This document is a solicitation amendment for Solicitation No. 47PM1124R0011, the National Elevator Modernization & Construction IDIQ. The amendment makes several changes to the solicitation, including:

  1. Uploading preproposal conference slides and questions/answers into the solicitation attachments.
  2. Amending the Housing and Urban Development (HUD) Task Order Statement of Work (SOW) to expand the warranty period requirements.
  3. Adding the applicable Wage Determination and Liquidated Damages clauses to the HUD Task Order attachments.
  4. Adding an attachment showing the travel path for the HUD Task Order.
  5. Amending the Lafayette Task Order SOW to expand the warranty period and add maintenance requirements.
  6. Clarifying the use of the Lafayette Task Order Bid Spreadsheet.
  7. Adding the Liquidated Damages and Wage Determination clauses to the Lafayette Task Order attachments.
  8. Including information about GSA's Google Drive and Google Sites compliance with FIPS 140-2.
  9. Extending the proposal due date to June 6, 2024 at 11:59pm EST.

The overall solicitation is for a National Elevator Modernization IDIQ Contract with a $650 million ceiling over 5 years. It is an unrestricted competition with no small business set-aside.

View the file

Other files for this federal contract opportunity

Other files attached to National Elevator Modernization & Construction IDIQ AND AMENDMENT 001 & 002, newest first.
File Type Posted
10 H 01 Rev1 _ SF18 Request for Quotation.pdf PDF
10 H 20 Rev1 _ Bid Spreadsheet for HUD Elevator Modernization 2024 05 08 _ Bid Sheet.pdf PDF
L 02 SOW Attachment 15 Spec 284620 Multiplex Fire Alarm.pdf PDF
47PM1124R0011_AMEND 0002.pdf PDF
10_NEW National Elevator IDIQ RFP and Agreement 2024 05 16.pdf PDF
10 H 02 rev2 _ HUD Elevator Modernization DB Statement of Work_SOW_ 2024 05 08.pdf PDF
Questions and Answers as of 2024 05 16.pdf PDF
10 H 02 rev 1 HUD Elevator Modernization DB SOW 2024 05 02.pdf PDF
0 SF-18 Lafayette Elevator.pdf PDF
GSA Affiliated Customer Account GACA.pdf PDF
HUD Loading Doc sign.jpg JPG image
3 SOW - Modernize Lafayette Elevators Task Order SOW Rev 5-6-2024.pdf PDF
24 Lafayette Additional Task Order Provisions and Clauses 2024 05 02.pdf PDF
10 H 01A rev1 Additional Task Order Provisions and Clauses.pdf PDF
Questions and Answers as of 2024 05 08.pdf PDF
10 H 01A rev1 - Additional Task Order Provisions and Clauses.pdf PDF
10 H 24 RFI Response to Travel Path.pdf PDF
25 Lafayette Additional Task Order Provisions and Clauses 2024 05 02.pdf PDF
Questions and Answers 2024 05 02.pdf PDF
10 H 02 rev 1 HUD Elevator Modernization DB SOW 2024 05 02.pdf PDF
10 H 01A rev1 - Additional Task Order Provisions and Clauses 2024 05 02.pdf PDF
09 PreProposal Conference 2024 04 30.pdf PDF
10 10 IDIQ attachment Reps and Certifications.pdf PDF
10 06 IDIQ attachment PIB 18 02 Attachment 6 File Naming.pdf PDF
10 00 IDIQ attachment NDA_Document_Security.pdf PDF
10 15A IDIQ attachment IDIQ Pricing Sheet_NEW.xlsx XLSX spreadsheet
10 14 IDIQ attachment Bonding Insurance Geography Qualification Sheet_NEW.xlsx XLSX spreadsheet
10 12 IDIQ attachment Past Performance_NEW.xlsx XLSX spreadsheet
10 02 IDIQ attachment Section 02085 Asbestos Abatement Procedures.pdf PDF
10 01 IDIQ attachment Section 01546 Safety and Health Specification.pdf PDF
Solicitation National Elevator IDIQ and agreement.pdf PDF
10 15B Pricing Sheet Attachment Wage Determination.pdf PDF
10 05 IDIQ attachment Section 02090 Control of Lead Based Paint Specification.pdf PDF
10 09 ADM 2181 1 Homeland Security Presidential Directive 12 Personal Identity Verification for Contractor Employees.pdf PDF
Solicitation Cover Letter.pdf PDF
10 03 IDIQ attachment Section 02085 Roofing.pdf PDF
10 13 Past Performance_Customer Surveys.pdf PDF
10 11 IDIQ attachment GSA 527 Contractors Qualifications and Financial Information.pdf PDF
10 07 IDIQ attachment ADM 7002.1 GSA Smart Buildings.pdf PDF
10 04 IDIQ attachment Section 02087 Removal of Bird and Bat Droppings.pdf PDF
10 08 IDIQ attachment CIO 2180.2 GSA Rules of Behavior for Handling Personally Identifiable Information PII.pdf PDF
Show all 41

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

4/24/2024

Ericka Wilson, Contracting Officer

Multiple0001

GSA PBS R11 Office of Acquisitions Special Programs FDA80 1800 F Street, NW Washington, DC, DC 20405 USA

47PM1124R0011

WPH1DD

5/9/2024

This solicitation amendment, 001, modifies the solicitation as follows:

1 – Preproposal conference slides are uploaded into the solicitation attachments.

2 – Questions as of May 8, 2024 and answers at this time are uploaded into solicitation attachments.

3 – The Housing and Urban Development (HUD) Task Order (TO) Statement of Work (SOW) has been amended to include language that expands on the warranty period requirements - “10 H 02 rev 1 HUD Elevator...

[See Description of Modification Continuation Page]

X 1

Description of Modification Continuation Page

... Modernization DB SOW 2024 05 02.pdf".

4 - The HUD TO attachment has been changed to add the applicable Wage Determination clause associated with Housing and Urban Development Task Order Attachment in addition to the liquidated damages clause that was in the attachment - "10 H 01A rev1 - Additional Task Order Provisions and Clauses.pdf".

5 - A HUD TO attachment has been added to show the travel path from the freight elevator to the hoistway room and the elevator machine room at the penthouse level - "10 H 24 â RFI Response to Travel Path.pdf".

6 - The Lafayette TO SOW has been amended to include language that expands on the warranty period requirements and adds maintenance for the building's elevators during the modernization period - "3 SOW â Modernize Lafayette Elevators Task Order SOW Rev 5-6-2024.pdf".

7 - The Lafayette TO SF-18 has been amendment to clarify the use of the Bid Spreadsheet, "22 Bid Spreadsheet for Lafayette Elevator Modernization.xlsx" - "0 SF-18 Lafayette Elevator.pdf".

8 - A Lafayette TO attachment has been added to include the additional clauses document for the TO to include the Liquidated Damages Clause and Wage Determination clause - "24 Lafayette Additional Task Order Provisions and Clauses 2024 05 02.pdf".

9 - Include the GSA Affliated Custsomer Account (GACA) email from GSA IT for companies needing confirmation GSA's Google Drive and Google Sites systems are compliant to the Federal Information Processing Standard

(FIPS) 140-2.

10 - The proposal due date has been extended until June 6, 2024 at 11:59pm EST.

47PM1124R0011/0001