552-19-102 Drawings_Volume2.pdf
PDF 10 MB Posted
- Solicitation number
- 36C25025B0036
About this file
These documents are Life Safety Plan and Infection Control/Phasing drawings for the VA Dayton Medical Center Building 408 Infrastructure Deficiencies Correction project. The drawings detail a comprehensive renovation project spanning four phases, focusing on mechanical, electrical, plumbing, and technology (MEPTF) systems upgrades, hazardous material abatement, and window and door replacements. The project involves a fully sprinklered, Type II-B construction business occupancy building with strict infection control protocols, including temporary barrier walls, construction access doors, and phased work schedules to minimize disruption to ongoing facility operations.
The project's four phases are strategically planned: Phase 1 involves site investigation, utility assessment, and basement work; Phase 2 targets the central building section; Phase 3 focuses on the northern wing; and Phase 4 addresses the southern wing. Key requirements include working primarily during off-hours (5:00 PM to 5:00 AM), maintaining exit access during business hours, minimizing noise and vibration, implementing infection control measures like sticky walk-off mats and hand sanitizers, and ensuring proper debris and hazardous material management. The project is fully compliant with NFPA 101 Life Safety Code and follows VA design manual specifications.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DN
UNEXCAVATED
SPRINKELR SYSTEM
CONTROLS
205J
PIPE SPACE
205K
UNEXCAVATED
UNEXCAVATED
Room
205N
UNEXCAVATED UNEXCAVATED
CONCRETE SLAB
Room
205R
PIPE SPACE
STORAGE
ENGINEERING
STORAGE ROOM
ELEV.
NO.12
MACHINE ROOM
LOCKSMITH
C-B-1
C-B-2
CODE ANALYSIS - NFPA 101, BUSINESS CHAPTER 38
CODE CRITERIA
GENERAL: THIS SUMMARY OF CODE REQUIREMENTS IS BASED PRIMARILY ON NFPA 101 (LSC). DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE IDENTIFIED. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD
PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES.
NOTES:
CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
CODE REVIEW
THE 2021 EDITION OF THE LIFE SAFETY CODE, NFPA 101, HAS BEEN USED TO REVIEW THIS PROJECT FOR COMPLIANCE WITH THE FIRE AND LIFE SAFETY REQUIREMENTS.
FOR FEATURES NOT ADDRESSED BY NFPA 101 AND THE REFERENCED NATIONAL FIRE CODES, THE 2021 EDITION OF THE INTERNATIONAL BUILDING CODE HAS BEEN
USED.
PROJECT SCOPE
1. THE CONSTRUCTION TYPE IS DETERMINED BASED UPON THE ALLOWABLE AREA AND HEIGHT REQUIREMENTS OF CHAPTER 5 OF THE 2021 IBC. CONSTRUCTION TYPE AND MATERIALS SHALL BE PER CHAPTER 6 OF THE IBC FOR TYPE II-B CONSTRUCTION AS FOLLOWS:
2. OCCUPANCY TYPE: B-BUSINESS, IBC CHAPTER 3/LSC CHAPTER 38
3. FIRE RESISTIVE RATINGS TYPE II-B/ II(000) CONSTRUCTION, CHAPTER 6 IBC/NFPA 101:
STRUCTURAL FRAME: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
BEARING WALLS
EXTERIOR: NONCOMBUSTIBLE, 0 -HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
NON-BEARING WALLS AND PARTITIONS
EXTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE-RESISTIVE
FLOOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
ROOF: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
SHAFT ENCLOSURES 2-HOUR FIRE RESISTIVE >4 STORIES (IBC 713.4, LSC 12.3.6)
SHAFT ENCLOSURES 1-HOUR FIRE RESISTIVE <4 STORIES (IBC 713.4, LSC 12.3.6)
4. STRUCTURAL DESIGN SHALL COMPLY WITH CHAPTER 16 OF THE IBC.
5. ALLOWABLE HEIGHT: 75 FT (IBC, TABLE 504.3)
6. ALLOWABLE NUMBER OF STORIES ABOVE GRADE PLAN: 4 (IBC, TABLE 504.4)
7. ALLOWABLE AREA: BASED UPON B OCCUPANCY, II-B CONSTRUCTION TYPE, AND FULLY SPRINKLED: ALLOWABLE AREA: 69,000 (IBC, TABLE 506.2)
8. BUILDING SEPARATION: BASED ON A >30 FIRE SEPARATION DISTANCE A 0 -HOUR FIRE RESISTANCE WALL RATING IS REQUIRED. (IBC, TABLE 602)
9. MEANS OF EGRESS
• CLEAR WIDTH OF CORRIDORS SHALL BE CLEAR 44 INCHES.
• CLEAR WIDTH OF DOORS SHALL BE CLEAR 32 INCHES
• NOT LESS THAN 2 EXITS SHALL BE PROVIDED PER FLOOR.
• ADDITION OCCUPANCY LOAD: <500 THEREFORE 2 EXITS REQUIRED (LSC 7.4.1)
• MAXIMUM TRAVEL DISTANCE, FULLY SPRINKLED: 300 FEET (LSC 38.2.6.3)
• COMMON PATH OF TRAVEL SHALL NOT EXCEED 100 FEET (LSC 38.2.5.3.1)
• DEAD END CORRIDORS SHALL NOT EXCEED 50 FEET. (LSC 38.2.5.2.1)
• MEANS OF EGRESS SHALL BE ILLUMINATED. (LSC 38.2.8)
• EMERGENCY LIGHTING SHALL BE PROVIDED, BUILDING OVER 3 STORIES. (LSC 38.2.9.1)
• EXIT SIGNAGE SHALL BE PROVIDED. (LSC 38.2.10)
10. PROTECTION FROM ANY AREA HAVING A DEGREE OF HAZARD GREATER THAN THAT NORMAL TO THE GENERAL OCCUPANCY OF THE BUILDING OR STRUCTURE SHALL BE PROVIDED BY PROTECTING THE AREA WITH AUTOMATIC EXTINGUISHING SYSTEMS IN ACCORDANCE WITH SECTION 9.7(3). WHERE HAZARD IS SEVERE PER LSC CHAPTER 38, SOILED HOLDING, PROTECTION IS PROVIDED WITH AN AUTOMATIC EXTINGUISHING SYSTEMS THE SPACE SHALL ALSO BE ENCLOSED WITH SMOKE
PARTITIONS IN ACCORDANCE WITH SECTION 8.4.
11. INTERIOR FINISH
• WALLS AND CEILINGS: INTERIOR FINISH FLAME SPREAD SHALL BE LIMITED PER CHAPTER 8 OF THE NFPA 101 TO CLASS A, B AND C MATERIALS. INTERIOR WALL
AND CEILING FINISH SHALL BE CLASS A OR CLASS B IN EXITS, CORRIDORS AND LOBBIES; AND CLASS A, CLASS B, OR CLASS C IN ALL OTHER AREAS. (LSC 38.3.3)
• · CLASS A: FLAME SPREAD 0-25; SMOKE DEVELOPED 0-450.
