These technical drawings are part of a Department of Veterans Affairs (VA) infrastructure improvement project for the Dayton VAMC (Medical Center), specifically Project 552-19-102 for Correcting Infrastructure Deficiencies in Building 408. The drawings include detailed mechanical, fire suppression, and plumbing system plans across multiple floors, showing new work for sanitary waste and vent systems, fire suppression sprinkler installations, and HVAC system modifications. The documents are prepared by Heapy Engineering and Guidon Design Inc., with a project number 2018-05164, and are dated April 2025.

The technical drawings provide comprehensive diagrams for basement, first floor, second floor, and attic levels, detailing specific infrastructure updates including sanitary waste systems with drain symbols, sewage ejector specifications, trap primers, fire suppression sprinkler layouts, and HVAC system removals and installations. The drawings include precise technical annotations, equipment schedules, piping and ductwork symbols, and general notes outlining installation requirements, coordination protocols, and compliance standards for the renovation project at the VA medical facility.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FD1

FD1

FD1

SE1

2"

2"

2"

3"

3"

3"

4"

4"

SAN

SAN

SAN

SAN

SAN

S A

N

VV

1.5"

2"

FIRST FLOOR

SECOND FLOOR

ATTIC

3" VTR

3"

2"

2"

2"

V V

CO

CO

CO

CO

2"

FLOOR

2"

1.5" VENT

2"

PDCO

1 BASIN (36" DIA x 60" HEIGHT)

2 ANTI-FLOTATION FLANGE

3 BASIN LID - BOLTED & GASKETED.

4 6" SAND BED. LEVEL BASIN.

5 INLET PIPE. SEE FLOOR PLAN FOR NUMBER

AND INVERT(S).

6 DUPLEX CONTROL PANEL. MOUNT 60" AFF TO

TOP OF PANEL.

7 CONNECT TO TOP OF GRAVITY DRAINAGE PIPE.

8 INSTALL PIPE ACCESSORIES IN HORIZONTAL

PORTION OF PIPING.

9 POWER WIRING IN CONDUIT TO CONTROL

PANEL.

10 PUMP

CAPACITY: 15 GPM @ 15 FT. HD.

ELECTRICAL: 230V/ 1PH/ 60 HZ/ 1/2HP

11 CONCRETE FILL. 25 CU FT. MINIMUM EVENLY

DISTRIBUTED AROUND BASIN.

12 PUMP REMOVAL RAIL SYSTEM.

CONTROL INVERTS (BELOW FINISHED FLOOR)

PUMPS OFF 54 IN

LEAD PUMP ON 44 IN

LAG PUMP ON 40 IN

HIGH LEVEL ALARM 36 IN

P D

P D

NOTESV

3"

TRAP PRIMER, WITH DISTRIBUTION

UNIT WHEN SERVING MULTIPLE

DRAINS. LOCATE ABOVE CEILING

IN FINISHED AREAS.

0.5''SUPPLY SHALL BE

OFF TOP OF MAIN

COLD WATER MAIN

T P

T P

WALL

FINISHED CEILING

WHERE APPLICABLE

FLOOR DRAINS

FLOOR

TP

PIPING TO FLOOR DRAINS

SHALL BE RUN BELOW FLOOR,

UNLESS NOTED OTHERWISE.

INSTALL PIPING CONCEALED

IN WALL IN FINISHED AREAS.

INSTALL PIPING TIGHT TO WALL

SURFACE IN UNFINISHED AREAS.

P: 937-224-0861 www.heapy.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

GUIDON DESIGN INC.

905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204

317.800.6388 | WWW.GUIDONDESIGN.COM

SUSTAINABLE ARCHITECTURE + ENGINEERING

PROJECT LEAD

Architect, Structural Engineer, Civil Engineer

PROJECT NO. STATE COA FIRM NO.2018-05164 01528

/2

/2

:4

:2

P

M

P501

DETAILS AND SCHEDULES CORRECT

INFRASTRUCTURE

DEFICIENCIES, B408

DAYTON, OHIO 45428

552-19-102

PHIL WEST, COR

May 2nd, 2025 EWL KMB

BID DOCUMENTS

FULLY SPRINKLERED

DRAIN SCHEDULE

SYMBOL DESCRIPTION

BODY STRAINER / GRATE TOP FINISH

C.I. S.S. C.R. BRASS RD. SQ. ADJUST. FLAT RECESS DOME

NICKLE

BRONZE C.I. C.R. S.S.

FD1 3" MEDIUM DUTY/ DOUBLE DRAINAGE/ VANDAL RESISTANT (TYPE C)/ TRAP PRIMER

CONNECTION

GENERAL NOTES:

A. PROVIDE ROUGH-IN.

B. INSTALL ALL "LOOSE" COMPONENTS.

C. PROVIDE ALL NECESSARY SUPPLIES, STOPS, TRAPS,

FIX. DRAINS, CONTINUOUS WASTE, & ALL INDIRECT WASTE.

D. MAKE ALL FINAL CONNECTIONS.

E. THE P.C. SHALL CONFIRM ALL PIPING CONNECTIONS &

SIZES BEFORE ROUGH-IN.

EQUIPMENT SCHEDULE

MARK DESCRIPTION

SUPPLY WASTE & VENT WASTE SYSTEM

REFER TO

EQUIPMENT

SCHEDULE

NOTES C

O

L D

W A

T E

R

H O

T W

A T

E R

R O

D

I W

A T

E R

T E

M P

E R

E D

W A

T E

R

L A

B A

IR

F

IX

T U

R E

O U

T L

E T

T R

A P

F

IX

T U

R E

D R

A

IN

W A

S T

E -M

IN

IM

U M

V E

N T

-M

IN

IM

U

M

I N

D

IR

E C

T

A

IR

G A

P

A

IR

B R

E A

K

T O

F L

O O

R D

R A

IN

T O

S T

A N

D P

IP

E

S A

N

IT

A R

Y

K

IT

C H

E N

W A

S T

E

A C

ID

W

A S

T E

SE1 DUPLEX SEWAGE EJECTOR/ 230V 1PH 60 HZ/ 1/2HP/ 15GPM

@ 15 FT HD

2" ●

NOT TO SCALEP501

A SANITARY WASTE & VENT DIAGRAM

PIPE SPACE

NOT TO SCALEP501

B SEWAGE EJECTOR (SE1)

REFER TO DETAIL "B" / THIS

SHEET FOR CONTINUATION

NOT TO SCALEP501

C TRAP PRIMER

Revisions: Date:

A1

P1 P1OR

A1

OH

P2

B

P2

GENERAL FLOOR PLAN NOTES

RISER OR STACK NUMBER

DETAIL: B = DETAIL DESIGNATION

P2 = SHEET WHERE DETAIL IS LOCATED

FIRE SUPPRESSION HAZARD CLASSIFICATION AND HAZARD

CLASSIFICATION GROUP

SECTION: 1 = SECTION DESIGNATION

P2 = SHEET WHERE DETAIL IS LOCATED

EQUIPMENT REFERENCE. LETTER DESIGNATION VARIES.

REFER TO SCHEDULES.

EQUIPMENT, DEVICE, OR PLUMBING FIXTURE MARK. LETTER

DESIGNATIONS REFER TO SCHEDULES.

CONNECT TO EXISTING

PLAN NOTE. APPLIES ONLY TO THE SHEET WHICH IT IS SHOWN

UNLESS NOTED OTHERWISE.

DETAIL NOTE. APPLIES ONLY TO THE ASSOCIATED DETAIL.

"UP TO" SYMBOL (ITEM ON FLOOR ABOVE)

10" 10"

ELEV: 8' - 0"ELEV: 8' - 0"

TOE: 3' - 0"

BOE: 0' - 6"

APPROXIMATE DIMENSION ABOVE FINISHED FLOOR TO TOP OR

BOTTOM OF EQUIPMENT, UNLESS NOTED OTHERWISE

APPROXIMATE DIMENSION ABOVE FINISHED FLOOR TO

CENTERLINE OF PIPE, UNLESS NOTED OTHERWISE

FIRE SUPPRESSION SYMBOLS

DOUBLE LINE SINGLE LINE

CONCEALED PENDENT SPRINKLER

FS

PIV

S

FIRE HYDRANT

FLOW SWITCH

GATE VALVE OS&Y

INSTITUTIONAL PENDENT SPRINKLER

PENDENT SPRINKLER

POST INDICATOR VALVE

RECESSED PENDENT SPRINKLER

SIDE WALL SPRINKLER

SUPERVISED VALVE

UPRIGHT SPRINKLER

PIPING SYMBOLS

DOUBLE LINE SINGLE LINE

BOTTOM CONNECTION (45°)

BRANCH TEE CONNECTION (NOTE:

BULLHEAD TEE'S ARE NOT

PERMITTED)

DIRECTION OF PITCH

DROP

ELBOW DOWN

ELBOW UP

EXISTING PIPE TO BE REMOVED

EXISTING PIPE TO REMAIN

FLOW DIRECTION DESIGNATION

PUMP

RISE

TOP CONNECTION (45°)

TOP CONNECTION (90°)

BOTTOM CONNECTION (90°)

DD

RR

SPECIALTY GAS SYMBOLS

AIR OUTLET - LAB TYPE

VC

VC

CARBON DIOXIDE OUTLET - HOSPITAL TYPE

MEDICAL AIR OUTLET - HOSPITAL TYPE

MEDICAL VACUUM INLET - HOSPITAL TYPE

NITROGEN OUTLET - HOSPITAL TYPE

NITROUS OXIDE OUTLET - HOSPITAL TYPE

OXYGEN OUTLET - HOSPITAL TYPE

WAGD INLET - HOSPITAL TYPE

NATURAL GAS OUTLET - LAB TYPE

VACUUM OUTLET - LAB TYPE

VACUUM CLEANING STATION - WALL

VACUUM CLEANING STATION - FLOOR

PLUMBING AND FIRE SUPPRESSION

PIPING DESIGNATIONS

DOMESTIC COLD WATER

DOMESTIC HOT WATER

DOMESTIC HOT WATER RETURN

EXISTING PIPE TO REMAIN

EXISTING PIPE TO BE REMOVED

HOT WATER PIPE (140 DEGS. F.)

