This document is a section of technical specifications related to the removal of bird and bat droppings, which is an attachment to a federal contract opportunity.

The key details are:

  • The control area includes the work area, which must be isolated and contained prior to removal.
  • The contractor is responsible for protecting workers and adjacent personnel during the removal process.
  • Workers must wear appropriate personal protective equipment, including disposable coveralls, gloves, and NIOSH-approved respirators.
  • The contaminated area must be saturated prior to removal using a soapy water mixture or chlorine-based disinfectant.
  • Gross debris must be removed manually or using a HEPA vacuum, and properly bagged and disposed.
  • Surfaces must be cleaned using a water stream or final application of disinfectant.
  • Visual inspection by the Contracting Officer is required to approve the decontamination work.

The federal contract opportunity is for a National Elevator Modernization IDIQ with a maximum aggregate value of $650 million. It is an unrestricted solicitation, with no small business set-aside. Proposals are due on May 28, 2024.

View the file

Other files

File Type Posted
47PM1124R0011_AMEND 0002.pdf PDF
Questions and Answers as of 2024 05 16.pdf PDF
10 H 02 rev2 _ HUD Elevator Modernization DB Statement of Work_SOW_ 2024 05 08.pdf PDF
10 H 01 Rev1 _ SF18 Request for Quotation.pdf PDF
10 H 20 Rev1 _ Bid Spreadsheet for HUD Elevator Modernization 2024 05 08 _ Bid Sheet.pdf PDF
L 02 SOW Attachment 15 Spec 284620 Multiplex Fire Alarm.pdf PDF
10_NEW National Elevator IDIQ RFP and Agreement 2024 05 16.pdf PDF
10 H 02 rev 1 HUD Elevator Modernization DB SOW 2024 05 02.pdf PDF
GSA Affiliated Customer Account GACA.pdf PDF
0 SF-18 Lafayette Elevator.pdf PDF
24 Lafayette Additional Task Order Provisions and Clauses 2024 05 02.pdf PDF
3 SOW - Modernize Lafayette Elevators Task Order SOW Rev 5-6-2024.pdf PDF
HUD Loading Doc sign.jpg JPG image
10 H 24 RFI Response to Travel Path.pdf PDF
Solicitation Amendment 47PM1124R0011_0001.pdf PDF
Questions and Answers as of 2024 05 08.pdf PDF
10 H 01A rev1 Additional Task Order Provisions and Clauses.pdf PDF
25 Lafayette Additional Task Order Provisions and Clauses 2024 05 02.pdf PDF
10 H 01A rev1 - Additional Task Order Provisions and Clauses 2024 05 02.pdf PDF
Questions and Answers 2024 05 02.pdf PDF
10 H 02 rev 1 HUD Elevator Modernization DB SOW 2024 05 02.pdf PDF
09 PreProposal Conference 2024 04 30.pdf PDF
10 13 Past Performance_Customer Surveys.pdf PDF
10 11 IDIQ attachment GSA 527 Contractors Qualifications and Financial Information.pdf PDF
10 03 IDIQ attachment Section 02085 Roofing.pdf PDF
10 02 IDIQ attachment Section 02085 Asbestos Abatement Procedures.pdf PDF
10 10 IDIQ attachment Reps and Certifications.pdf PDF
10 14 IDIQ attachment Bonding Insurance Geography Qualification Sheet_NEW.xlsx XLSX spreadsheet
Solicitation National Elevator IDIQ and agreement.pdf PDF
10 07 IDIQ attachment ADM 7002.1 GSA Smart Buildings.pdf PDF
10 12 IDIQ attachment Past Performance_NEW.xlsx XLSX spreadsheet
10 15A IDIQ attachment IDIQ Pricing Sheet_NEW.xlsx XLSX spreadsheet
10 08 IDIQ attachment CIO 2180.2 GSA Rules of Behavior for Handling Personally Identifiable Information PII.pdf PDF
10 06 IDIQ attachment PIB 18 02 Attachment 6 File Naming.pdf PDF
10 00 IDIQ attachment NDA_Document_Security.pdf PDF
10 01 IDIQ attachment Section 01546 Safety and Health Specification.pdf PDF
10 05 IDIQ attachment Section 02090 Control of Lead Based Paint Specification.pdf PDF
Solicitation Cover Letter.pdf PDF
10 15B Pricing Sheet Attachment Wage Determination.pdf PDF
10 09 ADM 2181 1 Homeland Security Presidential Directive 12 Personal Identity Verification for Contractor Employees.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