• · CLASS B: FLAME SPREAD 26-75; SMOKE DEVELOPED 0-450.
• · CLASS C: FLAME SPREAD 76-200; SMOKE DEVELOPED 0-450
• FLOORS: INTERIOR FLOOR FINISH SHALL BE CLASS I OR CLASS II IN CORRIDORS AND EXITS.
• FABRIC DRAPERIES, CURTAINS (EXCLUDING SHOWER CURTAINS, BUT INCLUDING CUBICLE CURTAINS), AND OTHER LOOSELY HANGING FABRICS AND FILMS
SERVING AS FURNISHINGS OR DECORATIONS IN HEALTH CARE OCCUPANCIES MUST MEET THE FLAME RESISTANCE REQUIREMENTS OF NFPA 701, STANDARD
METHODS OF FIRE TESTS FOR FLAME-RESISTANT TEXTILES AND FILMS.
• UPHOLSTERED FURNITURE AND MATTRESSES. UPHOLSTERED FURNITURE AND MATTRESSES MUST ALSO MEET SPECIFIED REQUIREMENTS, BASED ON NFPA
260, NFPA 261, NFPA 266, 16 CFR 1632, ASTME E1537, AND ASTME E1590
12. EXTINGUISHMENTS REQUIREMENTS, PORTABLE FIRE EXTINGUISHERS SHALL BE PROVIDED PER NFPA 10. (38.3.5)
13. DETECTION, ALARM, AND COMMUNICATIONS SYSTEMS.
• FIRE ALARM SYSTEM SHALL BE PROVIDED LSC, NFPA 70 (NEC) AND NFPA 72. (LSC 9.6.1)
• FIRE ALARM MAY BE BY MANUAL MEANS (LSC 38.4.2)(LSC 9.6.2)
• OCCUPANT NOTIFICATION SHALL BE THROUGH AUTOMATIC MEANS. (LSC 38.3.4.3)
• SMOKE DETECTION SHALL BE PROVIDED PER NFPA 72.
• EMERGENCY RESPONDER NOTIFICATION SHALL BE NOTIFIED BY ALARM AND DETECTION SYSTEM. (LSC 38.3.4.4)
14. FIRE SUPPRESSION:
SPRINKLER SYSTEM: BUILDING IS REQUIRED TO BE SPRINKLED THROUGHOUT IN ACCORDANCE WITH NFPA 13.
THE SPRINKLER SYSTEM SHALL BE HYDRAULICALLY DESIGNED IN ACCORDANCE WITH 2013 EDITION OF NFPA 13 AND THE SIXTH EDITION OF THE DEPARTMENT OF
VETERANS AFFAIRS FIRE PROTECTION DESIGN MANUAL: MINIMUM DESIGN REQUIREMENTS:
STORAGE MECHANICAL AND ELECTRICAL ROOMS SHALL BE PROTECTED AS:
ORDINARY HAZARD OCCUPANCY, GROUP 1: 0.15 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 250 GPM
ALL OTHER AREAS SHALL BE PROTECTED AS:
LIGHT HAZARD OCCUPANCY: 0.10 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 100 GPM
ALL SPRINKLERS WITHIN THE SMOKE ZONE SHALL BE QUICK RESPONSE SPRINKLERS.
15. CONSTRUCTION BARRIERS CONSTRUCTED ALONG MEANS OF EGRESS ALONG HEALTHCARE OCCUPANCIES (LSC CHAPTER 18 AND 19) SHALL BE CONSTRUCTED AND
MAINTAINED PER NFPA 241.
CODE ANALYSIS LEGEND
TOTAL OCCUPANCY
FEC
EXIT
OCCUPANCY LOAD FACTOR
EXITS REQUIRED
SQUARE FOOTAGE
OCCUPANCY TYPE
EGRESS EXIT SIGNAGE
FIRE EXTINGUISHER CABINET
DIAGONAL DISTANCE
EXIT SEPARATION DISTANCE
EGRESS PATH
2 HR - FIRE SEPARATION
1 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
B
1500 SF
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
P
.1
V
A D a y to n
I D
IQ
\T
O
C o rr e c t In fr a s tr u c ti o n
D e fe c ie n c ie s B ld g
G D
I\
D ra w in g s \2
-1 A rc h it e c tu re \1
-1 R e v it \1
.1
.0
B L
D G v
.r v t
/2
/2
:3
:1
P
M
GI101
LIFE SAFETY PLAN
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA STREET, SUITE 200
INDIANAPOLIS, IN 46202
317-800-6388
ADAM OGRZEWALLA
HEAPY ENGINEERING
1400 W DOROTHY LANE
DAYTON, OH 45409
317-800-6388
MATT GRAHAM
CORRECT INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OH 45428
552-19-102
PHIL WEST, COR
08/15/2022 AO AO
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 3/32" = 1'-0"GI101
2 BASEMENT
N
Revisions: Date:
aogrzewalla Text Box 05/02/2025 aogrzewalla Snapshot
CONFERENCE
103C
OFFICE
OFFICE
103D
OFFICE
103A
OFFICE
TELE PHARMACY
MENS
COMM.
103B
LOBBY
OFFICE
101C
ACQUISITION
CHAPLAIN
OFFICE
101D
OFFICE
101A
KITCHEN
OFFICE
106k
OFFICE
106l
OFFICE
106h
OFFICE
106g
DSS SUITE
OFFICE
106e
STORAGE
106d
OFFICE
106a
OFFICE
106j
OFFICE
106f
COPIER
106c
OFFICE
106b
OPEN OFFICE
OFFICE
100d
OFFICE
100c
OFFICE
100h
OFFICE
100k
OFFICE
100j
OFFICE
100l
WOMENS
OFFICE
100n
OFFICE
100g
OFFICE
100m
CONFERENCE
107f
OFFICE
107g
OFFICE
107a
OFC
107c
OFC
107d
OFC
107e
OFC
107b
SUITE
COMM
101B
OFFICE
109C
CODE ANALYSIS LEGEND
TOTAL OCCUPANCY
FEC
EXIT
OCCUPANCY LOAD FACTOR
EXITS REQUIRED
SQUARE FOOTAGE
OCCUPANCY TYPE
EGRESS EXIT SIGNAGE
FIRE EXTINGUISHER CABINET
DIAGONAL DISTANCE
EXIT SEPARATION DISTANCE
EGRESS PATH
2 HR - FIRE SEPARATION
1 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
B
1500 SF
CODE ANALYSIS - NFPA 101, BUSINESS CHAPTER 38
CODE CRITERIA
GENERAL: THIS SUMMARY OF CODE REQUIREMENTS IS BASED PRIMARILY ON NFPA 101 (LSC). DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE IDENTIFIED. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD
PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES.