HOT WATER PIPE (180 DEGS. F.)

HOT WATER RETURN PIPE (140 DEGS. F.)

HOT WATER RETURN PIPE (180 DEGS. F.)

ARGON PIPE

COMPRESSED AIR PIPE

MEDICAL CARBON DIOXIDE PIPE

COMBINATION FIRE SUPPRESSION AND DOMESTIC

WATER SERVICE

DIESEL FUEL PIPE

SPRINKLER PIPE (DRY)

FIRE SUPPRESSION (STANDPIPE / SPRINKLER MAIN)

FIRE SERVICE

FUEL OIL FLOW LINE

FUEL OIL GAUGE LINE

FUEL OIL RETURN LINE

FUEL OIL SUPPLY LINE

NATURAL GAS PIPE

GARAGE DRAINAGE PIPE

GAS SERVICE

HYDROGEN PIPE

HELIUM PIPE

MEDICAL INSTRUMENT AIR PIPE

KITCHEN WASTE PIPE

LABORATORY COMPRESSED AIR PIPE

LABORATORY VENT PIPE

LABORATORY VACUUM PIPE

LABORATORY WASTE PIPE

MEDICAL NITROGEN PIPE

MEDICAL COMPRESSED AIR PIPE

MEDICAL-SURGICAL VACUUM PIPE

GASOLINE PIPE (NON-LEAD)

MEDICAL NITROUS OXIDE PIPE

NON-POTABLE

MEDICAL OXYGEN PIPE

(OVERFLOW) SECONDARY STORM DRAINAGE PIPE

PROPANE GAS PIPE

PUMP DISCHARGE PIPE

PRE-ACTION / DELUGE SPRINKLER PIPE

PURE WATER PIPE

SPRINKLER PIPE (WET)

SANITARY DRAINAGE PIPE

SOFT COLD WATER

SPRINKLER DRAIN PIPE

STORM DRAINAGE PIPE

FUEL TANK VENT PIPE

TRAP PRIMER DISCHARGE PIPE

TEMPERED WATER PIPE

SANITARY SEWER VENT

WASTE ANESTHESIA GAS DISPOSAL PIPE

WATER SERVICE

LV

140R

180R

AR

CA

CO2

CWS

DF

DS

F

FS

FOF

FOG

FOR

FOS

G

GD

GS

H2

HE

IA

IV

IW

LA

LV

LW

N2

MA

MV

NG

NO

NPW

O2

OD

P

PD

PS

PW

S

SAN

SCW

SD

STM

T

TP

TW

V

WAGD

WS

INDIRECT VENT PIPE

INDIRECT WASTE PIPE

K

CHECK VALVE

T

P

FOB

FOT

SHUTOFF VALVE (REFER TO SPECIFICATIONS

FOR REQUIRED TYPE BASED ON

APPLICATIONS)

CONCENTRIC PIPE REDUCER

ECCENTRIC PIPE REDUCER

PRESSURE GAUGE

TEMPERATURE GAUGE OR THERMOMETER

UNION

CLEANOUT

STRAINER

STRAINER WITH A BLOW DOWN VALVE AND

HOSE CONNECTION

DRAIN VALVE WITH HOSE END CONNECTION

AUTOMATIC FLOW CONTROLLER WITH P/T

PLUG IN AND OUT

EXPANSION JOINT

PRESSURE REGULATING VALVE

SAFETY RELIEF VALVE. PIPE DISCHARGE AIR

GAPPED TO FLOOR DRAIN UNLESS NOTED

OTHERWISE.

PRESSURE AND TEMPERATURE TEST PLUG

TRAP PRIMER

VACUUM GAUGE WITH STOP

CLEANOUT TO GRADE OR FINISHED FLOOR

END CAP

MIXING FAUCET

PLUG

HOSE BIB

WALL HYDRANT

PLUG VALVE

SHUTOFF VALVE AND BOX

SHUTOFF VALVE ON RISER

V

VB

TP

CO

COMBINATION SHUTOFF AND BALANCING

VALVE (REFER TO SPECIFICATIONS FOR

REQUIRED TYPE BASED ON APPLICATIONS)

BALL VALVE

BUTTERFLY VALVE

GATE VALVE

VALVES AND FITTINGS

DOUBLE LINE SINGLE LINE

SOLENOID VALVE

S

P/T PRESSURE AND TEMPERATURE SAFETY

RELIEF VALVE. PIPE DISCHARGE AIR GAPPED

TO FLOOR DRAIN UNLESS NOTED

OTHERWISE.

FIRE DEPARTMENT VALVE

WATER METERM

ACID VENT PIPEAV

ACID WASTE PIPEAW

ABBREVIATIONS

AAP - AREA ALARM PANEL (MEDICAL GAS)

AC - AIR COMPRESSOR OR AIR CONDITIONER

ACC - ACCESS

ACCU - AIR COOLED CONDENSING UNIT

AD - ACCESS DOOR OR AREA DRAIN

ADB - ACID DILUTION BASIN

ADJ - ADJUSTABLE

AFF - ABOVE FINISHED FLOOR

AFG - ABOVE FINISHED GRADE

ALT - ALTERNATE

AP - ACCESS PANEL

APPROX - APPROXIMATE

AR - AIR RECEIVER OR ARGON

ARCH - ARCHITECT OR ARCHITECTURAL

ASSY - ASSEMBLY

AV - ACID VENT

AW - ACID WASTE

BDD - BACK DRAFT DAMPER

BFP - BACKFLOW PREVENTER

BLDG - BUILDING

BOB - BOTTOM OF BEAM

BOD - BOTTOM OF DUCT

BOE - BOTTOM OF EQUIPMENT

BOF - BOTTOM OF FOOTING

BOG - BOTTOM OF GRILLE

BOP - BOTTOM OF PIPE

BOT - BOTTOM

BT - BATHTUB

BTU - BRITISH THERMAL UNIT

BTUH - BRITISH THERMAL UNIT PER HOUR

BTWN - BETWEEN

CA - COMPRESSED AIR

CB - CATCH BASIN

CBD - COUNTER BALANCED BACKDRAFT DAMPER

CFCI - CONTRACTOR FURNISHED CONTRACTOR

INSTALLED

CFM - CUBIC FEET PER MINUTE

CHS - CHILLED WATER SUPPLY

CHR - CHILLED WATER RETURN

CI - CAST IRON

CK - CLINICAL SINK

CLG - CEILING

CMU - CONCRETE MASONRY UNIT

CO - CLEAN OUT

CO2 - MEDICAL CARBON DIOXIDE

CONN - CONNECT OR CONNECTION

CONTR - CONTRACTOR

COR - CONTRACTING OFFICER'S REPRESENTATIVE

CORR - CORRIDOR

CS - CLINICAL SINK OR COLD SOFT WATER

CTR - CENTER

CU - COPPER

CW - COLD WATER

CWS - COMBINATION WATER SERVICE

OR CONDENSER WATER SUPPLY

CWR - CONDENSER WATER RETURN

D - DEPTH OR DRAIN LINE

DD - DECK DRAIN

DET - DETAIL

DF - DRINKING FOUNTAIN OR WATER COOLER

OR DIESEL FUEL

DFU - DRAINAGE FIXTURE UNIT

DI - DEIONIZED WATER

DIA - DIAMETER

DIM - DIMENSION

DN - DOWN

DS - DOWN SPOUT OR SPRINKLER (DRY)

DT - PERFORATED DRAIN TILE

DWG - DRAWING

EA - EACH

EC - ELECTRICAL CONTRACTOR (DIVISION 26)

EEW - EMERGENCY EYE WASH

EJ - EXPANSION JOINT

ELEC - ELECTRICAL

ELEV - ELEVATOR

EQ - EQUAL

EQUIP - EQUIPMENT

ET - EXPANSION TANK

ETR - EXISTING TO REMAIN

ES - EMERGENCY SHOWER

EQS - EQUIPMENT SUPPLIER

EWC - ELECTRICAL WATER COOLER

EXH - EXHAUST AIR

EXP - EXPANSION

EXT - EXTERIOR

EX - EXISTING

F - FIRE SUPPRESSION (STANDPIPE/SPRINKLER

MAIN)

