COR.
D VERIFY THAT THERE IS ADEQUATE SPACE TO INSTALL ALL NEW PIPING
REQUIRED TO COMPLETED THIS WORK.
E ALL SPRINKLER PIPING IS LOCATED ABOVE THE CEILING (AT THE BOTTOM OF
STRUCTURE IN EXPOSED STRUCTURAL AREAS) UNLESS OTHERWISE
INDICATED.
F THE BASIS OF DESIGN OF SPACING AND SIZING FOR THE COMPLETE FIRE
SUPPRESSION SPRINKLER SYSTEM SHALL BE FOR A WET/DRY PIPE SYSTEM
HYDRAULICALLY CALCULATED FOR A :
1 LIGHT HAZARD AREA LIMITED TO A MAXIMUM OF 225 SQ. FT. PER
SPRINKLER WITH THE DENSITY OF 0.10 GPM/ SQ. FT. OVER THE MOST
REMOTE 1500 SQ. FT. PROVIDE AN ADDITION OF 100 GPM HOSE
ALLOWANCE.
2 ALL MECHANICAL, ELECTRICAL AND SIMILAR SPACE AREAS SHALL BE
ORDINARY HAZARD (GROUP 1) LIMITED TO A MAXIMUM OF 130 SQ. FT. PER
SPRINKLER WITH A DENSITY OF 0.15 GPM/ SQ. FT. PROVIDE AN ADDITION
OF 250 GPM HOSE ALLOWANCE.
3 ALL STORAGE, TRASH, FILE STORAGE AND SIMILAR SPACE AREAS SHALL
BE ORDINARY HAZARD (GROUP 2) LIMITED TO A MAXIMUM OF 130 SQ. FT.
PER SPRINKLER WITH A DENSITY OF 0.20 GPM/ SQ. FT. PROVIDE AN
ADDITION OF 250 GPM HOSE ALLOWANCE.
G PROVIDE SPRINKLER LOCATIONS AND RELATED PIPING.
H THE ENTIRE SPRINKLER SYSTEM SHALL CONFORM TO VAMC, LOCAL, STATE
AND NFPA STANDARD, RULES AND REGULATIONS.
I CAREFULLY COORDINATE THE LOCATION OF ALL SPRINKLERS AND PIPING
WITH ALL OTHER TRADES AND THE ARCHITECT.
J VERIFY THE LOCATION OF ALL LIGHTING FIXTURES AND AIR DEVICES BEFORE
INSTALLATION OF SPRINKLERS.
K PROVIDE SPRINKLER PIPING LAYOUT AND SIZING.
L ALL SPRINKLER LOCATIONS MUST BE COORDINATED WITH ALL EQUIPMENT
KINDRED TO OTHER TRADES. SPRINKLER LOCATIONS MUST BE APPROVED BY
THE ARCHITECT BEFORE WORK COMMENCES. REFER TO THE ARCHITECTURAL
AND REFLECTIVE CEILING PLANS FOR ADDITIONAL INFORMATION ON ALL
CEILING TYPES, HEIGHTS AND OTHER ARCHITECTURAL FEATURES.
M MAKE NECESSARY FLOW TESTS, LAYOUT SYSTEMS, OBTAIN APPROVALS
FROM THE AUTHORITIES HAVING JURISDICTION PRIOR TO BEGINNING ANY
FABRICATION OR INSTALLATION WORK.
N SPRINKLER PIPING SHALL BE 1" MINIMUM SIZE.
O SPRINKLERS (UNLESS OTHERWISE NOTED):
EXPOSED AREAS - UPRIGHT OR PENDENT TYPE - STANDARD BRASS
CEILING AREAS - RECESS PENDENT TYPE
ALL SPRINKLERS SHALL BE UL LISTED AND FM APPROVED.
P SPRINKLERS SHALL BE "QUICK RESPONSE" TYPE IN ALL AREAS EXCEPT HIGH
TEMPERATURE AREAS.
Q ALL PENDENT TYPE SPRINKLERS LOCATED IN SUSPENDED CEILING TILE
AREAS SHALL BE LOCATED IN THE CENTER OF THE CEILING TILE.
R ANNULAR SPACE AT PIPE AND OTHER SIMILAR PENETRATION OF FIRE RATED
ASSEMBLIES SHALL BE FIRESTOPPED. REFER TO SPECIFICATION SECTION
07 84 00 FIRESTOPPING. REFER TO ARCHITECTURAL DRAWINGS FOR
CONSTRUCTION, LAYOUT AND FIRE RATING OF FLOORS, WALLS, PARTITIONS
AND OTHER BUILDING ELEMENTS.
S A FLOW TEST IS REQUIRED. REFER TO SPECIFICATION SECTION 21 13 13 FOR
FLOW TEST INFORMATION.
T ALL SPRINKLER ZONES SHALL MATCH SMOKE COMPARTMENTS.
U REFER TO ARCHITECTURAL DRAWINGS FOR INFORMATION ON SMOKE
COMPARTMENTS, SMOKE PARTITIONS AND FIRE BARRIERS.
V PHASING: REFER TO ARCHITECTURAL DRAWINGS FOR AN OUTLINE OF
PROJECT PHASING. ADDITIONAL NOTES DESCRIBING PHASING DETAILS MAY
BE INCLUDED THROUGHOUT THIS DRAWING SET.
W BID ITEMS: REFER TO ARCHITECTURAL DRAWINGS AND SPECIFICATION
SECTION 01 00 00 FOR AN OUTLINE OF BID ITEMS. ADDITIONAL NOTES
DESCRIBING BID ITEM DETAILS MAY BE INCLUDED THROUGHOUT THIS
DRAWING SET.