NOTES:
CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
CODE REVIEW
THE 2021 EDITION OF THE LIFE SAFETY CODE, NFPA 101, HAS BEEN USED TO REVIEW THIS PROJECT FOR COMPLIANCE WITH THE FIRE AND LIFE SAFETY REQUIREMENTS.
FOR FEATURES NOT ADDRESSED BY NFPA 101 AND THE REFERENCED NATIONAL FIRE CODES, THE 2021 EDITION OF THE INTERNATIONAL BUILDING CODE HAS BEEN
USED.
PROJECT SCOPE
1. THE CONSTRUCTION TYPE IS DETERMINED BASED UPON THE ALLOWABLE AREA AND HEIGHT REQUIREMENTS OF CHAPTER 5 OF THE 2021 IBC. CONSTRUCTION TYPE AND MATERIALS SHALL BE PER CHAPTER 6 OF THE IBC FOR TYPE II-B CONSTRUCTION AS FOLLOWS:
2. OCCUPANCY TYPE: B-BUSINESS, IBC CHAPTER 3/LSC CHAPTER 38
3. FIRE RESISTIVE RATINGS TYPE II-B/ II(000) CONSTRUCTION, CHAPTER 6 IBC/NFPA 101:
STRUCTURAL FRAME: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
BEARING WALLS
EXTERIOR: NONCOMBUSTIBLE, 0 -HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
NON-BEARING WALLS AND PARTITIONS
EXTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE-RESISTIVE
FLOOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
ROOF: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
SHAFT ENCLOSURES 2-HOUR FIRE RESISTIVE >4 STORIES (IBC 713.4, LSC 12.3.6)
SHAFT ENCLOSURES 1-HOUR FIRE RESISTIVE <4 STORIES (IBC 713.4, LSC 12.3.6)
4. STRUCTURAL DESIGN SHALL COMPLY WITH CHAPTER 16 OF THE IBC.
5. ALLOWABLE HEIGHT: 75 FT (IBC, TABLE 504.3)
6. ALLOWABLE NUMBER OF STORIES ABOVE GRADE PLAN: 4 (IBC, TABLE 504.4)
7. ALLOWABLE AREA: BASED UPON B OCCUPANCY, II-B CONSTRUCTION TYPE, AND FULLY SPRINKLED: ALLOWABLE AREA: 69,000 (IBC, TABLE 506.2)
8. BUILDING SEPARATION: BASED ON A >30 FIRE SEPARATION DISTANCE A 0 -HOUR FIRE RESISTANCE WALL RATING IS REQUIRED. (IBC, TABLE 602)
9. MEANS OF EGRESS
• CLEAR WIDTH OF CORRIDORS SHALL BE CLEAR 44 INCHES.
• CLEAR WIDTH OF DOORS SHALL BE CLEAR 32 INCHES
• NOT LESS THAN 2 EXITS SHALL BE PROVIDED PER FLOOR.
• ADDITION OCCUPANCY LOAD: <500 THEREFORE 2 EXITS REQUIRED (LSC 7.4.1)
• MAXIMUM TRAVEL DISTANCE, FULLY SPRINKLED: 300 FEET (LSC 38.2.6.3)
• COMMON PATH OF TRAVEL SHALL NOT EXCEED 100 FEET (LSC 38.2.5.3.1)
• DEAD END CORRIDORS SHALL NOT EXCEED 50 FEET. (LSC 38.2.5.2.1)
• MEANS OF EGRESS SHALL BE ILLUMINATED. (LSC 38.2.8)
• EMERGENCY LIGHTING SHALL BE PROVIDED, BUILDING OVER 3 STORIES. (LSC 38.2.9.1)
• EXIT SIGNAGE SHALL BE PROVIDED. (LSC 38.2.10)
10. PROTECTION FROM ANY AREA HAVING A DEGREE OF HAZARD GREATER THAN THAT NORMAL TO THE GENERAL OCCUPANCY OF THE BUILDING OR STRUCTURE SHALL BE PROVIDED BY PROTECTING THE AREA WITH AUTOMATIC EXTINGUISHING SYSTEMS IN ACCORDANCE WITH SECTION 9.7(3). WHERE HAZARD IS SEVERE PER LSC CHAPTER 38, SOILED HOLDING, PROTECTION IS PROVIDED WITH AN AUTOMATIC EXTINGUISHING SYSTEMS THE SPACE SHALL ALSO BE ENCLOSED WITH SMOKE
PARTITIONS IN ACCORDANCE WITH SECTION 8.4.
11. INTERIOR FINISH
• WALLS AND CEILINGS: INTERIOR FINISH FLAME SPREAD SHALL BE LIMITED PER CHAPTER 8 OF THE NFPA 101 TO CLASS A, B AND C MATERIALS. INTERIOR WALL
AND CEILING FINISH SHALL BE CLASS A OR CLASS B IN EXITS, CORRIDORS AND LOBBIES; AND CLASS A, CLASS B, OR CLASS C IN ALL OTHER AREAS. (LSC 38.3.3)
• · CLASS A: FLAME SPREAD 0-25; SMOKE DEVELOPED 0-450.
• · CLASS B: FLAME SPREAD 26-75; SMOKE DEVELOPED 0-450.
• · CLASS C: FLAME SPREAD 76-200; SMOKE DEVELOPED 0-450
• FLOORS: INTERIOR FLOOR FINISH SHALL BE CLASS I OR CLASS II IN CORRIDORS AND EXITS.
• FABRIC DRAPERIES, CURTAINS (EXCLUDING SHOWER CURTAINS, BUT INCLUDING CUBICLE CURTAINS), AND OTHER LOOSELY HANGING FABRICS AND FILMS
SERVING AS FURNISHINGS OR DECORATIONS IN HEALTH CARE OCCUPANCIES MUST MEET THE FLAME RESISTANCE REQUIREMENTS OF NFPA 701, STANDARD
METHODS OF FIRE TESTS FOR FLAME-RESISTANT TEXTILES AND FILMS.
• UPHOLSTERED FURNITURE AND MATTRESSES. UPHOLSTERED FURNITURE AND MATTRESSES MUST ALSO MEET SPECIFIED REQUIREMENTS, BASED ON NFPA
260, NFPA 261, NFPA 266, 16 CFR 1632, ASTME E1537, AND ASTME E1590
12. EXTINGUISHMENTS REQUIREMENTS, PORTABLE FIRE EXTINGUISHERS SHALL BE PROVIDED PER NFPA 10. (38.3.5)
13. DETECTION, ALARM, AND COMMUNICATIONS SYSTEMS.
• FIRE ALARM SYSTEM SHALL BE PROVIDED LSC, NFPA 70 (NEC) AND NFPA 72. (LSC 9.6.1)
• FIRE ALARM MAY BE BY MANUAL MEANS (LSC 38.4.2)(LSC 9.6.2)
• OCCUPANT NOTIFICATION SHALL BE THROUGH AUTOMATIC MEANS. (LSC 38.3.4.3)
• SMOKE DETECTION SHALL BE PROVIDED PER NFPA 72.
