This is Addendum #1 to an Invitation to Bid issued by the Florida Department of Military Affairs, Construction & Facility Management Office, for the 4800 Area Paving project at Camp Blanding Joint Training Center in Starke, Florida. The addendum modifies the original bidding documents for Projects 220016 and 220017, which consist of repaving three avenues (Plant City, Melbourne, and Quincy) and four streets (Pensacola, Westerly, Rutland, and Eustis), including culvert replacement on a like-for-like basis, milling of existing asphalt, and two-lift asphalt paving operations. The original Invitation to Bid was issued on July 21, 2026, with a bid opening scheduled for September 9, 2026, at 2:00 p.m. Eastern Time. A mandatory pre-bid site visit and meeting was held on August 5, 2026, and questions were due by August 19, 2026. Acknowledgement of this addendum in the Bid Proposal form is required.

The addendum's primary modification addresses substantial completion and liquidated damages requirements. The project must be substantially completed within 180 calendar days after the Notice to Proceed, with liquidated damages assessed at $216.20 per calendar day for failure to meet this deadline. The addendum includes comprehensive Questions and Answers addressing bidder inquiries regarding work hours (0700–1630 hours, including Alternative Work Schedule Mondays), permit requirements (none required), site visit access procedures, ditch cleaning specifications, testing protocols for open cuts, milling delivery procedures, intersection turn radius requirements, pavement section specifications (8" stabilized fill, 6" lime rock, 3" asphalt 12.5 mix), striping requirements (6" white edge lines and 6" single solid yellow centerlines in standard paint with reflective crystals), and various technical clarifications. The contractor is responsible for conducting its own culvert count, performing quality control testing in accordance with FDOT specifications, and providing As-Built documentation limited to culvert locations, sizes, and invert elevations. Existing 12-foot-wide roads must be widened to 20 feet and brought to current standards before paving.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Army National Guard

Construction & Facility Management Office

ISSUED ADDENDUM

Rev. 11/2018

Date August 26, 2026

ADDENDUM Number 1

Project Number and Name 4800 Area Paving – CBJTC SR16

Invitation to Bid Date July 21, 2026

Number of Attachments 1

Bid Opening Date and Time September 9, 2026, 2:00 p.m. Eastern

From: Department of Military Affairs, CFMO Contracting Office

This addendum and the listed attachments forms a part of the contract documents and modifies the original bidding documents. Acknowledgement of this addendum in Exhibit 4 - Bid Proposal form is required.

Concerns with this addendum should be addressed to:

ng.fl.flarng.list.cfmo-contracting@army.mil

Answers to Questions (Q) / Clarifications (C) / Modifications (M)

M. SUBSTANTIAL COMPLETION AND LIQUIDATED DAMAGES: Section C-7 is amended in part as follows: This Project is to be substantially complete within -180-calendar days after the date of the Notice to Proceed. This date may be extended only in accordance with the Contract Documents. If the project is not substantially completed by the required date, liquidated damages shall be assessed at the rate of $ 216.20 per calendar day.

Attachment List

Questions & Answers See Updated Map Below

END OF ADDENDUM #1

mailto:ng.fl.flarng.list.cfmo-contracting@army.mil

QUESTIONS AND ANSWERS

4800 Area Paving

Q. Please confirm approved daily work hours and if Contractor can work on Mondays as it relates to the Alternative Work Schedule.

A. Approved daily work hours are 0700 through 1630 to include AWS Mondays.

Q. Please confirm that permits are not required for this project.

A. Permits are not required for this project.

Q. Please advise the process for Contractor and Subcontractors to gain access for site visits to obtain measurements and culvert inspection.

A. Contractor may request access for site visits via the DPW Mail Group (NG FL FLARNG List CBJTC DPW Construction ng.fl.flarng.list.cbjtc-dpw-construction@army.mil ).

Q. Project Note 3. requires Contractor to "clean roadside ditches". Please define the expectations.

A. Excess material in ditches to be removed along newly paved sections. The depth should be from the inverts of culverts and maintains a positive flow.

Q. Project Note 3. indicates that the Contractor is responsible for repairing damage caused by its operations.

Please confirm that any pre-existing cracking, settlement, spalling, erosion, or other damage to existing concrete-lined ditches is considered existing site conditions and is not the responsibility of the Contractor.