FCE - FIRE CONTROL EQUIPMENT

FCO - FLOOR CLEANOUT

FD - FLOOR DRAIN

FDC - FIRE DEPARTMENT CONNECTION

FDV - FIRE DEPARTMENT VALVE

FF - FINISHED FLOOR ELEVATION

FHC - FIRE HOSE CABINET

FLR - FLOOR

FM - FORCE MAIN

FOB - FLAT ON BOTTOM

FOF - FUEL OIL FLOW

FOG - FUEL OIL GAUGE

FOR - FUEL OIL RETURN

FOS - FUEL OIL SUPPLY

FOT - FLAT ON TOP

FPM - FEET PER MINUTE

FR - FIRE RISER

FS - FLOOR SINK OR FIRE SERVICE

FSC - FIRE SUPPRESSION CONTRACTOR

(DIVISION 21)

FT - FEET

FTG - FOOTING

G - GAS OR NATURAL GAS

GA - GAUGE

GAL - GALLON

GALV - GALVANIZED

GC - GENERAL TRADES CONTRACTOR

GD - GARAGE DRAINAGE

GPM - GALLONS PER MINUTE

GS - GAS SERVICE

GW - GREASE WASTE

H2 - HYDROGEN

HB - HOSE BIBB

HC - HVAC CONTRACTOR (DIVISION 23)

HD - HUB DRAIN

HE - HELIUM

HG - REFRIGERANT HOT GAS

HP - HORSEPOWER OR HIGH POINT

HPC - HIGH PRESSURE CONDENSATE RETURN

HPS - HIGH PRESSURE STEAM SUPPLY

HPW - HIGH PURITY WATER

HPWR - HIGH PURITY WATER RETURN

HR - HOSE REEL

HT - HEAT TRACE

HTR - HEATER

HVAC - HEATING, VENTILATING, AND AIR

CONDITIONING

HW - HOT WATER

HWR - HEATING HOT WATER RETURN

HWS - HEATING HOT WATER SUPPLY

IA - MEDICAL INSTRUMENT AIR

ID - INSIDE DIAMETER

INV - INVERT ELEVATION

IN - INCHES

IV - INDIRECT VENT

IW - INDIRECT WASTE

JS - JANITOR SINK

K - KITCHEN WASTE

KEC - KITCHEN EQUIPMENT CONTRACTOR

L - LENGTH

LA - LABORATORY COMPRESSED AIR

LAV - LAVATORY

LBS - POUNDS

LCW - LABORATORY COLD WATER

LEC - LABORATORY EQUIPMENT CONTRACTOR

LHW - LABORATORY HOT WATER

LHWR - LABORATORY HOT WATER RETURN

LPC - LOW PRESSURE CONDENSATE RETURN

LPS - LOW PRESSURE STEAM SUPPLY

LV - LABORATORY VACUUM OR LABORATORY

VENT

LW - LABORATORY WASTE

MA - MEDICAL COMPRESSED AIR

MAP - MASTER ALARM PANEL (MEDICAL GAS)

MAX - MAXIMUM

MB - MOP BASIN

MC - MECHANICAL CONTRACTOR (DIVISION 23)

MEZZ - MEZZANINE

MFR - MANUFACTURER

MH - MANHOLE

MIN - MINIMUM OR MINUTE

MISC - MISCELLANEOUS

MTD - MOUNTED

MTG - MOUNTING

MPC - MEDIUM PRESSURE CONDENSATE RETURN

MPS - MEDIUM PRESSURE STEAM SUPPLY

MU - WATER MAKE-UP

MV - MEDICAL SURGICAL VACUUM

N2 - MEDICAL NITROGEN

N/C - NORMALLY CLOSED

NG - GASOLINE (NON-LEAD)

NIC - NOT IN CONTRACT

N/O - NORMALLY OPEN

NO - MEDICAL NITROUS OXIDE

NOM - NOMINAL

NPW - NON-POTABLE WATER

NPT - NATIONAL PIPE THREAD

NTS - NOT TO SCALE

02 - MEDICAL OXYGEN

OA - OUTDOOR AIR

OD - OUTSIDE DIAMETER OR OVERFLOW DRAIN

OFCI - OWNER FURNISHED CONTRACTOR

INSTALLED

OFOI - OWNER FURNISHED OWNER INSTALLED

P - PROPANE GAS

PC - PLUMBING CONTRACTOR (DIVISION 22)

OR PUMPED CONDENSATE RETURN

PD - PUMP DISCHARGE OR PARAPET DRAIN

PIV - POST INDICATOR VALVE

PLBG - PLUMBING

PS - PRE-ACTION/DELUGE SPRINKLER

PRESS - PRESSURE

PRV - PRESSURE REGULATING VALVE

PSF - POUNDS PER SQUARE FOOT

PSI - POUNDS PER SQUARE INCH

PSV - PRESSURE SUSTAINING VALVE

PSIG - POUNDS PER SQUARE INCH GAUGE

PW - PURE WATER

RA - RETURN AIR

RAD - RADIUS

RCP - REINFORCED CONCRETE PIPE

RD - ROOF DRAIN

REC - RECESSED

REQD - REQUIRED

RI - ROUGH IN

RL - REFRIGERANT LIQUID

ROS - REVERSE OSMOSIS WATER SUPPLY

ROR - REVERSE OSMOSIS WATER RETURN

RPM - REVOLUTIONS PER MINUTE

RS - REFRIGERANT SUCTION

RV - RELIEF VALVE

S - SPRINKLER (WET)

SA - SHOCK ARRESTOR OR SUPPLY AIR

SAN - SANITARY OR SANITARY DRAIN

SCH - SCHEDULE

SCW - SOFT COLD WATER

SD - SPRINKLER DRAIN OR SUBSOIL DRAIN

SH - SHOWER

SHT - SHEET

SK - SINK

SPEC - SPECIFICATIONS

SQ - SQUARE

SR - SUPPLY RISER

SS - SANITARY STACK (SOIL OR WASTE) OR

STAINLESS STEEL

STD - STANDARD

STM - STORM OR STORM DRAINAGE

STRUC - STRUCTURAL OR STRUCTURE

SUC - SITE UTILITY CONTRACTOR

T - FUEL TANK VENT

TD - TRENCH DRAIN

TEMP - TEMPERATURE

TOB - TOP OF BEAM

TOD - TOP OF DUCT

TOE - TOP OF EQUIPMENT

TOF - TOP OF FOOTING

TOJ - TOP OF JOIST

TOP - TOP OF PIPE

TOS - TOP OF SLAB OR TOP OF STEEL

TF - TRAP FILLER

TP - TRAP PRIMER OR TRAP PRIMER

DISCHARGE

TW - TEMPERED WATER

TYP - TYPICAL

UR - URINAL

UNO - UNLESS NOTED OTHERWISE

V - VENT OR SANITARY SEWER VENT

VAC - VACUUM

VC - VACUUM CLEANING

VCV - VACUUM CLEANING VALVE

VE - VACUUM EXHAUST

VEL - VELOCITY

VIB - VALVE IN BOX

VOL - VOLUME

VP - VACUUM PUMP

VS - VENT STACK

VTR - VENT THROUGH ROOF

VR - VENT RISER

W/ - WITH

W/O - WITHOUT

W - WASTE

WAGD - WASTE ANESTHESIA GAS DISPOSAL

WC - WATER CLOSET

WCO - WALL CLEANOUT

WH - WALL HYDRANT OR WATER HEATER

WIV - WALL INDICATOR VALVE

WS - WATER SERVICE

YCO - YARD CLEANOUT

ZVC - ZONE VALVE CABINET

PIPE RISER

NOTE:

ALL SYMBOLS OR ABBREVIATIONS MIGHT NOT

NECESSARILY BE USED ON THIS PROJECT.

FIRE SUPPRESSION DESIGN NOTES

A PROVIDE A COMPLETE FIRE SUPPRESSION SPRINKLER SYSTEM IN THE

RENOVATED AREA.

B COORDINATE WORK WITH VAMC, PHASING PLAN AND OTHER TRADES. OFFSET

AND/OR RELOCATE EXISTING SERVICES TO ACCOMMODATE NEW WORK OF

OTHER TRADES.

C DESIGN SERVICES SHALL FOLLOW ALL VA STANDARD DESIGN PRACTICES,

DETAILS, SPECIFICATIONS AND SITE SPECIFIC COR REQUIREMENTS AS WELL

AS WORK SHOWN ON THESE DOCUMENTS. ALL DEVIATIONS FROM

AFOREMENTIONED REQUIREMENTS SHALL BE APPROVED BY THE COR.

D VERIFY THAT THERE IS ADEQUATE SPACE TO INSTALL ALL NEW PIPING

REQUIRED TO COMPLETED THIS WORK.

E ALL SPRINKLER PIPING IS LOCATED ABOVE THE CEILING (AT THE BOTTOM OF

STRUCTURE IN EXPOSED STRUCTURAL AREAS) UNLESS OTHERWISE

INDICATED.

F THE BASIS OF DESIGN OF SPACING AND SIZING FOR THE COMPLETE FIRE

SUPPRESSION SPRINKLER SYSTEM SHALL BE FOR A WET/DRY PIPE SYSTEM

HYDRAULICALLY CALCULATED FOR A :

1 LIGHT HAZARD AREA LIMITED TO A MAXIMUM OF 225 SQ. FT. PER

SPRINKLER WITH THE DENSITY OF 0.10 GPM/ SQ. FT. OVER THE MOST

REMOTE 1500 SQ. FT. PROVIDE AN ADDITION OF 100 GPM HOSE

ALLOWANCE.