• EMERGENCY RESPONDER NOTIFICATION SHALL BE NOTIFIED BY ALARM AND DETECTION SYSTEM. (LSC 38.3.4.4)
14. FIRE SUPPRESSION:
SPRINKLER SYSTEM: BUILDING IS REQUIRED TO BE SPRINKLED THROUGHOUT IN ACCORDANCE WITH NFPA 13.
THE SPRINKLER SYSTEM SHALL BE HYDRAULICALLY DESIGNED IN ACCORDANCE WITH 2013 EDITION OF NFPA 13 AND THE SIXTH EDITION OF THE DEPARTMENT OF
VETERANS AFFAIRS FIRE PROTECTION DESIGN MANUAL: MINIMUM DESIGN REQUIREMENTS:
STORAGE MECHANICAL AND ELECTRICAL ROOMS SHALL BE PROTECTED AS:
ORDINARY HAZARD OCCUPANCY, GROUP 1: 0.15 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 250 GPM
ALL OTHER AREAS SHALL BE PROTECTED AS:
LIGHT HAZARD OCCUPANCY: 0.10 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 100 GPM
ALL SPRINKLERS WITHIN THE SMOKE ZONE SHALL BE QUICK RESPONSE SPRINKLERS.
15. CONSTRUCTION BARRIERS CONSTRUCTED ALONG MEANS OF EGRESS ALONG HEALTHCARE OCCUPANCIES (LSC CHAPTER 18 AND 19) SHALL BE CONSTRUCTED AND
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
P
.1
V
A D a y to n
I D
IQ
\T
O
C o rr e c t In fr a s tr u c ti o n
D e fe c ie n c ie s B ld g
G D
I\
D ra w in g s \2
-1 A rc h it e c tu re \1
-1 R e v it \1
.1
.0
B L
D G v
.r v t
/2
/2
:3
:1
P
M
GI102
LIFE SAFETY PLAN
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA STREET, SUITE 200
INDIANAPOLIS, IN 46202
317-800-6388
ADAM OGRZEWALLA
HEAPY ENGINEERING
1400 W DOROTHY LANE
DAYTON, OH 45409
317-800-6388
MATT GRAHAM
CORRECT INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OH 45428
552-19-102
PHIL WEST, COR
08/15/2022 AO AO
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 3/32" = 1'-0"GI102
1 LEVEL 1N
Revisions: Date:
aogrzewalla Text Box 05/02/2025
OFFICE
201A
LOUNGE
C-2-1
CHAPLAIN OFFICE
OFFICE
208E
OFFICE
208D
OFFICE
208C
OFFICE
208B
OFFICE
208F
OFFICE
208G
OFFICE
208H
OFFICE
207E
OFFICE
207D
OFFICE
107v
OFFICE
207B
AFCU SUITE
OFFICE
207F
OFFICE
207G
OFFICE
207I
OFFICE
207HTOILET
SAFETY
107dd
OFFICE
202G
OFFICE
202F
OFFICE
202E
OFFICE
202D
OFFICE
202C
OFFICE
202B
OFFICE
202A
202H
C-2-2C-2-5
C-2-3
205l
ELEV.
NO.12
NNU OFFICE
205A
NNU OFFICE
205B
SAFETY OFFICE
205G
SAFETY OFFICE
205F
SAFETY OFFICE
205E
OIT OFFICE
205D
SAFETY OFFICE
205H
NNU OFFICE
205C
OFFICE
203F
SUITE
OFFICE
203D
OFFICE
203C
OFFICE
203B
OFFICE
203A
TOILET
208A
CONFERENCE ROOM
203E
CODE ANALYSIS - NFPA 101, BUSINESS CHAPTER 38
CODE CRITERIA
GENERAL: THIS SUMMARY OF CODE REQUIREMENTS IS BASED PRIMARILY ON NFPA 101 (LSC). DESIGN FEATURES NOT ADDRESSED BY NFPA 101 OR DOCUMENTS REFERENCED THEREIN SHALL COMPLY WITH THE REQUIREMENTS OF THE LATEST EDITION OF THE IBC OR AS OTHERWISE IDENTIFIED. FOR DESIGN FEATURES THAT ARE ADDRESSED BY BOTH THE IBC AS WELL AS NFPA 101 OR A DOCUMENT REFERENCED BY NFPA 101, THE REQUIREMENTS OF NFPA 101 OR THE DOCUMENT REFERENCED BY NFPA 101 SHALL BE USED EXCLUSIVELY (THIS APPLIES EVEN IF THE IBC REQUIREMENTS ARE DIFFERENT).
LOCAL CODES: AS AN AGENCY OF THE FEDERAL GOVERNMENT, VA IS NOT SUBJECT TO LOCAL IMPOSITION OF CODE ENFORCEMENT PROCEDURES (DRAWING REVIEWS, BUILDING PERMITS, INSPECTIONS, FEES, ETC.). VA MUST FUNCTION AS THE AUTHORITY HAVING JURISDICTION (AHJ) AND THUS HAS THE RESPONSIBILITY TO GUARD
PUBLIC HEALTH AND SAFETY THROUGH ENFORCING ITS ADOPTED CODES.
NOTES:
CONFLICTS BETWEEN NATIONALLY RECOGNIZED CODES AND STANDARDS AND VA REQUIREMENTS – SHOULD A CONFLICT EXIST BETWEEN VA REQUIREMENTS AND VA ADOPTED NATIONALLY RECOGNIZED CODES AND STANDARDS, THE CONFLICT SHALL BE BROUGHT TO THE ATTENTION OF VA. THE RESOLUTION OF THE CONFLICT SHALL BE MADE BY THE AUTHORITY HAVING JURISDICTION FOR VA TO ENSURE A CONSISTENCY SYSTEM WIDE.
CODE REVIEW
THE 2021 EDITION OF THE LIFE SAFETY CODE, NFPA 101, HAS BEEN USED TO REVIEW THIS PROJECT FOR COMPLIANCE WITH THE FIRE AND LIFE SAFETY REQUIREMENTS.
FOR FEATURES NOT ADDRESSED BY NFPA 101 AND THE REFERENCED NATIONAL FIRE CODES, THE 2021 EDITION OF THE INTERNATIONAL BUILDING CODE HAS BEEN
USED.