March 2012 Revision 02087-1

SECTION 02087- REMOVAL OF BIRD AND BAT DROPPINGS

Part 1 - GENERAL

1.1 CONTROL AREA

A. The control area includes the following:

Describe work area and indicate on project drawings

B. Related work specified in other sections:

Section 01546, "Safety and Health," applies to all work covered by this section.

1.2 SUBMITTALS

Contractor’s plan of action: to be approved prior to the commencement of work.

A. Work practices and dust control measures to eliminate or reduce dust generation during the removal.

B. Material Safety Data Sheets (MSDS) for any products used on site.

1.3 CONTRACTOR RESPONSIBILITY

The contractor shall assume full responsibility for the protection of workers, visitors to the site, and persons occupying areas adjacent to the site.

1.4 SEQUENCING

Removal of droppings must be done in conjunction with other environmental abatement work as appropriate and prior to work of other trades.

Part 2 - PRODUCTS

2.1 EQUIPMENT

A. Equipment, protective clothing and respirators required for the execution of this contract shall comply with all applicable Federal, State, and local regulations, including but not limited to: 29 CFR 1910.132 and 29 CFR 1910.132.

March 2012 Revision 02087-2

B. At a minimum, workers shall wear disposable coveralls including disposable shoe coverings and gloves. Workers shall wear NIOSH-approved full face respirators with combination high-efficiency particulate air (HEPA) filters capable of excluding particles of 0.3 micron size. Chemical cartridges for chlorine are required if a chlorine-based disinfectant is used.

Part 3 - EXECUTION

3.1 WORK PROCEDURES

A. Isolate the work area by sealing off all openings and fixtures, including but not limited to heating and cooling system air intakes and doorways. Cover all non-removable items and equipment in the work area with plastic sheeting taped securely in place.

B. Prior to removal, saturate the contaminated area. Small areas can be wetted with a soapy water mixture/water with a surfactant. Alternatively, the contractor may use a chlorine-based disinfecting solution, used at the manufacturers’ suggested maximum concentration (requires pre-approval of the product’s MSDS). Apply solution using a low velocity sprayer to prevent debris from becoming airborne.

Use an application rate to completely saturate the material. If necessary, spray the area several times to fully saturate. The disinfectant solution should be sprayed intermittently during removal to keep debris saturated. Prevent drainage of gross debris into the building drainage system.

C. Use manual scrapers, shovels, and the like for gross debris removal. Bag the droppings in doubled, 6-mil plastic bags. Close bags securely and transport to a landfill for burial.

D. An acceptable alternative method is the use of an industrial HEPA vacuum to remove the debris. Truck-mounted or trailer-mounted HEPA vacuum systems are recommended for buildings with deep accumulations of bat or bird droppings, feathers, carcasses, etc.

3.2 CLEAN-UP AND DISPOSAL

A. Disposable coveralls shall be placed in plastic bags prior to exiting work area.

Provisions for showers shall be available in the event coveralls are torn or breached. It is recommended that workers shower, thoroughly washing their hair, at the end of each work shift.

B. After gross debris has been abated, if conditions allow, the surfaces shall be final cleaned using a water stream. If this is not feasible a final application of chlorinated disinfectant shall be applied.

March 2012 Revision 02087-3

C. Air sampling, surface sampling, or the use of any other sampling method intended to confirm cleanliness is unnecessary in most cases. However, before a removal activity is considered finished, the cleaned area should be inspected visually to ensure that no residual dust or debris remains. The Contracting Officer or his/her designated representative will inspect the work area prior to approval of decontamination work.

END OF SECTION 02087