2 ALL MECHANICAL, ELECTRICAL AND SIMILAR SPACE AREAS SHALL BE

ORDINARY HAZARD (GROUP 1) LIMITED TO A MAXIMUM OF 130 SQ. FT. PER

SPRINKLER WITH A DENSITY OF 0.15 GPM/ SQ. FT. PROVIDE AN ADDITION

OF 250 GPM HOSE ALLOWANCE.

3 ALL STORAGE, TRASH, FILE STORAGE AND SIMILAR SPACE AREAS SHALL

BE ORDINARY HAZARD (GROUP 2) LIMITED TO A MAXIMUM OF 130 SQ. FT.

PER SPRINKLER WITH A DENSITY OF 0.20 GPM/ SQ. FT. PROVIDE AN

ADDITION OF 250 GPM HOSE ALLOWANCE.

G PROVIDE SPRINKLER LOCATIONS AND RELATED PIPING.

H THE ENTIRE SPRINKLER SYSTEM SHALL CONFORM TO VAMC, LOCAL, STATE

AND NFPA STANDARD, RULES AND REGULATIONS.

I CAREFULLY COORDINATE THE LOCATION OF ALL SPRINKLERS AND PIPING

WITH ALL OTHER TRADES AND THE ARCHITECT.

J VERIFY THE LOCATION OF ALL LIGHTING FIXTURES AND AIR DEVICES BEFORE

INSTALLATION OF SPRINKLERS.

K PROVIDE SPRINKLER PIPING LAYOUT AND SIZING.

L ALL SPRINKLER LOCATIONS MUST BE COORDINATED WITH ALL EQUIPMENT

KINDRED TO OTHER TRADES. SPRINKLER LOCATIONS MUST BE APPROVED BY

THE ARCHITECT BEFORE WORK COMMENCES. REFER TO THE ARCHITECTURAL

AND REFLECTIVE CEILING PLANS FOR ADDITIONAL INFORMATION ON ALL

CEILING TYPES, HEIGHTS AND OTHER ARCHITECTURAL FEATURES.

M MAKE NECESSARY FLOW TESTS, LAYOUT SYSTEMS, OBTAIN APPROVALS

FROM THE AUTHORITIES HAVING JURISDICTION PRIOR TO BEGINNING ANY

FABRICATION OR INSTALLATION WORK.

N SPRINKLER PIPING SHALL BE 1" MINIMUM SIZE.

O SPRINKLERS (UNLESS OTHERWISE NOTED):

EXPOSED AREAS - UPRIGHT OR PENDENT TYPE - STANDARD BRASS

CEILING AREAS - RECESS PENDENT TYPE

ALL SPRINKLERS SHALL BE UL LISTED AND FM APPROVED.

P SPRINKLERS SHALL BE "QUICK RESPONSE" TYPE IN ALL AREAS EXCEPT HIGH

TEMPERATURE AREAS.

Q ALL PENDENT TYPE SPRINKLERS LOCATED IN SUSPENDED CEILING TILE

AREAS SHALL BE LOCATED IN THE CENTER OF THE CEILING TILE.

R ANNULAR SPACE AT PIPE AND OTHER SIMILAR PENETRATION OF FIRE RATED

ASSEMBLIES SHALL BE FIRESTOPPED. REFER TO SPECIFICATION SECTION

07 84 00 FIRESTOPPING. REFER TO ARCHITECTURAL DRAWINGS FOR

CONSTRUCTION, LAYOUT AND FIRE RATING OF FLOORS, WALLS, PARTITIONS

AND OTHER BUILDING ELEMENTS.

S A FLOW TEST IS REQUIRED. REFER TO SPECIFICATION SECTION 21 13 13 FOR

FLOW TEST INFORMATION.

T ALL SPRINKLER ZONES SHALL MATCH SMOKE COMPARTMENTS.

U REFER TO ARCHITECTURAL DRAWINGS FOR INFORMATION ON SMOKE

COMPARTMENTS, SMOKE PARTITIONS AND FIRE BARRIERS.

V PHASING: REFER TO ARCHITECTURAL DRAWINGS FOR AN OUTLINE OF

PROJECT PHASING. ADDITIONAL NOTES DESCRIBING PHASING DETAILS MAY

BE INCLUDED THROUGHOUT THIS DRAWING SET.

W BID ITEMS: REFER TO ARCHITECTURAL DRAWINGS AND SPECIFICATION

SECTION 01 00 00 FOR AN OUTLINE OF BID ITEMS. ADDITIONAL NOTES

DESCRIBING BID ITEM DETAILS MAY BE INCLUDED THROUGHOUT THIS

DRAWING SET.

X SPRINKLER SYSTEM PIPING AND FITTINGS SHALL BE IN ACCORDANCE WITH

NFPA 13:

1 PIPING SIZES 2 INCHES AND SMALLER SHALL BE BLACK STEEL SCHEDULE

40 WITH THREADED END CONNECTIONS.

2 PIPING SIZES 2.5 INCHES AND LARGER SHALL BE BLACK STEEL SCHEDULE

10 WITH GROOVED CONNECTIONS. GROOVES IN SCHEDULE 10 PIPING

SHALL BE ROLLED GROOVED ONLY.

P: 937-224-0861 www.heapy.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

GUIDON DESIGN INC.

905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204

317.800.6388 | WWW.GUIDONDESIGN.COM

SUSTAINABLE ARCHITECTURE + ENGINEERING

PROJECT LEAD

Architect, Structural Engineer, Civil Engineer

PROJECT NO. STATE COA FIRM NO.2018-05164 01528

/2

/2

:4

:1

P

M

FX001

LEGEND, ABBREVIATIONS & INDEX

OF DRAWINGS

CORRECT

INFRASTRUCTURE

DEFICIENCIES, B408

DAYTON, OHIO 45428

552-19-102

PHIL WEST, COR

May 2nd, 2025 EWL KMB

BID DOCUMENTS

FULLY SPRINKLERED

INDEX OF DRAWINGS - FIRE SUPPRESSION

Sheet Number Sheet Name

FX001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS

FX100 FIRE SUPPRESSION PLANS

S

3 - AIR COMPRESSOR

TO FDC

Storage

Unexcavated

OH

100m

OFFICE

100g

OFFICE

100n

OFFICE

OPEN

OFFICE

100h

OFFICE

103C

CONFERENCE

OFFICE

103D

OFFICE

103A

OFFICE

OFFICE

TELE

PHARMACY

MENS

103B

COMM.

Room

101C

OFFICE

ACQUISITION

CHAPLAIN

101D

OFFICE

101A

OFFICE

KITCHEN

106k

OFFICE

106l

OFFICE

106h

OFFICE

106g

OFFICE

DSS SUITE

106e

OFFICE

106d

STORAGE

106a

OFFICE

106j

OFFICE

106f

OFFICE

106c

COPIER

106b

OFFICE

100d

OFFICE

100c

OFFICE

100k

OFFICE

100j

OFFICE

100l

OFFICE

WOMENS

107f

CONFERENCE

107g

OFFICE

107a

OFFICE

107c

OFC

107d

OFC

107e

OFC

107b

OFC

SUITE

109C

OFFICE

203E

CONFERENCE

ROOM

TOILET

TOILET

205B

NNU

OFFICE

F S

DSS

EXISTING DRY VALVE

NEW SUPERVISED

VALVE

6"

6"

6"

6"

NEW 6-INCH DOUBLE CHECK

DETECTOR ASSEMBLY WITH

SUPERVISED VALVES.

NEW CHECK VALVECONT'D TO FDC

CONT'D TO WET-

PIPE SYSTEM

CONT'D TO DRY-

PIPE SYSTEMEXISTING FIRE SERVICE ENTRANCE

P: 937-224-0861 www.heapy.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

GUIDON DESIGN INC.

905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204

317.800.6388 | WWW.GUIDONDESIGN.COM

SUSTAINABLE ARCHITECTURE + ENGINEERING

PROJECT LEAD

Architect, Structural Engineer, Civil Engineer

PROJECT NO. STATE COA FIRM NO.2018-05164 01528

/2

/2

:4

:2

P

M

FX100

FIRE SUPPRESSION PLANS CORRECT

INFRASTRUCTURE

DEFICIENCIES, B408

DAYTON, OHIO 45428

552-19-102

PHIL WEST, COR

May 2nd, 2025 EWL KMB

BID DOCUMENTS

FULLY SPRINKLERED

SCALE: 1/16" = 1'-0"FX100

1 BASEMENT - FIRE SUPPRESSION - NEW WORK

SCALE: 1/16" = 1'-0"FX100

2 FIRST FLOOR - FIRE SUPPRESSION - NEW WORK

SCALE: 1/16" = 1'-0"FX100

3 SECOND FLOOR - FIRE SUPPRESSION - NEW WORK

SCALE: 1/16" = 1'-0"FX100

4 ATTIC - FIRE SUPPRESSION - NEW WORK

GENERAL NOTES

A REFER TO SHEET FX001 FOR LEGEND AND GENERAL NOTES.