PROJECT SCOPE
1. THE CONSTRUCTION TYPE IS DETERMINED BASED UPON THE ALLOWABLE AREA AND HEIGHT REQUIREMENTS OF CHAPTER 5 OF THE 2021 IBC. CONSTRUCTION TYPE AND MATERIALS SHALL BE PER CHAPTER 6 OF THE IBC FOR TYPE II-B CONSTRUCTION AS FOLLOWS:
2. OCCUPANCY TYPE: B-BUSINESS, IBC CHAPTER 3/LSC CHAPTER 38
3. FIRE RESISTIVE RATINGS TYPE II-B/ II(000) CONSTRUCTION, CHAPTER 6 IBC/NFPA 101:
STRUCTURAL FRAME: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
BEARING WALLS
EXTERIOR: NONCOMBUSTIBLE, 0 -HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
NON-BEARING WALLS AND PARTITIONS
EXTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
INTERIOR: NONCOMBUSTIBLE, 0-HOUR FIRE-RESISTIVE
FLOOR: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
ROOF: NONCOMBUSTIBLE, 0-HOUR FIRE RESISTIVE
SHAFT ENCLOSURES 2-HOUR FIRE RESISTIVE >4 STORIES (IBC 713.4, LSC 12.3.6)
SHAFT ENCLOSURES 1-HOUR FIRE RESISTIVE <4 STORIES (IBC 713.4, LSC 12.3.6)
4. STRUCTURAL DESIGN SHALL COMPLY WITH CHAPTER 16 OF THE IBC.
5. ALLOWABLE HEIGHT: 75 FT (IBC, TABLE 504.3)
6. ALLOWABLE NUMBER OF STORIES ABOVE GRADE PLAN: 4 (IBC, TABLE 504.4)
7. ALLOWABLE AREA: BASED UPON B OCCUPANCY, II-B CONSTRUCTION TYPE, AND FULLY SPRINKLED: ALLOWABLE AREA: 69,000 (IBC, TABLE 506.2)
8. BUILDING SEPARATION: BASED ON A >30 FIRE SEPARATION DISTANCE A 0 -HOUR FIRE RESISTANCE WALL RATING IS REQUIRED. (IBC, TABLE 602)
9. MEANS OF EGRESS
• CLEAR WIDTH OF CORRIDORS SHALL BE CLEAR 44 INCHES.
• CLEAR WIDTH OF DOORS SHALL BE CLEAR 32 INCHES
• NOT LESS THAN 2 EXITS SHALL BE PROVIDED PER FLOOR.
• ADDITION OCCUPANCY LOAD: <500 THEREFORE 2 EXITS REQUIRED (LSC 7.4.1)
• MAXIMUM TRAVEL DISTANCE, FULLY SPRINKLED: 300 FEET (LSC 38.2.6.3)
• COMMON PATH OF TRAVEL SHALL NOT EXCEED 100 FEET (LSC 38.2.5.3.1)
• DEAD END CORRIDORS SHALL NOT EXCEED 50 FEET. (LSC 38.2.5.2.1)
• MEANS OF EGRESS SHALL BE ILLUMINATED. (LSC 38.2.8)
• EMERGENCY LIGHTING SHALL BE PROVIDED, BUILDING OVER 3 STORIES. (LSC 38.2.9.1)
• EXIT SIGNAGE SHALL BE PROVIDED. (LSC 38.2.10)
10. PROTECTION FROM ANY AREA HAVING A DEGREE OF HAZARD GREATER THAN THAT NORMAL TO THE GENERAL OCCUPANCY OF THE BUILDING OR STRUCTURE SHALL BE PROVIDED BY PROTECTING THE AREA WITH AUTOMATIC EXTINGUISHING SYSTEMS IN ACCORDANCE WITH SECTION 9.7(3). WHERE HAZARD IS SEVERE PER LSC CHAPTER 38, SOILED HOLDING, PROTECTION IS PROVIDED WITH AN AUTOMATIC EXTINGUISHING SYSTEMS THE SPACE SHALL ALSO BE ENCLOSED WITH SMOKE
PARTITIONS IN ACCORDANCE WITH SECTION 8.4.
11. INTERIOR FINISH
• WALLS AND CEILINGS: INTERIOR FINISH FLAME SPREAD SHALL BE LIMITED PER CHAPTER 8 OF THE NFPA 101 TO CLASS A, B AND C MATERIALS. INTERIOR WALL
AND CEILING FINISH SHALL BE CLASS A OR CLASS B IN EXITS, CORRIDORS AND LOBBIES; AND CLASS A, CLASS B, OR CLASS C IN ALL OTHER AREAS. (LSC 38.3.3)
• · CLASS A: FLAME SPREAD 0-25; SMOKE DEVELOPED 0-450.
• · CLASS B: FLAME SPREAD 26-75; SMOKE DEVELOPED 0-450.
• · CLASS C: FLAME SPREAD 76-200; SMOKE DEVELOPED 0-450
• FLOORS: INTERIOR FLOOR FINISH SHALL BE CLASS I OR CLASS II IN CORRIDORS AND EXITS.
• FABRIC DRAPERIES, CURTAINS (EXCLUDING SHOWER CURTAINS, BUT INCLUDING CUBICLE CURTAINS), AND OTHER LOOSELY HANGING FABRICS AND FILMS
SERVING AS FURNISHINGS OR DECORATIONS IN HEALTH CARE OCCUPANCIES MUST MEET THE FLAME RESISTANCE REQUIREMENTS OF NFPA 701, STANDARD
METHODS OF FIRE TESTS FOR FLAME-RESISTANT TEXTILES AND FILMS.
• UPHOLSTERED FURNITURE AND MATTRESSES. UPHOLSTERED FURNITURE AND MATTRESSES MUST ALSO MEET SPECIFIED REQUIREMENTS, BASED ON NFPA
260, NFPA 261, NFPA 266, 16 CFR 1632, ASTME E1537, AND ASTME E1590
12. EXTINGUISHMENTS REQUIREMENTS, PORTABLE FIRE EXTINGUISHERS SHALL BE PROVIDED PER NFPA 10. (38.3.5)
13. DETECTION, ALARM, AND COMMUNICATIONS SYSTEMS.
• FIRE ALARM SYSTEM SHALL BE PROVIDED LSC, NFPA 70 (NEC) AND NFPA 72. (LSC 9.6.1)
• FIRE ALARM MAY BE BY MANUAL MEANS (LSC 38.4.2)(LSC 9.6.2)
• OCCUPANT NOTIFICATION SHALL BE THROUGH AUTOMATIC MEANS. (LSC 38.3.4.3)
• SMOKE DETECTION SHALL BE PROVIDED PER NFPA 72.
• EMERGENCY RESPONDER NOTIFICATION SHALL BE NOTIFIED BY ALARM AND DETECTION SYSTEM. (LSC 38.3.4.4)
14. FIRE SUPPRESSION:
SPRINKLER SYSTEM: BUILDING IS REQUIRED TO BE SPRINKLED THROUGHOUT IN ACCORDANCE WITH NFPA 13.
THE SPRINKLER SYSTEM SHALL BE HYDRAULICALLY DESIGNED IN ACCORDANCE WITH 2013 EDITION OF NFPA 13 AND THE SIXTH EDITION OF THE DEPARTMENT OF
VETERANS AFFAIRS FIRE PROTECTION DESIGN MANUAL: MINIMUM DESIGN REQUIREMENTS:
STORAGE MECHANICAL AND ELECTRICAL ROOMS SHALL BE PROTECTED AS:
ORDINARY HAZARD OCCUPANCY, GROUP 1: 0.15 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 250 GPM
ALL OTHER AREAS SHALL BE PROTECTED AS:
LIGHT HAZARD OCCUPANCY: 0.10 GPM/FT2 OVER 1,500 FT2.