X SPRINKLER SYSTEM PIPING AND FITTINGS SHALL BE IN ACCORDANCE WITH
NFPA 13:
1 PIPING SIZES 2 INCHES AND SMALLER SHALL BE BLACK STEEL SCHEDULE
40 WITH THREADED END CONNECTIONS.
2 PIPING SIZES 2.5 INCHES AND LARGER SHALL BE BLACK STEEL SCHEDULE
10 WITH GROOVED CONNECTIONS. GROOVES IN SCHEDULE 10 PIPING
SHALL BE ROLLED GROOVED ONLY.
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC.
905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
PROJECT NO. STATE COA FIRM NO.2018-05164 01528
/2
/2
:4
:1
P
M
FX001
LEGEND, ABBREVIATIONS & INDEX
OF DRAWINGS
CORRECT
INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OHIO 45428
552-19-102
PHIL WEST, COR
May 2nd, 2025 EWL KMB
BID DOCUMENTS
FULLY SPRINKLERED
INDEX OF DRAWINGS - FIRE SUPPRESSION
Sheet Number Sheet Name
FX001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
FX100 FIRE SUPPRESSION PLANS
S
3 - AIR COMPRESSOR
TO FDC
Storage
Unexcavated
OH
100m
OFFICE
100g
OFFICE
100n
OFFICE
OPEN
OFFICE
100h
OFFICE
103C
CONFERENCE
OFFICE
103D
OFFICE
103A
OFFICE
OFFICE
TELE
PHARMACY
MENS
103B
COMM.
Room
101C
OFFICE
ACQUISITION
CHAPLAIN
101D
OFFICE
101A
OFFICE
KITCHEN
106k
OFFICE
106l
OFFICE
106h
OFFICE
106g
OFFICE
DSS SUITE
106e
OFFICE
106d
STORAGE
106a
OFFICE
106j
OFFICE
106f
OFFICE
106c
COPIER
106b
OFFICE
100d
OFFICE
100c
OFFICE
100k
OFFICE
100j
OFFICE
100l
OFFICE
WOMENS
107f
CONFERENCE
107g
OFFICE
107a
OFFICE
107c
OFC
107d
OFC
107e
OFC
107b
OFC
SUITE
109C
OFFICE
203E
CONFERENCE
ROOM
TOILET
TOILET
205B
NNU
OFFICE
F S
DSS
EXISTING DRY VALVE
NEW SUPERVISED
VALVE
6"
6"
6"
6"
NEW 6-INCH DOUBLE CHECK
DETECTOR ASSEMBLY WITH
SUPERVISED VALVES.
NEW CHECK VALVECONT'D TO FDC
CONT'D TO WET-
PIPE SYSTEM
CONT'D TO DRY-
PIPE SYSTEMEXISTING FIRE SERVICE ENTRANCE
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC.
905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
PROJECT NO. STATE COA FIRM NO.2018-05164 01528
/2
/2
:4
:2
P
M
FX100
FIRE SUPPRESSION PLANS CORRECT
INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OHIO 45428
552-19-102
PHIL WEST, COR
May 2nd, 2025 EWL KMB
BID DOCUMENTS
FULLY SPRINKLERED
SCALE: 1/16" = 1'-0"FX100
1 BASEMENT - FIRE SUPPRESSION - NEW WORK
SCALE: 1/16" = 1'-0"FX100
2 FIRST FLOOR - FIRE SUPPRESSION - NEW WORK
SCALE: 1/16" = 1'-0"FX100
3 SECOND FLOOR - FIRE SUPPRESSION - NEW WORK
SCALE: 1/16" = 1'-0"FX100
4 ATTIC - FIRE SUPPRESSION - NEW WORK
GENERAL NOTES
A REFER TO SHEET FX001 FOR LEGEND AND GENERAL NOTES.
B EXISTING CORRIDORS OR ROOMS TO REMAIN OPERATIONAL
AT ALL TIMES DURING BUSINESS HOURS. AUTOMATIC
SPRINKLER SYSTEM SHALL BE MAINTAINED IN FULLY
OPERATIONAL CONDITION (PER NFPA 241, SPRINKLER
SYSTEM(S) WILL BE OPERATIONAL, BUT IMPAIRED WHILE
CEILINGS ARE REMOVED). SPRINKLER SYSTEM MAY BE TAKEN
OFF-LINE FOR UP TO 4 HOURS AS REQUIRED TO MAKE
MODIFICATIONS/ CONNECTIONS TO ACCOMMODATE PROJECT
PHASING. COORDINATE WORK WITH COR.
PLAN NOTES
1 LIMITS OF AREA REQUIRING CEILING REMOVAL AND
MODIFICATIONS TO EXISTING SPRINKLER SYSTEM.
MODIFICATIONS INCLUDE, BUT ARE NOT LIMITED TO,
REPLACEMENT OF SPRINKLERS AND BRANCH PIPING TO
CONFORM TO NEW MECHANICAL EQUIPMENT, DUCTWORK
AND PIPING AND ELECTRICAL EQUIPMENT AND COMPONENTS.
EXISTING PIPING SHALL BE RE-USED AS MUCH AS POSSIBLE.
2 NEW 6-INCH ASSE 1015 LISTED DOUBLE CHECK DETECTOR
ASSEMBLY. REVISE EXISTING FIRE SERVICE PIPING AND
ACCESSORIES FOR ADDITION OF NEW DOUBLE CHECK
DETECTOR ASSEMBLY.