B EXISTING CORRIDORS OR ROOMS TO REMAIN OPERATIONAL

AT ALL TIMES DURING BUSINESS HOURS. AUTOMATIC

SPRINKLER SYSTEM SHALL BE MAINTAINED IN FULLY

OPERATIONAL CONDITION (PER NFPA 241, SPRINKLER

SYSTEM(S) WILL BE OPERATIONAL, BUT IMPAIRED WHILE

CEILINGS ARE REMOVED). SPRINKLER SYSTEM MAY BE TAKEN

OFF-LINE FOR UP TO 4 HOURS AS REQUIRED TO MAKE

MODIFICATIONS/ CONNECTIONS TO ACCOMMODATE PROJECT

PHASING. COORDINATE WORK WITH COR.

PLAN NOTES

1 LIMITS OF AREA REQUIRING CEILING REMOVAL AND

MODIFICATIONS TO EXISTING SPRINKLER SYSTEM.

MODIFICATIONS INCLUDE, BUT ARE NOT LIMITED TO,

REPLACEMENT OF SPRINKLERS AND BRANCH PIPING TO

CONFORM TO NEW MECHANICAL EQUIPMENT, DUCTWORK

AND PIPING AND ELECTRICAL EQUIPMENT AND COMPONENTS.

EXISTING PIPING SHALL BE RE-USED AS MUCH AS POSSIBLE.

2 NEW 6-INCH ASSE 1015 LISTED DOUBLE CHECK DETECTOR

ASSEMBLY. REVISE EXISTING FIRE SERVICE PIPING AND

ACCESSORIES FOR ADDITION OF NEW DOUBLE CHECK

DETECTOR ASSEMBLY.

3 EXISTING TO REMAIN.

N N

NN

NOT TO SCALEFX100

5 EXISTING FIRE SERVICE

NOT TO SCALEFX100

6 FIRE SERVICE

DUCT THERMOSTAT WITH AVERAGING ELEMENT

DUCT STATIC PRESSURE SENSOR

DUCT HUMIDITY SENSOR

ROOM SENSOR: TEMPERATURE, HUMIDITY

LENGTH IN DUCT WHEN SPACE PERMITS)

REMOTE BULB THERMOSTAT

ROOM CONTROL: THERMOSTAT, HUMIDISTAT

DIFFERENTIAL PRESSURE SWITCH

DUCT TEMPERATURE SENSOR WITH AVERAGING ELEMENT

SMOKE DETECTOR (SEE DIV. 28)

DUCT OR PIPE TEMP. SENSOR

DUCT OR PIPE THERMOSTAT (NOTE 1: PROVIDE 12" MIN.

CURRENT SENSING RELAY

AIR FOIL WHEEL (FAN)

AIR HANDLING UNIT

ANALOG INPUT

AIR PRESSURE DROP

ANALOG OUTPUT

AUTOMATIC TEMPERATURE CONTROLS

BACKWARD INCLINED WHEEL (FAN)

AIR FLOW MEASURING DEVICE

ABOVE FINISHED FLOOR

DIFFERENTIAL OR STATIC PRESSURE TRANSMITTER

COOLING COIL

CONVERTOR

CONVECTOR

CLEAN OUT

CEILING GRILLE

CENTRIFUGAL FAN

CEILING DIFFUSER

BOTTOM REGISTER (WALL TYPE)

BOTTOM GRILLE (WALL TYPE)

CEILING REGISTER

COLD WATER (POTABLE)

DIGITAL OUTPUT

DIGITAL INPUT

DIRECT DIGITAL CONTROLS

DRY BULB TEMPERATURE, DEG. F

AUTOMATIC CONTROL DAMPER

EXHAUST FAN

ENGINEERING CONTROL CENTER

DOUBLE WIDTH DOUBLE INLET (FAN)

DOOR UNDERCUT - REFER TO ARCHITECTURAL DRAWINGS

IN COORDINATING THE VARIOUS TRADES.)

LISTED SIZE OF DUCT. (TO BE USED AS AND AID IN

APPROXIMATE ELEVATION FROM FLOOR TO BOTTOM OF

MANUAL VOLUME DAMPER

U/C

STATIC TYPE 'B' FIRE DAMPER

BUTTERFLY VALVE

CIRCUIT SETTER

BALL VALVE

COMBINATION BALANCING/SHUT-OFF VALVE

MANUAL AIR VENT

AUTOMATIC FLOW CONTROL VALVE

TEST PLUG (PRESSURE/TEMPERATURE)

SAFETY VALVE OR PRESSURE RELIEF

PRESSURE REDUCING VALVE

STRAIGHT-THRU TWO-POSITION CONTROL VALVE

THREE-WAY MODULATING CONTROL VALVE

STRAIGHT-THRU MODULATING CONTROL VALVE

EX.

EF

EXISTING

DWDI

ECC

DI

DO

DB

DDC

D

Db

DECIBELS

BUILDING NO. WHERE EQUIPMENT IS LOCATED.

EQUIPMENT ABBREVIATION (SUPPLY FAN)

SUPPLY FAN NO.3 IN BUILDING NO.1

DRAWING NUMBER WHERE DRAWN

DRAWING NUMBER WHERE DRAWN

SUPPLY TOP REGISTER OR GRILLE (WALL TYPE)

RETURN DUCT (UP & DOWN)

VANED ELBOW & AIR SPLIT TYPE DUCT TAKE-OFF

EXHAUST OR RETURN TOP REGISTER OR GRILLE,

EXHAUST OR RETURN BOTTOM REGISTER OR GRILLE,

EXHAUST OR RETURN CEILING REGISTER OR GRILLE

SUPPLY DUCT (UP & DOWN)

INCLINED RISE, IN DIRECTION OF AIR FLOW

NEW DUCT - WIDTH X DEPTH

RECTANGULAR ELBOWS WITH VANES EVEN IF

VANED ELBOW (PROVIDE ALL SQUARE OR

INCLINED DROP, IN DIRECTION OF AIR FLOW

ACOUSTICAL DUCT LINING

STANDARD RADIUS ELBOW

R

10/8

FC

D

SYMBOL IS MISSING)

FLEXIBLE CONNECTION

UP

(WALL TYPE)

(WALL TYPE)

DN

UP

1-01

1-SF3

AIR HANDLING UNIT NUMBER

TERMINAL UNIT DESIGNATION

TYPICAL UNIT NO.

DN

SECTION LETTER

DETAIL NUMBER

ECCENTRIC REDUCER

DIRECTION OF FLOW

CAPPED OUTLET

SIDE CONNECTION

EXISTING WORK.

ACCESSORIES (SEE STANDARD DETAIL)

INVERTED BUCKET TRAP SET INCLUDING PIPING

POINT OF CONNECTION BETWEEN NEW AND

RISE OR DROP IN PIPE

BOTTOM CONNECTION, 45 DEG. OR 90 DEG.

TOP CONNECTION, 45 DEG. OR 90 DEG.

REDUCER OR INCREASER

DIRECTION OF PIPE PITCH (DOWN)

THERMOMETER

THERMOSTATIC TRAP

STRAINER

GATE VALVE

PRESSURE GAGE

CHECK VALVE

GLOBE VALVE

PIPING ACCESSORIES (SEE STANDARD DETAIL)

FLOAT AND THERMOSTATIC TRAP SET INCLUDING

GATE VALVE WITH 3/4" HOSE END ADAPTER

EXISTING PIPE TO BE REMOVED

DRAIN LINE

UNION

D

CONV

CW

CR

CO

CG

CF

CD

CC

C

BR

BIW

BG

ATC

AFW

AI

APD

AO

AHU

AFM

AFF

VENT LINE

HEATING HOT WATER RETURN

HEATING HOT WATER SUPPLY

LOW PRESSURE STEAM CONDENSATE RETURN

LOW PRESSURE STEAM (15 PSIG & BELOW)

MEDIUM PRESSURE STEAM CONDENSATE RETURN

MEDIUM PRESSURE STEAM (16 PSIG THRU 59 PSIG)

NUMBER INDICATES STEAM PRESSURE

NUMBER INDICATES STEAM PRESSURE

LPR

V

HWS

HWR

LPS (5)

MPS (30)

MPR

HEATING

SP

S F

T

H

T

T H

WET BULB TEMPERATURE, DEG. FWb

MAXIMUM

OUTSIDE AIR

(16 PSIG THRU 59 PSIG)

PRE-FILTER

PUMPED CONDENSATE

PREHEAT COIL

RELATIVE HUMIDITY

SUPPLY FAN

STEAM HUMIDIFIER

TRANSFER GRILLE

UNIT HEATER

STATIC PRESSURE (INCHES OF WATER)

PRESSURE REDUCING VALVE

MEDIUM PRESSURE STEAM SUPPLY

MEDIUM PRESSURE STEAM CONDENSATE RETURN

PRESSURE DROP (FEET OF WATER)

TOP REGISTER (WALL TYPE)

VARIABLE FREQUENCY DRIVE

STATIC PRESSURE SENSOR

DOOR UNDERCUT BY GENERAL CONTRACTOR

SPS

TR

U/C

VFD

UH

V

TG

VALVE

S.P.

SH

SF

Rh

PD

PF

PH

PRV

MPC

MAX

O.A.