HOSE STREAM ALLOWANCE: 100 GPM
ALL SPRINKLERS WITHIN THE SMOKE ZONE SHALL BE QUICK RESPONSE SPRINKLERS.
15. CONSTRUCTION BARRIERS CONSTRUCTED ALONG MEANS OF EGRESS ALONG HEALTHCARE OCCUPANCIES (LSC CHAPTER 18 AND 19) SHALL BE CONSTRUCTED AND
CODE ANALYSIS LEGEND
TOTAL OCCUPANCY
FEC
EXIT
OCCUPANCY LOAD FACTOR
EXITS REQUIRED
SQUARE FOOTAGE
OCCUPANCY TYPE
EGRESS EXIT SIGNAGE
FIRE EXTINGUISHER CABINET
DIAGONAL DISTANCE
EXIT SEPARATION DISTANCE
EGRESS PATH
2 HR - FIRE SEPARATION
1 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREA
B
1500 SF
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
P
.1
V
A D a y to n
I D
IQ
\T
O
C o rr e c t In fr a s tr u c ti o n
D e fe c ie n c ie s B ld g
G D
I\
D ra w in g s \2
-1 A rc h it e c tu re \1
-1 R e v it \1
.1
.0
B L
D G v
.r v t
/2
/2
:3
:1
P
M
GI103
LIFE SAFETY PLAN
GUIDON DESIGN INC.
1221 N. PENNSYLVANIA STREET, SUITE 200
INDIANAPOLIS, IN 46202
317-800-6388
ADAM OGRZEWALLA
HEAPY ENGINEERING
1400 W DOROTHY LANE
DAYTON, OH 45409
317-800-6388
MATT GRAHAM
CORRECT INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OH 45428
552-19-102
PHIL WEST, COR
08/15/2022 AO AO
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 3/32" = 1'-0"GI103
1 LEVEL 2
N
Revisions: Date:
aogrzewalla Text Box 05/02/2025
DN
TEMPORARY IC BARRIER WALL
CONSTRUCTION (DUST WALL)
5/8" TYPE X GYP BD
3 5/8" STEEL STUDS @ 16"
O.C.
BEAD OF CONT. SEALANT
6-MIL FIRE RETARDANT POLY
INTERIOR SIDE
CEILING
2" DEEP LEG 3 5/8" STEEL SLIP TRACK
3 5/8" STEEL STUD TRACK
6" M
IN
CONTINUOUSLY ADHERE 6-MIL. FIRE
RETARDANT POLY TO DECK WITH TAPE
CONTINUOUSLY ADHERE FIRE RETARDANT
POLY TO FLOOR WITH TAPE
EXISTING DECK
CONSTRUCTION
SIDE
OCCUPIED
SIDE
PUBLIC
SIDE
1 HOUR FIRE RATED METAL DOOR ASSEMBLY
AND FRAME WITH SEALS, CARD READER,
HARDWARE AND CLOSER
TRIATEK MONITOR
HAND SANITIZER
SEAL ALL EDGES WITH TAPE
SEAL ALL EDGES WITH TAPE
REFER TO TEMPORARY BARRIER TYPE
FOR REQUIRED CONDITION TO
STRUCTURE ABOVE
VA / OSHA TEMPORARY SIGNAGE
UNEXCAVATED
SPRINKELR SYSTEM
CONTROLS
205J
PIPE SPACE
205K
UNEXCAVATED
UNEXCAVATED
Room
205N
UNEXCAVATED UNEXCAVATED
CONCRETE SLAB
Room
205R
PIPE SPACE
STORAGE
ENGINEERING
STORAGE ROOM
ELEV.
NO.12
MACHINE ROOM
LOCKSMITH
C-B-1
C-B-2
CLEAR
6' - 0"
2PHASE 1
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
TEMPORARY PLASTIC BARRIER. SEE PLAN
AND PLAN NOTES
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: LOW
CLASS OF PRECAUTION MATRIX: II
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH CARD
READER ACCESS. REFER TO ELEVATION 3/GI104.
PROVIDE TEMPORARY INFECTION CONTROL BARRIER WALL CONSTRUCTION.
REFER TO DETAIL 2/GI104.
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL INFORMATION.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
PROJECT SHALL BE COMPLETED IN 4 PHASES.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR,
NURSING STAFF AND OCCUPANTS BEFORE CONSTRUCTION MAY BEGIN.
PROVIDE PHASING INFORMATION FOR ABOVE CEILING WORK IN THE
CONTRACTOR PROVIDED CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE
AND BELOW THE FLOOR PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANNER UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36" STICKY
WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION.
MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
INFECTION CONTROL GENERAL NOTES
PHASING GENERAL NOTES #
A
B
C
PROJECT AREAS TO BE OCCUPIED BY STAFF AND VETERANS THROUGHOUT
CONSTRUCTION.
CONSTRUCTION WORK BEHIND TEMPORARY CONSTRUCTION PARTITIONS
SHALL BE COMPLETED DURING REGULAR SHIFTS, 8:00 AM TO 5:00 PM.
REFER TO SPECIFICATION 01 00 00 FOR INFORMATION ON WORK DURATION
FOR EACH PHASE AND AREA OF WORK.
PROJECT PHASING
PHASE 1:
CONTRACTOR SHALL MOBILIZE AND RESEARCH / INVESTIGATE
EXISTING CONDITIONS AND ALL UTILITIES (NEW AND ONES TO BE
RELOCATED) AT THE SITE. ALL SUBMITTALS, REVIEWS, AND
APPROVALS SHALL BE COMPLETED DURING PHASE 1 AND PRIOR TO
BEGINNING OF PHASE 2, INCLUDING MEPTF SYSTEMS AND
TECHNOLOGY SUBMITTALS. COMPLETE ALL BASEMENT WORK AND
NEW MEPTF SYSTEMS WORK TO SUPPORT THE SUBSEQUENT
PHASES.
PHASE 2:
CONSISTS OF ALL WORK TO RENOVATE THE MEPTF SYSTEMS, ABATE
HAZARDOUS MATERIALS, AND THE REPLACEMENT OF THE WINDOWS
AND DOORS THROUGHOUT THE AREA IDENTIFIED IN THE DRAWINGS
THROUGH THE CENTRAL SECTION OF THE BUILDING.
PHASE 3:
CONSISTS OF ALL WORK TO RENOVATE THE MEPTF SYSTEMS, ABATE
HAZARDOUS MATERIALS, AND THE REPLACEMENT OF THE WINDOWS
AND DOORS THROUGHOUT THE AREA IDENTIFIED IN THE DRAWINGS
THROUGH THE NORTHERN WING OF THE BUILDING.