3 EXISTING TO REMAIN.
N N
NN
NOT TO SCALEFX100
5 EXISTING FIRE SERVICE
NOT TO SCALEFX100
6 FIRE SERVICE
DUCT THERMOSTAT WITH AVERAGING ELEMENT
DUCT STATIC PRESSURE SENSOR
DUCT HUMIDITY SENSOR
ROOM SENSOR: TEMPERATURE, HUMIDITY
LENGTH IN DUCT WHEN SPACE PERMITS)
REMOTE BULB THERMOSTAT
ROOM CONTROL: THERMOSTAT, HUMIDISTAT
DIFFERENTIAL PRESSURE SWITCH
DUCT TEMPERATURE SENSOR WITH AVERAGING ELEMENT
SMOKE DETECTOR (SEE DIV. 28)
DUCT OR PIPE TEMP. SENSOR
DUCT OR PIPE THERMOSTAT (NOTE 1: PROVIDE 12" MIN.
CURRENT SENSING RELAY
AIR FOIL WHEEL (FAN)
AIR HANDLING UNIT
ANALOG INPUT
AIR PRESSURE DROP
ANALOG OUTPUT
AUTOMATIC TEMPERATURE CONTROLS
BACKWARD INCLINED WHEEL (FAN)
AIR FLOW MEASURING DEVICE
ABOVE FINISHED FLOOR
DIFFERENTIAL OR STATIC PRESSURE TRANSMITTER
COOLING COIL
CONVERTOR
CONVECTOR
CLEAN OUT
CEILING GRILLE
CENTRIFUGAL FAN
CEILING DIFFUSER
BOTTOM REGISTER (WALL TYPE)
BOTTOM GRILLE (WALL TYPE)
CEILING REGISTER
COLD WATER (POTABLE)
DIGITAL OUTPUT
DIGITAL INPUT
DIRECT DIGITAL CONTROLS
DRY BULB TEMPERATURE, DEG. F
AUTOMATIC CONTROL DAMPER
EXHAUST FAN
ENGINEERING CONTROL CENTER
DOUBLE WIDTH DOUBLE INLET (FAN)
DOOR UNDERCUT - REFER TO ARCHITECTURAL DRAWINGS
IN COORDINATING THE VARIOUS TRADES.)
LISTED SIZE OF DUCT. (TO BE USED AS AND AID IN
APPROXIMATE ELEVATION FROM FLOOR TO BOTTOM OF
MANUAL VOLUME DAMPER
U/C
STATIC TYPE 'B' FIRE DAMPER
BUTTERFLY VALVE
CIRCUIT SETTER
BALL VALVE
COMBINATION BALANCING/SHUT-OFF VALVE
MANUAL AIR VENT
AUTOMATIC FLOW CONTROL VALVE
TEST PLUG (PRESSURE/TEMPERATURE)
SAFETY VALVE OR PRESSURE RELIEF
PRESSURE REDUCING VALVE
STRAIGHT-THRU TWO-POSITION CONTROL VALVE
THREE-WAY MODULATING CONTROL VALVE
STRAIGHT-THRU MODULATING CONTROL VALVE
EX.
EF
EXISTING
DWDI
ECC
DI
DO
DB
DDC
D
Db
DECIBELS
BUILDING NO. WHERE EQUIPMENT IS LOCATED.
EQUIPMENT ABBREVIATION (SUPPLY FAN)
SUPPLY FAN NO.3 IN BUILDING NO.1
DRAWING NUMBER WHERE DRAWN
DRAWING NUMBER WHERE DRAWN
SUPPLY TOP REGISTER OR GRILLE (WALL TYPE)
RETURN DUCT (UP & DOWN)
VANED ELBOW & AIR SPLIT TYPE DUCT TAKE-OFF
EXHAUST OR RETURN TOP REGISTER OR GRILLE,
EXHAUST OR RETURN BOTTOM REGISTER OR GRILLE,
EXHAUST OR RETURN CEILING REGISTER OR GRILLE
SUPPLY DUCT (UP & DOWN)
INCLINED RISE, IN DIRECTION OF AIR FLOW
NEW DUCT - WIDTH X DEPTH
RECTANGULAR ELBOWS WITH VANES EVEN IF
VANED ELBOW (PROVIDE ALL SQUARE OR
INCLINED DROP, IN DIRECTION OF AIR FLOW
ACOUSTICAL DUCT LINING
STANDARD RADIUS ELBOW
R
10/8
FC
D
SYMBOL IS MISSING)
FLEXIBLE CONNECTION
UP
(WALL TYPE)
(WALL TYPE)
DN
UP
1-01
1-SF3
AIR HANDLING UNIT NUMBER
TERMINAL UNIT DESIGNATION
TYPICAL UNIT NO.
DN
SECTION LETTER
DETAIL NUMBER
ECCENTRIC REDUCER
DIRECTION OF FLOW
CAPPED OUTLET
SIDE CONNECTION
EXISTING WORK.
ACCESSORIES (SEE STANDARD DETAIL)
INVERTED BUCKET TRAP SET INCLUDING PIPING
POINT OF CONNECTION BETWEEN NEW AND
RISE OR DROP IN PIPE
BOTTOM CONNECTION, 45 DEG. OR 90 DEG.
TOP CONNECTION, 45 DEG. OR 90 DEG.