NOM

MIN

PC

MPS

NOMINAL

MINIMUM

HEATING COIL

HORSEPOWER

MIXING BOX

POUNDS PER HOUR

HIGH PRESSURE STEAM SUPPLY (60 PSIG & ABOVE)

LOW PRESSURE STEAM SUPPLY (15 PSIG & BELOW)

LOW PRESSURE STEAM CONDENSATE RETURN

HIGH PRESSURE STEAM CONDENSATE RETURNHPR

HPS

LPR

LBS/HR

MB

LPS

HC

HP

BLOW UNLESS OTHERWISE NOTED)

CEILING DIFFUSERS (FOUR WAY

CHILLED WATER RETURN

CHILLED WATER SUPPLYCHS

CHR

AIR CONDITIONING

CONTROL CIRCUIT CONN.H1 N

ETCHED CLEAR LACQUERE.C.L.

WHITE BAKED ENAMELW.B.E.

BRAKE HORSEPOWERBHP

BRITISH THERMAL UNITBTU

BRITISH THERMAL UNIT PER HOURBTUH

CUBIC FEET PER MINUTECFM

DEGREEDEG

DIAMETERDIA

DIFFERENTIAL PRESSURE SENSORDPS

ENTERINGENT

F FAHRENHEIT

F&T FLOAT AND THERMOSTATIC

FPM FEET PER MINUTE

FT FEET

GALLONS PER MINUTEGPM

HEADHD

CHILLED WATER RETURNCHR

CHILLED WATER SUPPLYCHS

HEATING HOT WATER RETURNHWR

HEATING HOT WATER SUPPLYHWS

INCHESIN

INCHES WATER COLUMNIN WC

INCHES WATER GAUGEIN WG

LEAVING AIR TEMPERATURELAT

LEAVINGLVG

MBH 1000 BTUH

MERV MINIMUM EFFICIENCY REPORTING VALUE

NC NOISE CRITERIA

REVOLUTIONS PER MINUTERPM

SMOKE DAMPER (SUPPLY)SDS

SMOKE DAMPER (RETURN)SDR

STEAM PRESSURE REDUCING VALVESPRV

VOLUME DAMPERVD

HIGH PRESSURE STEAM CONDENSATE RETURN

HIGH PRESSURE STEAM (60 PSIG AND ABOVE)

NUMBER INDICATES STEAM PRESSURE

HPS (125)

HPR

PIPE UP

PIPE DOWN

IN-LINE CENTRIFUGAL FANICF

T

T

T

T

H dP

CS

DP SP

H4

A

H7

B.O.D. 9'-6"

MV MANUAL AIR VENT

EXHAUST DUCT (UP & DOWN)UP DN

PUMPED CONDENSATE RETURNPC

COMBINATION HOT/CHILLED WATER SUPPLYHWS/CHS

COMBINATION HOT/CHILLED WATER RETURNHWR/CHR

EXPANSION TANK PIPEET

CONDENSATE PUMPCP

CABINET UNIT HEATERCUH

FCU FAN COIL UNIT

EXPANSION TANKET

PUMPP

PROPELLER UNIT HEATERPUH

RETURN FANRF

WATER FILTERWF

POWER TYPE ROOF VENTILATORRV

POWER TYPE WALL VENTILATORWV

COR

PROPELLER TYPE EXHAUST FANPEF

RETURN AIRR.A.

SUPPLY AIRS.A.

SINGLE WIDTH SINGLE INLET (FAN)SWSI

SPECIFIC GRAVITYSP. GR.

FD FLOOR DRAIN

FCW FORWARD CURVED WHEEL (FAN)

FC FLEXIBLE CONNECTION

ENERGY EFFICIENCY RATIOEER

EXHAUST AIRE.A.

CONTRACTING OFFICER'S REPRESENTATIVE

CENTRIFUGAL OR HELICAL ROTARY SCREW CHILLER UNITCCU

AIR SEPARATORAS

ANGLE GLOBE VALVE

PIPE GUIDE

PIPE ANCHOR

ORIFICE UNION

TREATED DOMESTIC MAKE-UP WATER

STAINLESS STEEL DUCT

MU

GMU

FOR HUMIDIFIER

GLYCOL MAKEUP WATER

HOT GLYCOL WATER RETURN

HOT GLYCOL WATER SUPPLYGHS

GHR

CHILLED GLYCOL WATER SUPPLYGCS

CHILLED GLYCOL WATER RETURNGCR

UTILITY SET FANUSF

T

GENERAL

DOMESTIC COLD WATERW

FLOW METERM

PIPE MOUNTED DDC TEMPERATURE SENSOR

TOP GRILLE (WALL TYPE)TG

WATER GAUGEWG

WATTSW

VARIABLE AIR VOLUMEVAV

THERMOSTATTSTAT

TOTAL STATIC PRESSURETSP

SMOKE DETECTORSD

SUPPLY AIR TEMPERATURESAT

OUTSIDE DIAMETEROD

N.C. NORMALLY CLOSED

N.O. NORMALLY OPEN

MCA MINIMUM BRANCH CIRCUIT AMPACITY

LEAVING WATER TEMPERATURELWT

ENTERING WATER TEMPERATUREEWT

EXTERNAL STATIC PRESSUREESP

DIRECT EXPANSIONDX

ENTERING AIR TEMPERATUREEAT

GHR HOT GLYCOL HEATING WATER RETURN

GHS HOT GLYCOL HEATING WATER SUPPLY

VARIABLE VOLUME REHEAT (AIR TERMINAL UNIT)VVR

FLR. FLOOR

C CARBON DIOXIDE SENSOR (MOUNTED AT 46") 37. ALL EXISTING DUCTWORK, PIPING, EQUIPMENT, CONTROLS, ETC. SHOWN ON REMOVAL

PLAN(S) SHALL BE REMOVED. THE MAJORITY OF WORK TO BE REMOVED IS SHOWN.

REMOVE ALL INCIDENTAL AND/OR ABANDONED DUCTWORK, PIPING, ETC. THAT MAY NOT

BE SHOWN BUT IS ASSOCIATED WITH THE REMOVAL WORK.

38. ALL ITEMS THAT REQUIRE ACCESS, SUCH AS FOR OPERATING, CLEANING, SERVICING,

MAINTENANCE, AND CALIBRATION, SHALL BE EASILY AND SAFELY ACCESSIBLE BY

PERSONS STANDING AT FLOOR LEVEL, OR STANDING ON PORTABLE LADDERS OR

PERMANENT PLATFORMS. EXAMPLES OF THESE ITEMS INCLUDE, BUT

ARE NOT LIMITED TO: ALL TYPES OF VALVES, FILTERS AND STRAINER, TRANSMITTERS,

CONTROL DEVICES, ETC.

39. WHERE EXISTING HVAC UTILITIES IN SERVICE WILL BE DISRUPTED DURING THE

CONSTRUCTION OF THIS PROJECT, THIS WORK SHALL BE PERFORMED ON WEEKENDS OR

WEEK NIGHTS. DOWNTIME SHALL BE KEPT TO A MINIMUM, AND SHALL BE COORDINATED

AND SCHEDULED AT LEAST 10 WORKING DAYS IN ADVANCE WITH THE COR.

40. WHEN NEW SUPPLY AND RETURN AIR DUCTS ARE CONNECTED TO EXISTING DUCTWORK,

CLEAN BOTH NEW AND EXISTING DUCTWORK BY MOPPING AND VACUUM CLEANING INSIDE

AND OUTSIDE BEFORE OPERATION. CLEANING OF EXISTING DUCTWORK SHALL BE LIMITED

TO THE IMMEDIATE AREA WITHIN REACH OF THE OPEN END OF THE DUCT.

41. RUNOUT PIPING TO TERMINAL UNITS SHALL BE 0.75” SIZE UNLESS OTHERWISE NOTED.

REFER TO AIR TERMINAL UNIT SCHEDULE(S).

42. APPROXIMATE ELEVATIONS NOTED ON FLOOR PLANS ARE TO THE BOTTOM OF DUCTS

AND EQUIPMENT, AND TO THE CENTER OF PIPES.

43. REFER TO ELECTRICAL DRAWINGS FOR VARIABLE SPEED MOTOR CONTROLLERS

ASSOCIATED WITH MECHANICAL EQUIPMENT.

44. ALL INSULATED DUCTWORK AND PIPING SHALL HAVE DAMPER/VALVE HANDLE

EXTENSIONS.

1. THESE NOTES APPLY EQUALLY TO THE FULL SET OF DOCUMENTS.

2. SITE VISIT(S) SHALL BE AS OUTLINED IN PROJECT SPECIFICATIONS.

3. INCLUDE ALL WORK NECESSARY TO ACCOMMODATE PHASING. REFER TO

ARCHITECTURAL DRAWINGS AND GENERAL REQUIREMENTS SECTION 01 00 00.

4. INSULATE DUCTWORK AND PIPING WHERE EXISTING INSULATION HAS BEEN DAMAGED

AND/OR REMOVED IN THE PERFORMANCE OF WORK IN THIS PROJECT.

5. PROVIDE ALL ROOFING PENETRATION, REPAIR & REINFORCEMENT IN THE EXISTING

BUILDING FOR WORK INDICATED. ENGAGE A ROOFING SUBCONTRACTOR TO PERFORM

THE ROOFING WORK. WHERE ROOFING WORK IS REQUIRED, THE EXISTING ROOFING

AND INSULATION SHALL BE CUT, REMOVED AND RESTORED AS REQUIRED TO

ATTAIN A WATERTIGHT CONDITION. THE ROOFING SUB-CONTRACTOR SHALL BE A

CERTIFIED INSTALLER FOR SUCH INSTALLATION TO MAINTAIN THE EXISTING WARRANTY

ON THE ROOF.