A. Pre-existing damaged areas not caused by the contractor will not be their responsibility unless defined in the project bid documents. Existing conditions are to be captured by contractor before area of work begins.

Q. Project Note 4. requires testing of existing open cuts on avenues. If an existing open cut is found to be deficient, please clarify the method of compensation to remediate. Will remediation be considered incidental to the contract, or will it be addressed through a contract modification/change order?

A. Remediation will be considered incidental to the contract.

Q. Does Project Note 4. apply to open cuts located on “streets”?

A. Yes – Project Note 4 applies to “streets”.

Q. Project Note 6. require millings to be delivered to a location on base. Please advise if Contractor is only obligated to dump and that millings will be pushed into piles by others.

A. Contractor will only dump the millings. Camp Blanding will push up the pile.

Q. Project Note 7 requires a 30-foot minimum turn radius at intersections. For bidding purposes, please identify each specific intersection within the project limits that are required to be modified to achieve the 30-foot minimum radius. Please provide the anticipated limits of widening for each affected intersection. As this is a lump-sum proposal, identifying the required locations will help ensure all bidders are pricing the same scope of work.

mailto:ng.fl.flarng.list.cbjtc-dpw-construction@army.mil

A. Each roadway intersection must be a 30’ radius due to the type of vehicles in use. Contractor is only responsible for their newly paved portions.

Q. For open-cut restoration and intersection widening, will the Owner consider a full-depth asphalt pavement section consisting of 9" asphalt base and 3" SP-12.5 surface course? If not, please provide the required pavement section to be used for bidding purposes.

A. 8” stabilized fill, 6” lime rock, 3” asphalt 12.5 mix.

Project Note 9 states "All Avenues will be re-striped with center line and edge markings. No reflectors." Please clarify the pavement marking requirements for both the Avenues and Streets projects. Specifically:

Q. Does the striping requirement apply to Project 220024 (Streets)?

A. Yes.

Q. Please confirm the required line types, widths, and colors for centerlines and edgelines.

A. 6” white for edge lines. 6” single/solid yellow for centerlines.

Q. Please advise whether centerlines shall be single yellow or double yellow.

A. Single solid yellow lines.

Q. Please advise of the required pavement marking material (FDOT standard paint, FDOT durable paint, or FDOT thermoplastic).

A. Standard paint with reflective crystals.

Q. Are temporary painted markings required between paving operations and thermoplastic (if required)?

A. Not required.

Q. Please confirm whether existing stop bars, crosswalks, and other pavement markings are to be replaced, and whether markings not currently present are required to be installed as part of this contract.

A. Stop bars, crosswalks and other pavement markings are to be replaced. Yes, stop bars and markings not currently present are required to be installed.

Q. Please confirm if RPMs are required for fire hydrants.

A. Not Required.

Q. Is there a cost to the Contractor for background checks?

A. There is no cost to the Contractor for background checks.

Paving scope:

Q. Is milling required prior to the placement of the 1.50” of leveling?

A. Yes, mill prior to placement of leveling.

Q. What is the control point for cross slope correction? Edge of pavement or centerline?

A. Centerline.

Q. If paving operations create an increase in elevation, please confirm that dropoff treatment at edge of pavement is excluded.

A. Treatment is excluded.

Q. Please confirm PG 76-22 is not required.

A. PG 76-22 is required.

Q. Please clarify whether the 90-calendar-day contract time for the 3600 Area Paving project remains unchanged if the same contractor is awarded multiple DMA paving projects currently out for bid. If multiple awards are made to one contractor, will additional contract time be considered, or will each project's contract duration run concurrently from its respective Notice to Proceed?

A. The 90-calendar-day contract time is specific and unchanged for each contract, however the scheduling of the “start” (Notice to Proceed) will be staggered according to the specific needs, once awarded.

Q. Please clarify whether fire hydrants are available for Contractor use with Contractor provided water meter.

A. Fire hydrants are available for Contractor use with a contractor-provided backflow preventer.

Q. The Supplemental Terms and Conditions require the Contractor to provide a project sign and state that it shall conform to the size, colors, and design specifications provided by the Owner. The bid documents do not appear to include the referenced sign design requirements. Please provide the required sign detail/template.