REDUCER OR INCREASER
DIRECTION OF PIPE PITCH (DOWN)
THERMOMETER
THERMOSTATIC TRAP
STRAINER
GATE VALVE
PRESSURE GAGE
CHECK VALVE
GLOBE VALVE
PIPING ACCESSORIES (SEE STANDARD DETAIL)
FLOAT AND THERMOSTATIC TRAP SET INCLUDING
GATE VALVE WITH 3/4" HOSE END ADAPTER
EXISTING PIPE TO BE REMOVED
DRAIN LINE
UNION
D
CONV
CW
CR
CO
CG
CF
CD
CC
C
BR
BIW
BG
ATC
AFW
AI
APD
AO
AHU
AFM
AFF
VENT LINE
HEATING HOT WATER RETURN
HEATING HOT WATER SUPPLY
LOW PRESSURE STEAM CONDENSATE RETURN
LOW PRESSURE STEAM (15 PSIG & BELOW)
MEDIUM PRESSURE STEAM CONDENSATE RETURN
MEDIUM PRESSURE STEAM (16 PSIG THRU 59 PSIG)
NUMBER INDICATES STEAM PRESSURE
NUMBER INDICATES STEAM PRESSURE
LPR
V
HWS
HWR
LPS (5)
MPS (30)
MPR
HEATING
SP
S F
T
H
T
T H
WET BULB TEMPERATURE, DEG. FWb
MAXIMUM
OUTSIDE AIR
(16 PSIG THRU 59 PSIG)
PRE-FILTER
PUMPED CONDENSATE
PREHEAT COIL
RELATIVE HUMIDITY
SUPPLY FAN
STEAM HUMIDIFIER
TRANSFER GRILLE
UNIT HEATER
STATIC PRESSURE (INCHES OF WATER)
PRESSURE REDUCING VALVE
MEDIUM PRESSURE STEAM SUPPLY
MEDIUM PRESSURE STEAM CONDENSATE RETURN
PRESSURE DROP (FEET OF WATER)
TOP REGISTER (WALL TYPE)
VARIABLE FREQUENCY DRIVE
STATIC PRESSURE SENSOR
DOOR UNDERCUT BY GENERAL CONTRACTOR
SPS
TR
U/C
VFD
UH
V
TG
VALVE
S.P.
SH
SF
Rh
PD
PF
PH
PRV
MPC
MAX
O.A.
NOM
MIN
PC
MPS
NOMINAL
MINIMUM
HEATING COIL
HORSEPOWER
MIXING BOX
POUNDS PER HOUR
HIGH PRESSURE STEAM SUPPLY (60 PSIG & ABOVE)
LOW PRESSURE STEAM SUPPLY (15 PSIG & BELOW)
LOW PRESSURE STEAM CONDENSATE RETURN
HIGH PRESSURE STEAM CONDENSATE RETURNHPR
HPS
LPR
LBS/HR
MB
LPS
HC
HP
BLOW UNLESS OTHERWISE NOTED)
CEILING DIFFUSERS (FOUR WAY
CHILLED WATER RETURN
CHILLED WATER SUPPLYCHS
CHR
AIR CONDITIONING
CONTROL CIRCUIT CONN.H1 N
ETCHED CLEAR LACQUERE.C.L.
WHITE BAKED ENAMELW.B.E.
BRAKE HORSEPOWERBHP
BRITISH THERMAL UNITBTU
BRITISH THERMAL UNIT PER HOURBTUH
CUBIC FEET PER MINUTECFM
DEGREEDEG
DIAMETERDIA
DIFFERENTIAL PRESSURE SENSORDPS
ENTERINGENT
F FAHRENHEIT
F&T FLOAT AND THERMOSTATIC
FPM FEET PER MINUTE
FT FEET
GALLONS PER MINUTEGPM
HEADHD
CHILLED WATER RETURNCHR
CHILLED WATER SUPPLYCHS
HEATING HOT WATER RETURNHWR
HEATING HOT WATER SUPPLYHWS
INCHESIN
INCHES WATER COLUMNIN WC
INCHES WATER GAUGEIN WG
LEAVING AIR TEMPERATURELAT
LEAVINGLVG
MBH 1000 BTUH
MERV MINIMUM EFFICIENCY REPORTING VALUE
NC NOISE CRITERIA
REVOLUTIONS PER MINUTERPM
SMOKE DAMPER (SUPPLY)SDS
SMOKE DAMPER (RETURN)SDR
STEAM PRESSURE REDUCING VALVESPRV
VOLUME DAMPERVD
HIGH PRESSURE STEAM CONDENSATE RETURN
HIGH PRESSURE STEAM (60 PSIG AND ABOVE)
NUMBER INDICATES STEAM PRESSURE
HPS (125)
HPR
PIPE UP
PIPE DOWN
IN-LINE CENTRIFUGAL FANICF
T
T
T
T
H dP
CS
DP SP
H4
A
H7
B.O.D. 9'-6"
MV MANUAL AIR VENT
EXHAUST DUCT (UP & DOWN)UP DN
PUMPED CONDENSATE RETURNPC
COMBINATION HOT/CHILLED WATER SUPPLYHWS/CHS
COMBINATION HOT/CHILLED WATER RETURNHWR/CHR
EXPANSION TANK PIPEET
CONDENSATE PUMPCP
CABINET UNIT HEATERCUH
FCU FAN COIL UNIT
EXPANSION TANKET
PUMPP
PROPELLER UNIT HEATERPUH
RETURN FANRF
WATER FILTERWF
POWER TYPE ROOF VENTILATORRV
POWER TYPE WALL VENTILATORWV
COR
PROPELLER TYPE EXHAUST FANPEF
RETURN AIRR.A.
SUPPLY AIRS.A.
SINGLE WIDTH SINGLE INLET (FAN)SWSI
SPECIFIC GRAVITYSP. GR.
FD FLOOR DRAIN
FCW FORWARD CURVED WHEEL (FAN)
FC FLEXIBLE CONNECTION
ENERGY EFFICIENCY RATIOEER
EXHAUST AIRE.A.