6. THE CONTRACTORS SHALL REFER TO ALL SPECIFICATION SECTIONS AND THESE

7. IN ACCORDANCE WITH GENERALLY ACCEPTED CONSTRUCTION PRACTICES, THE

CONTRACTOR WILL BE SOLELY AND COMPLETELY RESPONSIBLE FOR THE CONDITIONS ON

THE JOB SITE, INCLUDING SAFETY OF ALL PERSONS AND PROPERTY DURING

PERFORMANCE OF THE WORK. THIS WILL APPLY CONTINUOUSLY AND NOT BE LIMITED TO

NORMAL WORKING HOURS. SEE SPECIFICATIONS FOR MORE SPECIFIC DETAILS ON

RESPONSIBILITIES.

8. ALL WORK MUST BE COORDINATED WITH THE CONTRACTING OFFICER AND COR TO

MAINTAIN OPERATION OF THE EXISTING FACILITY.

9. EACH TRADE SHALL COORDINATE HIS WORK WITH THE WORK OF OTHERS. HE

SHALL KEEP HIMSELF INFORMED OF THE PROGRESS AND DETAIL DEVELOPMENT OF THE

WORK OF OTHERS AND SHALL BE RESPONSIBLE FOR COORDINATING AND EXPEDITING HIS

WORK WITH OTHERS SO THAT THE PROGRESS OF THE TOTAL WORK SHALL BE KEPT ON

SCHEDULE.

10. ALL WORK SHALL BE PERFORMED IN COMPLETE COMPLIANCE WITH ALL GOVERNING

CODES AND STANDARDS.

11. EXISTING CONDITIONS SHOWN HAVE BEEN BASED UPON VISUAL OBSERVATION AND/OR

AVAILABLE DRAWING INFORMATION, AND MAY BE AT VARIANCE WITH ACTUAL WORK IN

PLACE. THE CONTRACTOR SHALL TAKE ALL NECESSARY FIELD MEASUREMENTS AND

FIELD VERIFY ALL CONDITIONS AFFECTING THE EXECUTION OF THE WORK. ANY

DISCREPANCIES BETWEEN EXISTING CONDITIONS AND THE WORK SHOWN ON THE

CONTRACT DOCUMENTS WHICH MAY IMPACT THE PROGRESS OF THE WORK SHALL BE

BROUGHT TO THE ATTENTION OF THE CONTRACTING OFFICER IN WRITING FOR

RESOLUTION BEFORE PROCEEDING WITH THE WORK.

12. THE CONTRACTOR AND/OR TRADE, FITTING OR PLACING HIS WORK INTO OR ON THE

WORK OF OTHERS DOES SO WITH THE UNDERSTANDING THAT THE INSTALLATION OF HIS

WORK CONSTITUTES HIS ACCEPTANCE OF THE SUITABILITY OF THE WORK IN PLACE. IF

THE WORK OF OTHERS IS NOT ACCEPTABLE, HE SHALL NOTIFY THE COR AND SUCH WORK

SHALL BE CORRECTED. ANY NEW WORK INSTALLED IN UNSUITABLE EXISTING CONDITIONS

SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR OR TRADE INSTALLING THE NEW

WORK. NO CLAIMS FOR ADDITIONAL COMPENSATION FOR CORRECTING WORK INSTALLED

IN UNSUITABLE EXISTING CONDITIONS WILL BE CONSIDERED.

13. IF, IN THE PERFORMANCE OF THIS WORK, MATERIALS ARE OBSERVED WHICH ARE

SUSPECTED TO CONTAIN ASBESTOS, THE CONTRACTOR SHALL IMMEDIATELY INFORM THE

COR. WORK THAT WOULD EXPOSE WORKERS TO THE INHALATION OF ASBESTOS

PARTICLES SHALL BE TERMINATED. WORK MAY BE RESUMED ONLY AFTER A

DETERMINATION HAS BEEN MADE AND UNSAFE MATERIALS HAVE BEEN REMOVED OR

ENCAPSULATED AND THE AREA DECLARED SAFE.

14. REFER TO ARCHITECTURAL FIRE-RATED PARTITION PLAN(S) FOR LOCATIONS AND

FIRE-RATINGS OF NEW AND EXISTING WALL ASSEMBLIES. ALL PENETRATIONS THROUGH

FIRE-RATED ASSEMBLIES SHALL BE PROTECTED AND/OR FIRE-STOPPED AS REQUIRED TO

MAINTAIN FIRE-RATINGS INDICATED. COORDINATE WITH ALL TRADES TO ENSURE

FIRE-RATED PENETRATION REQUIREMENTS AND DETAILS ARE MET.

15. ANNULAR SPACE OF ALL PIPE, CONDUIT, DUCT & OTHER SIMILAR PENETRATIONS OF FIRE

RATED ASSEMBLIES SHALL BE FIRESTOPPED. IN ADDITION, PENETRATIONS THROUGH

0-HOUR RATED WALLS & FLOORS SHALL BE SEALED TO RETARD PASSAGE OF SMOKE.

16. ALL PIPING, DUCTS, CONDUITS, ETC. IN FINISHED ROOMS, CORRIDORS, ETC. SHALL BE

CONCEALED IN A FURRED CHASE OR ABOVE THE SUSPENDED CEILING.

17. THE FIRST FIGURE OF DUCT SIZE INDICATES DIMENSION OF FACE SHOWN OR INDICATED.

DUCT SIZES ARE NET INSIDE DIMENSIONS.

18. PROVIDE DUCT ACCESS PANELS AS REQUIRED BY 23 31 00 FOR ACCESS TO FIRE

DAMPERS, SMOKE DAMPERS, SMOKE DETECTORS, AUTOMATIC CONTROL DAMPERS, AND

HUMIDIFIER DISPERSION TUBES. REFER TO DETAIL SHEETS. COORDINATE SIZES

AND LOCATIONS WITH ACCESSORIES PROVIDED BY OTHER TRADES.

19. ACCESS PANELS IN NON ACCESSIBLE SUSPENDED CEILINGS SHALL BE PROVIDED FOR

ALL VALVES, TRAPS, DAMPERS, CLEANOUTS, FLOW METERS, CONTROLS, ETC.

COORDINATE SIZES AND LOCATIONS WITH OTHER TRADES.

20. TOTAL STATIC PRESSURE NOTED IN THE SCHEDULES INCLUDES DUCT SYSTEM,

TERMINAL UNITS, FILTERS, COILS, ETC.

21. FOR TYPICAL STEAM, WATER AND REFRIGERANT PIPING CONNECTIONS TO EQUIPMENT,

SEE STANDARD DETAILS AND PIPING SCHEMATICS.

22. DIFFUSER SIZES SHOWN ON FLOOR PLANS ARE NECK SIZES. REGISTER AND GRILLE

SIZES SHOWN ARE FACE SIZES.

23. REFER TO ARCHITECTURAL REFLECTED CEILING PLANS FOR EXACT LOCATION OF

CEILING DIFFUSERS, REGISTERS, AND GRILLES.

24. WATER PIPE CONNECTIONS TO AIR HEATING AND COOLING COILS SHALL BE MADE TO

PROVIDE COUNTER FLOW BETWEEN WATER AND AIR.

25. WALL TYPE EXHAUST REGISTERS NOTED AS "BR" ON DRAWINGS ARE TO BE INSTALLED

WITH BOTTOM OF REGISTERS SEVEN INCHES ABOVE FINISHED FLOOR.

26. WHERE DUCTS OR PIPES ARE REMOVED THRU WALL/FLOOR/ROOF THAT IS TO REMAIN,

PATCH WALL/FLOOR/ROOF OPENING TO MATCH EXISTING WHERE OPENING IS NOT

RE-USED.

27. ALL PRESSURES LISTED ARE GAGE PRESSURE UNLESS OTHERWISE NOTED.

28. ALL CUTTING AND PATCHING REQUIRED FOR THIS PROJECT SHALL BE INCLUDED IN THE

CONTRACT. REFINISH ANY SURFACE DISTURBED UNDER THIS WORK TO MATCH EXISTING.

29. IN GENERAL, KEEP DUCT AND PIPING MAINS NEXT TO UNDERSIDE OF STRUCTURE.

30. ANY REMOVED EQUIPMENT SHALL BE TURNED OVER TO THE VA. ITEMS NOT DESIRED BY

THE VA SHALL BE REMOVED FROM THE PREMISES AND DISPOSED OF PROPERLY BY THE

CONTRACTOR.

31. THE CONTRACT DRAWINGS ARE NOT INTENDED TO SHOW EVERY VERTICAL OR

HORIZONTAL OFFSET WHICH MAY BE NECESSARY TO COMPLETE THE SYSTEMS.

COORDINATE WORK IN ADVANCE WITH ALL OTHER TRADES AND REPORT IMMEDIATELY

ANY DIFFICULTIES WHICH CAN BE ANTICIPATED.

32. FIELD VERIFY EXISTING CONDITIONS, INCLUDING DUCT, PIPE AND EQUIPMENT SIZES,

SERVICES AND LOCATIONS PRIOR TO PERFORMING WORK.