A. Project sign is not required.

Q. Please confirm whether Builder’s Risk Insurance is required for this paving project. The work consists primarily of roadway milling, asphalt paving, and related site improvements, and no building construction is included. If Builder’s Risk coverage is required, please provide the minimum coverage and deductible requirements applicable to this scope of work.

A. Please see General Terms & Conditions C-3 for details. (4) Builder's Risk Insurance, All Risks Form:

To be issued on a completed value basis. Installation Floaters and other Inland Marine Forms may be utilized where applicable and are in the best interest of Owner.

Q. The Scope of Work requires the Contractor to perform all required inspections and testing, and the General Terms & Conditions indicate that certain required tests are the Contractor’s responsibility. Please confirm that Contractor-performed quality control testing in accordance with applicable FDOT specifications and requirements is acceptable for this project. Further, please confirm that the Contractor is not required to retain an independent third-party testing agency.

A. Applicable FDOT specifications and requirements are acceptable for this project. Compaction densities at any new subgrade mods are required.

Q. Please confirm whether As‑Built documentation is required for this project. If required, please provide the required format and deliverables and clarify whether the Owner will furnish existing CAD/base files for use in preparing record drawings, or if creation of all As‑Built documentation and CAD files is the Contractor's responsibility.

A. The only As-Built documentation that will be required will be the location/size of the culverts (i.e., Google Earth image with locations marked) to include invert elevations.

Q. Quincy Avenue and Wauchula Avenue contain approximately ten existing driveways. Please confirm that the Contractor's responsibility is limited to tying the proposed roadway pavement into the existing driveway surfaces as necessary to provide a smooth transition.

A. Confirmed

Q. Will the Owner extend the question cutoff date and postpone the bid due date until bidders are provided an opportunity to conduct a drainage survey and field quantity verification? We are currently waiting for authorization to schedule a site visit for these activities. Last year, the Owner accommodated bidders by providing two appointment windows for additional site access.

A. Owner will not extend the question cutoff date nor the bid due date, however follow-up site visits can be set up thru the Owner via the group email address: NG FL FLARNG List CBJTC DPW Construction ng.fl.flarng.list.cbjtc-dpw-construction@army.mil

Q. As requested at the pre-bid conference, can you please provide a list of pipes on each street and avenue? Can you also provide quantities?

A. The contractor will be responsible for doing their own culvert count.

Q. Widen these roads to match the 20-foot width used elsewhere in the project and bring the base up to current standards before paving, or leave the roads at their existing width and simply pave over the existing conditions where asphalt is already present?

A. Existing 12-foot-wide roads should be widened to the 20-foot width used elsewhere and brought to current standards before paving.

Q. Project Numbers 220016 and 220017 are bid and constructed concurrently under a single 90-day completion period. The Supplemental Conditions establish liquidated damages of $176.48/day for Streets and $256.08/day for Avenues. Please clarify whether liquidated damages are assessed separately by project number, cumulatively ($432.56/day total), or as a single project-wide assessment.

A. This is a single project assessment. This 4800 Area Project will have liquidated damages assessed at the rate of $216.20 per calendar day for an 180-day substantial completion period.

Q. Please provide road identification for Westerly and Rutland streets. The provided map does not indicate which roads are which. The referenced roads are not shown in Google Maps.

A. See updated map below, Q. Quincy Avenue contains approximately five existing driveways. Please confirm that the Contractor's responsibility is limited to tying the proposed roadway pavement into the existing driveway surfaces as necessary to provide a smooth transition.

A. Confirmed

Q. As requested at the pre-bid conference, can you please provide a list of pipes on each street and avenue? Can you also provide quantities?

A. The contractor will be responsible for doing their own culvert count.

Q. For the existing 12-foot-wide roads should the contractor widen these roads to match the 20-foot width used elsewhere in the project and bring the base up to current standards before paving, or leave the roads at their existing width and simply pave over the existing conditions where asphalt is already present?

A. Existing 12-foot-wide roads should be widened to the 20-foot width used elsewhere and brought to current standards before paving.