CONTRACTING OFFICER'S REPRESENTATIVE
CENTRIFUGAL OR HELICAL ROTARY SCREW CHILLER UNITCCU
AIR SEPARATORAS
ANGLE GLOBE VALVE
PIPE GUIDE
PIPE ANCHOR
ORIFICE UNION
TREATED DOMESTIC MAKE-UP WATER
STAINLESS STEEL DUCT
MU
GMU
FOR HUMIDIFIER
GLYCOL MAKEUP WATER
HOT GLYCOL WATER RETURN
HOT GLYCOL WATER SUPPLYGHS
GHR
CHILLED GLYCOL WATER SUPPLYGCS
CHILLED GLYCOL WATER RETURNGCR
UTILITY SET FANUSF
T
GENERAL
DOMESTIC COLD WATERW
FLOW METERM
PIPE MOUNTED DDC TEMPERATURE SENSOR
TOP GRILLE (WALL TYPE)TG
WATER GAUGEWG
WATTSW
VARIABLE AIR VOLUMEVAV
THERMOSTATTSTAT
TOTAL STATIC PRESSURETSP
SMOKE DETECTORSD
SUPPLY AIR TEMPERATURESAT
OUTSIDE DIAMETEROD
N.C. NORMALLY CLOSED
N.O. NORMALLY OPEN
MCA MINIMUM BRANCH CIRCUIT AMPACITY
LEAVING WATER TEMPERATURELWT
ENTERING WATER TEMPERATUREEWT
EXTERNAL STATIC PRESSUREESP
DIRECT EXPANSIONDX
ENTERING AIR TEMPERATUREEAT
GHR HOT GLYCOL HEATING WATER RETURN
GHS HOT GLYCOL HEATING WATER SUPPLY
VARIABLE VOLUME REHEAT (AIR TERMINAL UNIT)VVR
FLR. FLOOR
C CARBON DIOXIDE SENSOR (MOUNTED AT 46") 37. ALL EXISTING DUCTWORK, PIPING, EQUIPMENT, CONTROLS, ETC. SHOWN ON REMOVAL
PLAN(S) SHALL BE REMOVED. THE MAJORITY OF WORK TO BE REMOVED IS SHOWN.
REMOVE ALL INCIDENTAL AND/OR ABANDONED DUCTWORK, PIPING, ETC. THAT MAY NOT
BE SHOWN BUT IS ASSOCIATED WITH THE REMOVAL WORK.
38. ALL ITEMS THAT REQUIRE ACCESS, SUCH AS FOR OPERATING, CLEANING, SERVICING,
MAINTENANCE, AND CALIBRATION, SHALL BE EASILY AND SAFELY ACCESSIBLE BY
PERSONS STANDING AT FLOOR LEVEL, OR STANDING ON PORTABLE LADDERS OR
PERMANENT PLATFORMS. EXAMPLES OF THESE ITEMS INCLUDE, BUT
ARE NOT LIMITED TO: ALL TYPES OF VALVES, FILTERS AND STRAINER, TRANSMITTERS,
CONTROL DEVICES, ETC.
39. WHERE EXISTING HVAC UTILITIES IN SERVICE WILL BE DISRUPTED DURING THE
CONSTRUCTION OF THIS PROJECT, THIS WORK SHALL BE PERFORMED ON WEEKENDS OR
WEEK NIGHTS. DOWNTIME SHALL BE KEPT TO A MINIMUM, AND SHALL BE COORDINATED
AND SCHEDULED AT LEAST 10 WORKING DAYS IN ADVANCE WITH THE COR.
40. WHEN NEW SUPPLY AND RETURN AIR DUCTS ARE CONNECTED TO EXISTING DUCTWORK,
CLEAN BOTH NEW AND EXISTING DUCTWORK BY MOPPING AND VACUUM CLEANING INSIDE
AND OUTSIDE BEFORE OPERATION. CLEANING OF EXISTING DUCTWORK SHALL BE LIMITED
TO THE IMMEDIATE AREA WITHIN REACH OF THE OPEN END OF THE DUCT.
41. RUNOUT PIPING TO TERMINAL UNITS SHALL BE 0.75” SIZE UNLESS OTHERWISE NOTED.
REFER TO AIR TERMINAL UNIT SCHEDULE(S).
42. APPROXIMATE ELEVATIONS NOTED ON FLOOR PLANS ARE TO THE BOTTOM OF DUCTS
AND EQUIPMENT, AND TO THE CENTER OF PIPES.
43. REFER TO ELECTRICAL DRAWINGS FOR VARIABLE SPEED MOTOR CONTROLLERS
ASSOCIATED WITH MECHANICAL EQUIPMENT.
44. ALL INSULATED DUCTWORK AND PIPING SHALL HAVE DAMPER/VALVE HANDLE
EXTENSIONS.
1. THESE NOTES APPLY EQUALLY TO THE FULL SET OF DOCUMENTS.
2. SITE VISIT(S) SHALL BE AS OUTLINED IN PROJECT SPECIFICATIONS.
3. INCLUDE ALL WORK NECESSARY TO ACCOMMODATE PHASING. REFER TO
ARCHITECTURAL DRAWINGS AND GENERAL REQUIREMENTS SECTION 01 00 00.
4. INSULATE DUCTWORK AND PIPING WHERE EXISTING INSULATION HAS BEEN DAMAGED
AND/OR REMOVED IN THE PERFORMANCE OF WORK IN THIS PROJECT.
5. PROVIDE ALL ROOFING PENETRATION, REPAIR & REINFORCEMENT IN THE EXISTING
BUILDING FOR WORK INDICATED. ENGAGE A ROOFING SUBCONTRACTOR TO PERFORM
THE ROOFING WORK. WHERE ROOFING WORK IS REQUIRED, THE EXISTING ROOFING
AND INSULATION SHALL BE CUT, REMOVED AND RESTORED AS REQUIRED TO
ATTAIN A WATERTIGHT CONDITION. THE ROOFING SUB-CONTRACTOR SHALL BE A
CERTIFIED INSTALLER FOR SUCH INSTALLATION TO MAINTAIN THE EXISTING WARRANTY
ON THE ROOF.