33. HEPA FILTERED EXHAUST IS REQUIRED TO MAINTAIN A MINIMUM OF 0.01" W.G. NEGATIVE

PRESSURE IN CONSTRUCTION AREAS. COORDINATE WITH COR.

34. ALL ABANDONED EXTRANEOUS PIPING, DUCTWORK, SUPPORTS, CONTROLS, ETC. SHALL

BE REMOVED.

35. TERMINATE PIPING AND DUCTWORK BELOW FLOORS, ABOVE CEILINGS, ETC., IN

CONCEALED SPACES. ALL CUTTING AND PATCHING SHALL MATCH EXISTING FINISHES.

36. WHERE CONTROL DEVICES ARE REMOVED, PNEUMATIC LINES SHALL BE REMOVED BACK

TO MAIN AND CAPPED; AND CONTROL WIRING AND CONDUIT SHALL BE REMOVED BACK TO

SOURCE.

45. PERFORM AN AIR SURVEY OF ALL EXISTING DUCTED SYSTEMS PRIOR OF ANY REMOVAL WORK

DRAWINGS FOR DETAILS OF BUILDING CONSTRUCTION TO ENSURE SPACE AND

SATISFACTORY ARRANGEMENT FOR THEIR WORK. THE VARIOUS DRAWINGS COMPRISING

THE SET ARE INTERDEPENDENT AND MUST BE USED JOINTLY AT ALL TIMES. REFER TO

THE GENERAL REQUIREMENTS OF THE CONTRACT. THE NOTES AND SYMBOLS INDICATED

ON THE DRAWINGS ARE FOR THE GUIDANCE OF ALL TRADES INVOLVED IN THE PROJECT

AND MUST BE FOLLOWED TO EXECUTE THE WORK AS INTENDED. IF DISCREPANCIES

OCCUR, CONTACT THE COR THRU THE CONTRACTING OFFICER FOR CLARIFICATION

BEFORE PROCEEDING.

ACCESS DOORAD

FLOW ELEMENT AND TEMPERATURE ELEMENT FORFE TE

BTUH METER

TAKING PLACE. SUBMIT FINAL REPORT TO THE COR AND ENGINEER.

46. COORDINATE SEQUENCING OF ALL WORK CROSSING PHASING BOUNDRIES WITH COR WELL

IN ADVANCE.

S-B

ABBREVIATIONSCONTROLSPIPING SYMBOLSDRAWING SYMBOLS

DUCTWORK SYMBOLS

GENERAL NOTES

GENERAL

VALVES

GENERAL NOTES

ABBREVIATIONS

P: 937-224-0861 www.heapy.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

GUIDON DESIGN INC.

905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204

317.800.6388 | WWW.GUIDONDESIGN.COM

SUSTAINABLE ARCHITECTURE + ENGINEERING

PROJECT LEAD

Architect, Structural Engineer, Civil Engineer

PROJECT NO. STATE COA FIRM NO.2018-05164 01528

/3

/2

:3

:1

P

M

M001

LEGEND, ABBREVIATIONS & INDEX

OF DRAWINGS

CORRECT

INFRASTRUCTURE

DEFICIENCIES, B408

DAYTON, OHIO 45428

552-19-102

PHIL WEST, COR

May 2nd, 2025 GSE WJS

BID DOCUMENTS

FULLY SPRINKLERED

INDEX OF DRAWINGS - MECHANICAL

Sheet Number Sheet Name

M001 LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS

MD100 BASEMENT FLOOR PLAN - REMOVALS

MD101 FIRST FLOOR PLAN - REMOVALS

MD102 SECOND FLOOR PLAN - REMOVALS

MD103 ATTIC FLOOR PLAN - REMOVALS

MH100 BASEMENT FLOOR PLAN - DUCTWORK

MH101 FIRST FLOOR PLAN - DUCTWORK

MH102 SECOND FLOOR PLAN - DUCTWORK

MH103 ATTIC FLOOR PLAN - DUCTWORK

MP100 BASEMENT FLOOR PLAN - PIPING

MP101 FIRST FLOOR PLAN - PIPING

MP102 SECOND FLOOR PLAN - PIPING

MP103 ATTIC FLOOR PLAN - PIPING

M401 ENLARGED PLANS

M501 DETAILS

M502 DETAILS

M503 DETAILS

M504 HYDRONIC PIPING SCHEMATICS

M505 STEAM PIPING SCHEMATIC

M601 SCHEDULES

M602 SCHEDULES

M603 SCHEDULES

M701 CONTROLS AND AUTOMATION

M702 CONTROLS AND AUTOMATION

DN

AHU

CWR/CWS UP AND

CONDENSATE DRAIN.

18x12

12x8

10x88x8 12x8 10x8 x1

24x12

9 9

CWR/CWS UP AND

CONDENSATE DRAIN.

CWR/CWS UP AND

CONDENSATE DRAIN.

CWR/CWS UP AND

CONDENSATE DRAIN.

CWR/CWS UP.

PHASE 1

8 9

PHASE 3PHASE 4

P: 937-224-0861 www.heapy.com

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

GUIDON DESIGN INC.

905 N. CAPITOL AVE. SUITE 100 | INDIANAPOLIS, IN. 46204

317.800.6388 | WWW.GUIDONDESIGN.COM

SUSTAINABLE ARCHITECTURE + ENGINEERING

PROJECT LEAD

Architect, Structural Engineer, Civil Engineer

PROJECT NO. STATE COA FIRM NO.2018-05164 01528

/3

/2

:3

:2

P

M

MD100

BASEMENT FLOOR PLAN -

REMOVALS

CORRECT

INFRASTRUCTURE

DEFICIENCIES, B408

DAYTON, OHIO 45428

552-19-102

PHIL WEST, COR

May 2nd, 2025 GSE WJS

BID DOCUMENTS

FULLY SPRINKLERED

GENERAL NOTES

PLAN NOTES

A. REFER TO SHEET M001 FOR LEGEND, ABBREVIATIONS, INDEX OF DRAWINGS,

AND ADDITIONAL GENERAL NOTES.

1. EXISTING DUCTWORK TO REMAIN.

2. EXISTING STEAM PIPING UP THRU BUILDING TO REMAIN.

3. REMOVE EXISTING DUCTWORK AND ASSOCIATED ACCESSORIES, SUPPORTS, ETC.

4. REMOVE EXISTING DUCT TO THIS POINT FOR RECONNECTION IN NEW WORK.

5. REMOVE EXISTING AIR HANDLING UNIT AND ASSOCIATED DUCTWORK, PIPING,

CONTROLS, ETC.

6. REMOVE EXISTING PIPING AND ASSOCIATED ACCESSORIES, SUPPORTS, ETC. AFTER

NEW CHW AND HHW SYSTEMS ARE OPERATIONAL.

7. REMOVE ALL EXISTING CHILLED WATER SYSTEM COMPONENTS AFTER THE NEW

CHILLERS ARE INSTALLED AND OPERATIONAL.

8. REMOVE EXISTING DUCTWORK TO FLOOR PENETRATION. EXISTING AIR DEVICE ON

FIRST FLOOR TO REMAIN.

9. CAP UNDER FLOOR.

10. REMOVE EXISTING PIPING TO THIS POINT AND CAP AFTER NEW CHW AND HHW

SYSTEMS ARE OPERATIONAL.

11. REMOVE EXISTING AIR HANDLING UNIT STRUCTURAL SUPPORTS. AHU LOCATED ON

FIRST FLOOR.

SCALE: 1/8" = 1'-0"MD100

1 BASEMENT-HVAC-REMOVALS

N

ALL EXISTING STEAM AND CHILLED

WATER PIPING SHALL BE REMOVED

FROM THE BASEMENT/CRAWL

SPACE. THIS REMOVAL WORK SHALL

TAKE PLACE AFTER THE NEW

CHILLED WATER AND HOT WATER

SYSTEMS ARE OPERATIONAL. SOME

OF THE PIPING IS SHOWN ON THIS

FLOOR PLAN.

2018-05164_Div21_Dwgs
2018-05164_Div23_Dwgs
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING
MP103 - ATTIC FLOOR PLAN - PIPING
M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS
M401 - ENLARGED PLANS
M501 - DETAILS
M502 - DETAILS
M503 - DETAILS
M504 - HYDRONIC PIPING SCHEMATICS
M505 - STEAM PIPING SCHEMATIC
M601 - SCHEDULES
M602 - SCHEDULES
M603 - SCHEDULES
M701 - CONTROLS AND AUTOMATION
M702 - CONTROLS AND AUTOMATION
MD100 - BASEMENT FLOOR PLAN - REMOVALS
MD101 - FIRST FLOOR PLAN - REMOVALS
MD102 - SECOND FLOOR PLAN - REMOVALS
MD103 - ATTIC FLOOR PLAN - REMOVALS
MH100 - BASEMENT FLOOR PLAN - DUCTWORK
MH101 - FIRST FLOOR PLAN - DUCTWORK
MH102 - SECOND FLOOR PLAN - DUCTWORK
MH103 - ATTIC FLOOR PLAN - DUCTWORK
MP100 - BASEMENT FLOOR PLAN - PIPING
MP101 - FIRST FLOOR PLAN - PIPING
MP102 - SECOND FLOOR PLAN - PIPING