PHASE 4:
CONSISTS OF ALL WORK TO RENOVATE THE MEPTF SYSTEMS, ABATE
HAZARDOUS MATERIALS, AND THE REPLACEMENT OF THE WINDOWS
AND DOORS THROUGHOUT THE AREA IDENTIFIED IN THE DRAWINGS
THROUGH THE SOUTHERN WING OF THE BUILDING.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
P
.1
V
A D a y to n
I D
IQ
\T
O
C o rr e c t In fr a s tr u c ti o n
D e fe c ie n c ie s B ld g
G D
I\
D ra w in g s \2
-1 A rc h it e c tu re \1
-1 R e v it \1
.1
.0
B L
D G v
.r v t
/2
/2
:3
:2
P
M
GI104
INFECTION CONTROL/PHASING
PLANGUIDON DESIGN INC.
1221 N. PENNSYLVANIA STREET, SUITE 200
INDIANAPOLIS, IN 46202
317-800-6388
ADAM OGRZEWALLA
HEAPY ENGINEERING
1400 W DOROTHY LANE
DAYTON, OH 45409
317-800-6388
MATT GRAHAM
CORRECT INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OH 45428
552-19-102
PHIL WEST, COR
08/15/2022
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1 1/2" = 1'-0"GI104
2 TEMPORARY INFECTION CONTROL BARRIER WALL CONSTRUCTION
SCALE: 1/4" = 1'-0"GI104
3 TEMPORARY WALL CONSTRUCTION ELEVATION
SCALE: 1/8" = 1'-0"GI104
4 BASMENT INFECTON/CONTROL PAHSING PLAN
N
Revisions: Date:
aogrzewalla Text Box 05/02/2025
CONFERENCE
103C
OFFICE
OFFICE
103D
OFFICE
103A
OFFICE
TELE PHARMACY
MENS
OFFICE LOBBY
109A
COMM.
103B
LOBBY
OFFICE
101C
ACQUISITION
CHAPLAIN
101OFFICE
101D
OFFICE
101A
KITCHEN
OFFICE
106k
OFFICE
106l
OFFICE
106h
OFFICE
106g
DSS SUITE
OFFICE
106e
STORAGE
106d
OFFICE
106a
OFFICE
106j
OFFICE
106f
COPIER
106c
OFFICE
106b
OPEN OFFICE
OFFICE
100d
OFFICE
100c
OFFICE
100h
OFFICE
100k
OFFICE
100j
OFFICE
100l
WOMENS
OFFICE
100n
OFFICE
100g
OFFICE
100m
CONFERENCE
107f
OFFICE
107g
OFFICE
107a
OFC
107c
OFC
107d
OFC
107e
OFC
107b
SUITE
COMM
101B
OFFICE
109C
PHASE 2
1' - 11"
4'
3PHASE 4
PHASE 3
IC/PHASING LEGEND
TEMPORARY WALLS. SEE PLAN AND
PLAN NOTES
TEMPORARY CONSTRUCTION ACCESS
DOORS
REFERENCE AREA FOR ABOVE
CEILING WORK ON FLOOR BELOW.
REFER TO ENGINEERING DRAWINGS
FOR FULL SCOPE OF WORK
BEYOND PROJECT BOUNDARY
PROJECT BOUNDARY
TEMPORARY PLASTIC BARRIER. SEE PLAN
AND PLAN NOTES
INFECTION CONTROL PLAN NOTES #
INFECTION CONTROL PROJECT INFORMATION
CONSTRUCTION ACTIVITY - FIRE RISK: TYPE C
PATIENT RISK GROUP: LOW
CLASS OF PRECAUTION MATRIX: II
PROVIDE TEMPORARY INFECTION CONTROL CONSTRUCTION DOOR WITH CARD
READER ACCESS. REFER TO ELEVATION 3/GI104.
PROVIDE TEMPORARY INFECTION CONTROL BARRIER WALL CONSTRUCTION.
REFER TO DETAIL 2/GI104.
PROVIDE TEMPORARY INFECTION CONTROL PLASTIC BARRIER WALL
CONSTRUCTION. REFER TO SPECIFICATION FOR ADDITIONAL INFORMATION.
REFER TO LIST OF REQUIRED INFECTION CONTROL PRECAUTIONS OUTLINED
BY CLASS IN SPECIFICATION 010110 AND ADDITIONAL INFORMATION.
REFER TO DRAWINGS, SPECIFICATIONS AND DOOR HARDWARE SCHEDULE
FOR ADDITIONAL INFORMATION.
PROJECT SHALL BE COMPLETED IN 4 PHASES.
COORDINATE FULL SCOPE OF WORK WITH ENGINEERING DRAWINGS AND
FIELD VERIFICATION. CONTRACTOR IS RESPONSIBLE FOR SCOPE OF ABOVE
CEILING WORK REQUIRED ABOVE AND BELOW THE FLOOR PLATE OF THE
PROJECT BOUNDARY.
COORDINATE LOCATION OF TEMPORARY INFECTION CONTROL (IC) BARRIER
WALL CONSTRUCTION AND INFECTION CONTROL (IC) MEASURES WITH COR
AND PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE. TEMPORARY
IC BARRIER WALL CONSTRUCTION LOCATIONS IN DRAWINGS ARE
APPROXIMATE. CONTRACTOR SHALL PROVIDE DRAWING TO COR AND
PATIENT SAFETY/ INFECTION CONTROL REPRESENTATIVE ONCE ICRA
PROTOCOLS AND PLAN IS APPROVED.
SCHEDULE AND TIME OF CONSTRUCTION WORK TO BE APPROVED BY COR,
NURSING STAFF AND OCCUPANTS BEFORE CONSTRUCTION MAY BEGIN.
PROVIDE PHASING INFORMATION FOR ABOVE CEILING WORK IN THE
CONTRACTOR PROVIDED CMP SCHEDULE FOR WORK ALSO REQUIRED ABOVE
AND BELOW THE FLOOR PLATE OF THE PROJECT BOUNDARY.
ABOVE CEILING WORK SHALL TAKE PLACE BETWEEN THE HOURS OF 5:00 PM
AND 5:00 AM. IN AREAS THAT REQUIRE ABOVE CEILING WORK WHERE
CEILINGS ARE TO REMAIN, CEILING TILES SHALL BE REMOVED AND STORED IN
A SAFE MANNER UNTIL CEILING TILES CAN BE REINSTALLED. DAMAGED AND
BROKEN CEILING TILES SHALL BE REPLACED BY CONTRACTOR.
EXIT/ACCESS FOR ADJACENT OPERATIONAL AREAS SHALL BE MAINTAINED
DURING NORMAL BUSINESS HOURS. SEE SPECIFICATION FOR HOURS OF
OPERATION.
WORK REQUIRING VIBRATION OR LOAD NOISE SHALL TAKE PLACE BETWEEN
THE HOURS OF 5:00 PM AND 5:00 AM. EVERY EFFORT SHALL BE MADE TO
KEEP NOISE AND VIBRATION TO A MINIMUM.