6. THE CONTRACTORS SHALL REFER TO ALL SPECIFICATION SECTIONS AND THESE
7. IN ACCORDANCE WITH GENERALLY ACCEPTED CONSTRUCTION PRACTICES, THE
CONTRACTOR WILL BE SOLELY AND COMPLETELY RESPONSIBLE FOR THE CONDITIONS ON
THE JOB SITE, INCLUDING SAFETY OF ALL PERSONS AND PROPERTY DURING
PERFORMANCE OF THE WORK. THIS WILL APPLY CONTINUOUSLY AND NOT BE LIMITED TO
NORMAL WORKING HOURS. SEE SPECIFICATIONS FOR MORE SPECIFIC DETAILS ON
RESPONSIBILITIES.
8. ALL WORK MUST BE COORDINATED WITH THE CONTRACTING OFFICER AND COR TO
MAINTAIN OPERATION OF THE EXISTING FACILITY.
9. EACH TRADE SHALL COORDINATE HIS WORK WITH THE WORK OF OTHERS. HE
SHALL KEEP HIMSELF INFORMED OF THE PROGRESS AND DETAIL DEVELOPMENT OF THE
WORK OF OTHERS AND SHALL BE RESPONSIBLE FOR COORDINATING AND EXPEDITING HIS
WORK WITH OTHERS SO THAT THE PROGRESS OF THE TOTAL WORK SHALL BE KEPT ON
SCHEDULE.
10. ALL WORK SHALL BE PERFORMED IN COMPLETE COMPLIANCE WITH ALL GOVERNING
CODES AND STANDARDS.
11. EXISTING CONDITIONS SHOWN HAVE BEEN BASED UPON VISUAL OBSERVATION AND/OR
AVAILABLE DRAWING INFORMATION, AND MAY BE AT VARIANCE WITH ACTUAL WORK IN
PLACE. THE CONTRACTOR SHALL TAKE ALL NECESSARY FIELD MEASUREMENTS AND
FIELD VERIFY ALL CONDITIONS AFFECTING THE EXECUTION OF THE WORK. ANY
DISCREPANCIES BETWEEN EXISTING CONDITIONS AND THE WORK SHOWN ON THE
CONTRACT DOCUMENTS WHICH MAY IMPACT THE PROGRESS OF THE WORK SHALL BE
BROUGHT TO THE ATTENTION OF THE CONTRACTING OFFICER IN WRITING FOR
RESOLUTION BEFORE PROCEEDING WITH THE WORK.
12. THE CONTRACTOR AND/OR TRADE, FITTING OR PLACING HIS WORK INTO OR ON THE
WORK OF OTHERS DOES SO WITH THE UNDERSTANDING THAT THE INSTALLATION OF HIS
WORK CONSTITUTES HIS ACCEPTANCE OF THE SUITABILITY OF THE WORK IN PLACE. IF
THE WORK OF OTHERS IS NOT ACCEPTABLE, HE SHALL NOTIFY THE COR AND SUCH WORK
SHALL BE CORRECTED. ANY NEW WORK INSTALLED IN UNSUITABLE EXISTING CONDITIONS
SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR OR TRADE INSTALLING THE NEW
WORK. NO CLAIMS FOR ADDITIONAL COMPENSATION FOR CORRECTING WORK INSTALLED
IN UNSUITABLE EXISTING CONDITIONS WILL BE CONSIDERED.
13. IF, IN THE PERFORMANCE OF THIS WORK, MATERIALS ARE OBSERVED WHICH ARE
SUSPECTED TO CONTAIN ASBESTOS, THE CONTRACTOR SHALL IMMEDIATELY INFORM THE
COR. WORK THAT WOULD EXPOSE WORKERS TO THE INHALATION OF ASBESTOS
PARTICLES SHALL BE TERMINATED. WORK MAY BE RESUMED ONLY AFTER A
DETERMINATION HAS BEEN MADE AND UNSAFE MATERIALS HAVE BEEN REMOVED OR
ENCAPSULATED AND THE AREA DECLARED SAFE.
14. REFER TO ARCHITECTURAL FIRE-RATED PARTITION PLAN(S) FOR LOCATIONS AND
FIRE-RATINGS OF NEW AND EXISTING WALL ASSEMBLIES. ALL PENETRATIONS THROUGH
FIRE-RATED ASSEMBLIES SHALL BE PROTECTED AND/OR FIRE-STOPPED AS REQUIRED TO
MAINTAIN FIRE-RATINGS INDICATED. COORDINATE WITH ALL TRADES TO ENSURE
FIRE-RATED PENETRATION REQUIREMENTS AND DETAILS ARE MET.
15. ANNULAR SPACE OF ALL PIPE, CONDUIT, DUCT & OTHER SIMILAR PENETRATIONS OF FIRE
RATED ASSEMBLIES SHALL BE FIRESTOPPED. IN ADDITION, PENETRATIONS THROUGH
0-HOUR RATED WALLS & FLOORS SHALL BE SEALED TO RETARD PASSAGE OF SMOKE.
16. ALL PIPING, DUCTS, CONDUITS, ETC. IN FINISHED ROOMS, CORRIDORS, ETC. SHALL BE
CONCEALED IN A FURRED CHASE OR ABOVE THE SUSPENDED CEILING.
17. THE FIRST FIGURE OF DUCT SIZE INDICATES DIMENSION OF FACE SHOWN OR INDICATED.
DUCT SIZES ARE NET INSIDE DIMENSIONS.
