5_EWP_PrebidNotesIssued10132025.pdf
PDF 98 KB Posted
- Solicitation number
- PE-66249-NONST-2026-000000060
- Issued by
- Lanier County, Georgia
About this file
This is a pre-bid meeting memorandum issued by the City of Valdosta Engineering Department regarding an Emergency Watershed Protection Grant project. The project involves stream cleaning across three work areas: Sugar Creek, Two Mile Branch, and Three Mile Branch. The scope of work includes removal of debris and vegetation from stream beds and banks using hand labor and hand equipment only, with no mechanical equipment permitted in the streams per NRCS requirements. Work must be completed by January 16, 2026, as mandated by the Grant conditions. The project is structured as a unit cost contract with payment based on linear feet of stream cleaned, including all associated labor, equipment, materials, mulching, and grassing. A mandatory pre-bid meeting was held on October 7, 2025, with bid opening scheduled for October 23, 2025 at 10:00 a.m. in the City of Valdosta Engineering offices. Bids will be presented to City Council on the same day at 5:30 p.m. Requests for Information must be submitted by email to Charlie Clark and Chelsea Nevels by 5:00 p.m. on October 16, 2025. Site visits of the stream segments are available by contacting Angela Bray.
The contract is funded through a $1,020,000 Emergency Watershed Protection Grant, with the project scope subject to adjustment based on the lowest bid received to ensure the project remains within the available grant funding. The City has obtained no rights-of-entry prior to the project, requiring the contractor to acquire easements and right-of-entry from private property owners; however, the contractor bears no penalization if unable to obtain such access. Liquidated damages have been removed from the contract terms. Disposal of materials is the contractor's responsibility, with no burning permitted within city limits; mulching is the preferred disposal method. The City is investigating preferential pricing with a local firm for material disposal. Alternate bid items are available to assist in obtaining right-of-entry at the owner's discretion. No minority business or disadvantaged business requirements are specified in the grant or contract. An addendum correcting completion dates and removing utility contractor licensing requirements has been issued.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ENGINEERING DEPARTMENT
City Hall Annex • Post Office Box 1125 • 300 N. Lee Street • Valdosta, GA 31603-1125 Telephone (229) 259-3530 • Fax (229) 333-1884
An Equal Opportunity Employer
MEMORANDUM
Project: Emergency Watershed Protection Grant -City of Valdosta Regarding: Mandatory 10/07/2025 Pre-Bid Meeting - Notes Issue Date: 10/13/2025
The following is a summary of key facts and issues covered during the pre-bid meeting:
1. Bid opening is Thursday October 23, 2025 at 10am in the City of Valdosta Engineering offices. Bids will be presented to City Council on October 23, 2025 at their regular meeting session which begins at 5:30 pm at City Hall.
2. Scope of work was presented by Charlie Clark. There are 3 work areas as shown on the construction plans (Sugar Creek, Two Mile Branch and Three Mile Branch). Some stream segments are narrow with shallow water depth and narrow. Angela Bray encouraged bidders to contact her to walk stream segments to view the scope of work.
3. Schedule for work has a complete date of January 16, 2026. (note, the EWP Grant requires that all work must be completed on January 16, 2026.
An addendum is being issued along with these notes correcting the completion date on all documents).
4. The Alternate Bid items listed in the Unit Cost Schedule/Bid Form are to assist in obtaining Right-of-Entry from private property owners. These items will be approved at the Owner’s discretion and direction, and do not apply to direct stream cleaning activities.
5. This is a Unit Cost Contract- quantities are tracked per unit. Stream cleaning is paid on a linear foot basis, and includes all equipment, materials, labor, mulching, grassing and other costs associated with work in and alongside the stream bed.
6. Right-of-way and easement information: Easement/Right-of-Entry to be acquired by the contractor. The City has obtained no rights-of-entry prior to this project’s contract.
7. The EWP Grant requirements set the project time, scope and limitations.
8. Liquidated damages: Although a higher liquidate damage amount was discussed during the Pre-Bid Meeting, liquidated damages are being removed from the contract. Given the January 16, 2026 Grant Completion Date, any areas not cleaned by that date will be left as is.
Engineering Department
Memorandum
City Hall Annex • Post Office Box 1125 • 300 N. Lee Street • Valdosta, GA 31603-1125 Telephone (229) 259-3530 • Fax (229) 333-1884
An Equal Opportunity Employer
9. Based upon the low bid received and upon the available Grant Funding ($1,020,000), the City will adjust the scope of the stream cleaning to bring the project within the Grant Budget.
10. The Utility Contract Licensing requirement is removed from the bidding and contract requirements. Addendum #1 documents reflect this change.
11. Any correspondence for contractual communication must be received in writing. Email is considered “in writing”.
12. No equipment is allowed in stream beds. This is a hard direction received from NRCS. Stream bed and banks must be undamaged. Work must be completed by hand or with hand equipment, and debris must be carried out and pulled out.
13. There were questions regarding the tight timeline discussion. City staff has subsequently contacted NRCS, and there is no expectation for a tiem extension.
14. There is no penalization on the contractor due to inability to obtain property owner rights-of-entry.
15. Disposal: No burning is allowed within city limits. Disposal is the contractor’s responsibility. Mulching is a viable/preferred option.
16. City staff is investigating the option for disposal of wood and vegetative materials at the City’s preferred pricing for the contractor with a local firm (Greenworld). If that information is available prior to the end of this week (10/17/2025), another addendum will be issued with that pricing.
17. There are no requirements for minority business, disadvantages business requirements, etc. in the Grant or in the Contract.
18. Please submit questions and Requests for Information (RFI’s) by email to both Charlie Clark (chclark@valdostacity.com ) and Chelsea Nevels (cnevels@valdostacity.com ). Questions will be received until close of business, 5:00pm local time, on Thursday, 10/16/2025.
These notes are taken from the hand notations and the memory of the writer.
Please report any significant errors or oversights to the writer by no later than close of business, 5:00pm local time, on Thursday, 10/16/2025.
Submitted: Charlie Clark, P.E.
Engineering Services Manager mailto:chclark@valdostacity.com mailto:cnevels@valdostacity.com