PROVIDE THE FOLLOWING INFECTION CONTROL MEASURES, A 24"X36" STICKY
WALK OFF MAT AND HAND SANITIZER AT EACH TEMPORARY DOOR LOCATION.
MAT SHALL BE REPLACED OR CLEANED AS NECESSARY
PROVIDE THE VA AND OSHA REQUIRED TEMPORARY SIGNAGE AT EACH
TEMPORARY DOOR LOCATION.
CONTRACTOR SHALL SUPPLY SPILL KIT. SPILL KIT TO INCLUDE SHOP VAC,
MULTI-PURPOSE SPILL CONTROL SORBENTS TO ABSORB NON AGGRESSIVE
LIQUIDS UP TO 30 GALLONS.
ALL DEMOLITION MATERIAL SHALL BE REMOVED FROM THE PROJECT
BOUNDARY THROUGH THE FACILITY TO DUMPSTER ALONG VA APPROVED
ROUTE IN ENCLOSED DUMPSTER CART DESIGNED FOR SUCH PURPOSED
WITH A LID.
ALL MATERIAL, DEBRIS AND HAZARDOUS MATERIALS SHALL BE PROPERLY
STORED IN DESIGNATED AREAS AND APPROVED CONTAINERS. FLAMMABLE
MATERIALS SHALL NOT BE STORED IN THE FACILITY.
PROVIDE CONTAINMENT CART FOR ABOVE CEILING ACCESS OUTSIDE
PROJECT BOUNDARY.
A
B
C
D
E
F
G
H
I
J
K
L
M
N
O
INFECTION CONTROL GENERAL NOTES
PHASING GENERAL NOTES #
A
B
C
PROJECT AREAS TO BE OCCUPIED BY STAFF AND VETERANS THROUGHOUT
CONSTRUCTION.
CONSTRUCTION WORK BEHIND TEMPORARY CONSTRUCTION PARTITIONS
SHALL BE COMPLETED DURING REGULAR SHIFTS, 8:00 AM TO 5:00 PM.
REFER TO SPECIFICATION 01 00 00 FOR INFORMATION ON WORK DURATION
FOR EACH PHASE AND AREA OF WORK.
PROJECT PHASING
PHASE 1:
CONTRACTOR SHALL MOBILIZE AND RESEARCH / INVESTIGATE
EXISTING CONDITIONS AND ALL UTILITIES (NEW AND ONES TO BE
RELOCATED) AT THE SITE. ALL SUBMITTALS, REVIEWS, AND
APPROVALS SHALL BE COMPLETED DURING PHASE 1 AND PRIOR TO
BEGINNING OF PHASE 2, INCLUDING MEPTF SYSTEMS AND
TECHNOLOGY SUBMITTALS. COMPLETE ALL BASEMENT WORK AND
NEW MEPTF SYSTEMS WORK TO SUPPORT THE SUBSEQUENT
PHASES.
PHASE 2:
CONSISTS OF ALL WORK TO RENOVATE THE MEPTF SYSTEMS, ABATE
HAZARDOUS MATERIALS, AND THE REPLACEMENT OF THE WINDOWS
AND DOORS THROUGHOUT THE AREA IDENTIFIED IN THE DRAWINGS
THROUGH THE CENTRAL SECTION OF THE BUILDING.
PHASE 3:
CONSISTS OF ALL WORK TO RENOVATE THE MEPTF SYSTEMS, ABATE
HAZARDOUS MATERIALS, AND THE REPLACEMENT OF THE WINDOWS
AND DOORS THROUGHOUT THE AREA IDENTIFIED IN THE DRAWINGS
THROUGH THE NORTHERN WING OF THE BUILDING.
PHASE 4:
CONSISTS OF ALL WORK TO RENOVATE THE MEPTF SYSTEMS, ABATE
HAZARDOUS MATERIALS, AND THE REPLACEMENT OF THE WINDOWS
AND DOORS THROUGHOUT THE AREA IDENTIFIED IN THE DRAWINGS
THROUGH THE SOUTHERN WING OF THE BUILDING.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
Office of Construction and Facilities Management
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD
A/E:
STAMPCONSULTANT
321 4 5 6 7 8 9 10
Consultant:
P
.1
V
A D a y to n
I D
IQ
\T
O
C o rr e c t In fr a s tr u c ti o n
D e fe c ie n c ie s B ld g
G D
I\
D ra w in g s \2
-1 A rc h it e c tu re \1
-1 R e v it \1
.1
.0
B L
D G v
.r v t
/2
/2
:3
:2
P
M
GI105
INFECTION CONTROL/PHASING
PLANGUIDON DESIGN INC.
1221 N. PENNSYLVANIA STREET, SUITE 200
INDIANAPOLIS, IN 46202
317-800-6388
ADAM OGRZEWALLA
HEAPY ENGINEERING
1400 W DOROTHY LANE
DAYTON, OH 45409
317-800-6388
MATT GRAHAM
CORRECT INFRASTRUCTURE
DEFICIENCIES, B408
DAYTON, OH 45428
552-19-102
PHIL WEST, COR
08/15/2022 AO JP
100% CONSTRUCTION
DOCUMENTS
FULLY SPRINKLERED
SCALE: 1/8" = 1'-0"GI105
1 FIRST FLOOR INFECTON/CONTROL PAHSING PLAN
N
Revisions: Date:
aogrzewalla Text Box 05/02/2025
| 2018-05164_Div23_Dwgs |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
| MD100 - BASEMENT FLOOR PLAN - REMOVALS |
| MD101 - FIRST FLOOR PLAN - REMOVALS |
| MD102 - SECOND FLOOR PLAN - REMOVALS |
| MD103 - ATTIC FLOOR PLAN - REMOVALS |
| MH100 - BASEMENT FLOOR PLAN - DUCTWORK |
| MH101 - FIRST FLOOR PLAN - DUCTWORK |
| MH102 - SECOND FLOOR PLAN - DUCTWORK |
| MH103 - ATTIC FLOOR PLAN - DUCTWORK |
| MP100 - BASEMENT FLOOR PLAN - PIPING |
| MP101 - FIRST FLOOR PLAN - PIPING |
| MP102 - SECOND FLOOR PLAN - PIPING |
| MP103 - ATTIC FLOOR PLAN - PIPING |
| M001 - LEGEND, ABBREVIATIONS & INDEX OF DRAWINGS |
| M401 - ENLARGED PLANS |
| M501 - DETAILS |
| M502 - DETAILS |
| M503 - DETAILS |
| M504 - HYDRONIC PIPING SCHEMATICS |
| M505 - STEAM PIPING SCHEMATIC |
| M601 - SCHEDULES |
| M602 - SCHEDULES |
| M603 - SCHEDULES |
| M701 - CONTROLS AND AUTOMATION |
| M702 - CONTROLS AND AUTOMATION |
This is the start of the file's text. The full file is on GovTribe.