18. PROVIDE DUCT ACCESS PANELS AS REQUIRED BY 23 31 00 FOR ACCESS TO FIRE
DAMPERS, SMOKE DAMPERS, SMOKE DETECTORS, AUTOMATIC CONTROL DAMPERS, AND
HUMIDIFIER DISPERSION TUBES. REFER TO DETAIL SHEETS. COORDINATE SIZES
AND LOCATIONS WITH ACCESSORIES PROVIDED BY OTHER TRADES.
19. ACCESS PANELS IN NON ACCESSIBLE SUSPENDED CEILINGS SHALL BE PROVIDED FOR
ALL VALVES, TRAPS, DAMPERS, CLEANOUTS, FLOW METERS, CONTROLS, ETC.
COORDINATE SIZES AND LOCATIONS WITH OTHER TRADES.
20. TOTAL STATIC PRESSURE NOTED IN THE SCHEDULES INCLUDES DUCT SYSTEM,
TERMINAL UNITS, FILTERS, COILS, ETC.
21. FOR TYPICAL STEAM, WATER AND REFRIGERANT PIPING CONNECTIONS TO EQUIPMENT,
SEE STANDARD DETAILS AND PIPING SCHEMATICS.
22. DIFFUSER SIZES SHOWN ON FLOOR PLANS ARE NECK SIZES. REGISTER AND GRILLE
SIZES SHOWN ARE FACE SIZES.
23. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS FOR EXACT LOCATION OF
CEILING DIFFUSERS, REGISTERS, AND GRILLES.
24. WATER PIPE CONNECTIONS TO AIR HEATING AND COOLING COILS SHALL BE MADE TO
PROVIDE COUNTER FLOW BETWEEN WATER AND AIR.
25. WALL TYPE EXHAUST REGISTERS NOTED AS "BR" ON DRAWINGS ARE TO BE INSTALLED
WITH BOTTOM OF REGISTERS SEVEN INCHES ABOVE FINISHED FLOOR.
26. WHERE DUCTS OR PIPES ARE REMOVED THRU WALL/FLOOR/ROOF THAT IS TO REMAIN,
PATCH WALL/FLOOR/ROOF OPENING TO MATCH EXISTING WHERE OPENING IS NOT
RE-USED.
27. ALL PRESSURES LISTED ARE GAGE PRESSURE UNLESS OTHERWISE NOTED.
28. ALL CUTTING AND PATCHING REQUIRED FOR THIS PROJECT SHALL BE INCLUDED IN THE
CONTRACT. REFINISH ANY SURFACE DISTURBED UNDER THIS WORK TO MATCH EXISTING.
29. IN GENERAL, KEEP DUCT AND PIPING MAINS NEXT TO UNDERSIDE OF STRUCTURE.
30. ANY REMOVED EQUIPMENT SHALL BE TURNED OVER TO THE VA. ITEMS NOT DESIRED BY
THE VA SHALL BE REMOVED FROM THE PREMISES AND DISPOSED OF PROPERLY BY THE
CONTRACTOR.
31. THE CONTRACT DRAWINGS ARE NOT INTENDED TO SHOW EVERY VERTICAL OR
HORIZONTAL OFFSET WHICH MAY BE NECESSARY TO COMPLETE THE SYSTEMS.
COORDINATE WORK IN ADVANCE WITH ALL OTHER TRADES AND REPORT IMMEDIATELY
ANY DIFFICULTIES WHICH CAN BE ANTICIPATED.
32. FIELD VERIFY EXISTING CONDITIONS, INCLUDING DUCT, PIPE AND EQUIPMENT SIZES,
SERVICES AND LOCATIONS PRIOR TO PERFORMING WORK.
33. HEPA FILTERED EXHAUST IS REQUIRED TO MAINTAIN A MINIMUM OF 0.01" W.G. NEGATIVE
PRESSURE IN CONSTRUCTION AREAS. COORDINATE WITH COR.
34. ALL ABANDONED EXTRANEOUS PIPING, DUCTWORK, SUPPORTS, CONTROLS, ETC. SHALL
BE REMOVED.
35. TERMINATE PIPING AND DUCTWORK BELOW FLOORS, ABOVE CEILINGS, ETC., IN
CONCEALED SPACES. ALL CUTTING AND PATCHING SHALL MATCH EXISTING FINISHES.
36. WHERE CONTROL DEVICES ARE REMOVED, PNEUMATIC LINES SHALL BE REMOVED BACK
TO MAIN AND CAPPED; AND CONTROL WIRING AND CONDUIT SHALL BE REMOVED BACK TO
SOURCE.
45. PERFORM AN AIR SURVEY OF ALL EXISTING DUCTED SYSTEMS PRIOR OF ANY REMOVAL WORK
DRAWINGS FOR DETAILS OF BUILDING CONSTRUCTION TO ENSURE SPACE AND
SATISFACTORY ARRANGEMENT FOR THEIR WORK. THE VARIOUS DRAWINGS COMPRISING
THE SET ARE INTERDEPENDENT AND MUST BE USED JOINTLY AT ALL TIMES. REFER TO
THE GENERAL REQUIREMENTS OF THE CONTRACT. THE NOTES AND SYMBOLS INDICATED
ON THE DRAWINGS ARE FOR THE GUIDANCE OF ALL TRADES INVOLVED IN THE PROJECT
AND MUST BE FOLLOWED TO EXECUTE THE WORK AS INTENDED. IF DISCREPANCIES
OCCUR, CONTACT THE COR THRU THE CONTRACTING OFFICER FOR CLARIFICATION
BEFORE PROCEEDING.
ACCESS DOORAD
FLOW ELEMENT AND TEMPERATURE ELEMENT FORFE TE
BTUH METER
TAKING PLACE. SUBMIT FINAL REPORT TO THE COR AND ENGINEER.
46. COORDINATE SEQUENCING OF ALL WORK CROSSING PHASING BOUNDRIES WITH COR WELL
IN ADVANCE.
S-B
ABBREVIATIONSCONTROLSPIPING SYMBOLSDRAWING SYMBOLS
DUCTWORK SYMBOLS
GENERAL NOTES
GENERAL
VALVES
GENERAL NOTES
ABBREVIATIONS
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC.
905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
PROJECT NO. STATE COA FIRM NO.2018-05164 01528
/3
/2
:3
:1
P
M
M001
LEGEND, ABBREVIATIONS & INDEX
OF DRAWINGS
CORRECT
INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OHIO 45428
552-19-102
PHIL WEST, COR
May 2nd, 2025 GSE WJS
BID DOCUMENTS
FULLY SPRINKLERED
INDEX OF DRAWINGS - MECHANICAL
Sheet Number Sheet Name
M001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
MD100 BASEMENT FLOOR PLAN - REMOVALS
MD101 FIRST FLOOR PLAN - REMOVALS
MD102 SECOND FLOOR PLAN - REMOVALS
MD103 ATTIC FLOOR PLAN - REMOVALS
MH100 BASEMENT FLOOR PLAN - DUCTWORK
MH101 FIRST FLOOR PLAN - DUCTWORK
MH102 SECOND FLOOR PLAN - DUCTWORK
MH103 ATTIC FLOOR PLAN - DUCTWORK
MP100 BASEMENT FLOOR PLAN - PIPING
MP101 FIRST FLOOR PLAN - PIPING
MP102 SECOND FLOOR PLAN - PIPING
MP103 ATTIC FLOOR PLAN - PIPING
M401 ENLARGED PLANS
M501 DETAILS
M502 DETAILS
M503 DETAILS
M504 HYDRONIC PIPING SCHEMATICS
M505 STEAM PIPING SCHEMATIC
M601 SCHEDULES
M602 SCHEDULES
M603 SCHEDULES
M701 CONTROLS AND AUTOMATION
M702 CONTROLS AND AUTOMATION
DN
AHU
CWR/CWS UP AND
CONDENSATE DRAIN.
18x12
12x8
10x88x8 12x8 10x8 x1
24x12
9 9
CWR/CWS UP AND
CONDENSATE DRAIN.
CWR/CWS UP AND
CONDENSATE DRAIN.
CWR/CWS UP AND
CONDENSATE DRAIN.
CWR/CWS UP.
PHASE 1
8 9
PHASE 3PHASE 4
P: 937-224-0861 www.heapy.com
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
GUIDON DESIGN INC.
905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204
317.800.6388 | WWW.GUIDONDESIGN.COM
SUSTAINABLE ARCHITECTURE + ENGINEERING
PROJECT LEAD
Architect, Structural Engineer, Civil Engineer
PROJECT NO. STATE COA FIRM NO.2018-05164 01528
/3
/2
:3
:2
P
M
MD100
BASEMENT FLOOR PLAN -
REMOVALS
CORRECT
INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OHIO 45428
552-19-102
PHIL WEST, COR
May 2nd, 2025 GSE WJS
BID DOCUMENTS
FULLY SPRINKLERED
GENERAL NOTES
PLAN NOTES
A. REFER TO SHEET M001 FOR LEGEND, ABBREVIATIONS, INDEX OF DRAWINGS,
AND ADDITIONAL GENERAL NOTES.
1. EXISTING DUCTWORK TO REMAIN.
2. EXISTING STEAM PIPING UP THRU BUILDING TO REMAIN.
3. REMOVE EXISTING DUCTWORK AND ASSOCIATED ACCESSORIES, SUPPORTS, ETC.
4. REMOVE EXISTING DUCT TO THIS POINT FOR RECONNECTION IN NEW WORK.
5. REMOVE EXISTING AIR HANDLING UNIT AND ASSOCIATED DUCTWORK, PIPING,
CONTROLS, ETC.
6. REMOVE EXISTING PIPING AND ASSOCIATED ACCESSORIES, SUPPORTS, ETC. AFTER
NEW CHW AND HHW SYSTEMS ARE OPERATIONAL.
7. REMOVE ALL EXISTING CHILLED WATER SYSTEM COMPONENTS AFTER THE NEW
CHILLERS ARE INSTALLED AND OPERATIONAL.
8. REMOVE EXISTING DUCTWORK TO FLOOR PENETRATION. EXISTING AIR DEVICE ON
FIRST FLOOR TO REMAIN.
9. CAP UNDER FLOOR.
10. REMOVE EXISTING PIPING TO THIS POINT AND CAP AFTER NEW CHW AND HHW
SYSTEMS ARE OPERATIONAL.
11. REMOVE EXISTING AIR HANDLING UNIT STRUCTURAL SUPPORTS. AHU LOCATED ON
FIRST FLOOR.
SCALE: 1/8" = 1'-0"MD100
1 BASEMENT-HVAC-REMOVALS
N
ALL EXISTING STEAM AND CHILLED
WATER PIPING SHALL BE REMOVED
FROM THE BASEMENT/CRAWL
SPACE. THIS REMOVAL WORK SHALL
TAKE PLACE AFTER THE NEW
CHILLED WATER AND HOT WATER
SYSTEMS ARE OPERATIONAL. SOME
OF THE PIPING IS SHOWN ON THIS
FLOOR PLAN.
| 2018-05164_Div21_Dwgs |
| 2018-05164_Div23_Dwgs |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
This is the start of the file's text. The full file is on GovTribe.