About this file

This document provides pricing templates for a federal solicitation seeking multiple-award IDIQ contracts for general construction and design-build services to support the installation of electric vehicle supply equipment at federal agency locations nationwide. Offerors must provide fixed unit pricing for labor rates and materials for line items such as electrical engineering assessments, transformers, panelboards, conduit installation, concrete work, and safety equipment to be installed in four geographic zones covering the continental U.S. and Puerto Rico. The contracts have a one-year base period and four one-year options with a maximum value of $500 million per zone. Task orders are anticipated to range from $50,000 to $4 million for services such as site assessments, planning, permitting, construction, testing and transition to operations. The solicitation sets aside the awards for small businesses with a $39.5 million size standard under NAICS code 236220.

View the file

Other files

File Type Posted
Amendment 0004 Questions and Answers.pdf PDF
AMENDMENT 0004 ATTACHMENT A.pdf PDF
Amendment 0004 SF30.pdf PDF
Revised The Solicitation DB201.pdf PDF
The Agreement DB101 April 14 2022.pdf PDF
Statement of Work April 14 2022.pdf PDF
Revised ATTACHMENT B PRIOR EXPERIENCE WORKSHEET.docx DOCX document
Pre Proposal Conference Registration List 04072022.xlsx XLSX spreadsheet
Amendment 0003 SF30.pdf PDF
Pre Proposal Conference slides 04072022.pdf PDF
Amendment 0002 Questions and Answers.pdf PDF
Revised Supplemental SF 1442 Pricing Sheet.xlsx XLSX spreadsheet
Amendment 0002 SF30.pdf PDF
AMENDMENT 0002 ATTACHMENT A.pdf PDF
Amendment 0001 Questions and Answers.pdf PDF
AMENDMENT 0001 ATTACHMENT A.pdf PDF
Amendment 0001 SF30.pdf PDF
GSA Form 527 Contractor Qualification and Financial Information.pdf PDF
1442 47PL0122R0022.pdf PDF
The Solicitation DB201.pdf PDF
ATTACHMENT B Prior Experience Worksheet.docx DOCX document
ATTACHMENT A Past Performance Questionnaire.docx DOCX document
The Agreement DB101.pdf PDF
Statement of Work March 17 2022.pdf PDF
ATTACHMENT C Small Business Socioeconomic Category Designation Form.docx DOCX document
Supplemental SF 1442 Pricing Sheet.xlsx XLSX spreadsheet
PBS EV - Vendor SCRM Plan Template.xlsx XLSX spreadsheet
C301 Representations and Certifications.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions

Revised Supplemental SF1442 Pricing Sheet R1
Solicitation Number: 47PL0122R022
Instructions

1 Input the "Name of Offeror" for each Geographic Zone the offeror is requesting to be considered for (i.e., Zone A, B, C, D).

2 Input a maximum Unit Price (Column C) for every line item listed for each period (base + option periods 1-4), for each Geographic Zone the offeror is requesting to be considered for (i.e., Zone A, B, C, D). These Unit Prices will establish the ceiling rate for each line item within each Geographic Zone, for each of the years within the Base and Option contract periods. Each Task Order is anticipated to be competed. Pricing submitted for each Task Order can be lower than proposed Unit Prices, but can never be higher. These rates apply throughout the entire Geographic Zone regardless of project location within the zone.

3 The included Line Items, Unit, and Estimated Quantity (Columns A, B and D) are fixed to help the Government evaluate price. Do not change information in Columns A, B, and D on the sheets.

4 The Estimated Total Price column is the Unit Price inputted by the offeror multiplied by the Estimated Quantity (Column C times Column D). This column will add up to the “Total Year __ Estimated Price”.

5 The “Total Evaluated Price for Zone ___ (Total Estimated Price for Base Period + Option Period 1 + Option Period 2 + Option Period 3 + Otion Period 4)” will be used to evaluate the offeror's pricing for each of the Geographic Zones the offeror is requesting to be considered for. The Total Evaluated Price for each Geographic Zone will be evaluated separately.

6 Following IDIQ contract award, unless the Task Order Contracting Officer specifies another format, Task Order price proposals shall utilize the line items established in the IDIQ contract and not exceed the line item prices established in the IDIQ contract. For any work that is not covered by line items established in the IDIQ contract, the Task Order Contracting Officer will specify the format of the price proposal.

Zone A

Revised Supplemental SF1442 Pricing Sheet R1
Solicitation Number: 47PL0122R022
Name of Offeror:
Zone A - Base Period
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Base Period Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone A - Option Period I
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Option Period I Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone A - Option Period 2
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Option Period 2 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone A - Option Period 3
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Option Period 3 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone A - Option Period 4
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Option Period 4 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Total Evaluated Price for Zone A (Total Estimated Price for Base Year + Option 1 + Option 2 + Option 3 + Option 4) $0.00

Zone B

Revised Supplemental SF1442 Pricing Sheet R1
Solicitation Number: 47PL0122R022
Name of Offeror:
Zone B - Base Period
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 1 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone B - Option Period 1
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 2 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone B - Option Period 2
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 3 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone B - Option Period 3
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 4 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone B - Option Period 4
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 5 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Total Evaluated Price for Zone B (Total Estimated Price for Base Year + Option 1 + Option 2 + Option 3 + Option 4) $0.00

Zone C

Revised Supplemental SF1442 Pricing Sheet R1
Solicitation Number: 47PL0122R022
Name of Offeror:
Zone C - Base Period
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 1 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone C - Option Period 1
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 2 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone C - Option Period 2
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 3 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone C - Option Period 3
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 4 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone C - Option Period 4
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00]
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 5 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Total Evaluated Price for Zone C (Total Estimated Price for Base Year + Option 1 + Option 2 + Option 3 + Option 4) $0.00

Zone D

Revised Supplemental SF1442 Pricing Sheet R1
Solicitation Number: 47PL0122R022
Name of Offeror:
Zone D - Base Period
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 1 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone D - Option Period 1
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 2 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone D - Option Period 2
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 3 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone D - Option Period 3
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 4 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Zone D - Option Period 4
Line ItemsUnitUnit Price*Estimated QuantityEstimated Total Price
Electrical Engineer (Feasibility Study/Site Assessment) [mimimum BS Degree in Electrical Engineering, 4 years experience]hr32$0.00
Transformer (480V-208Y/120V, 3P, 4W, 225 kVA with grounding, copper windings, interior mtd, shall meet 10 CFR 431 part 196)ea1$0.00
Panelboard (480v, 800A, 3ph, M.L.O., surface mtd, interior mtd, 42-pole, 35 kAIC, fully populated 400A/3P)ea1$0.00
Panelboard (208/120v, 800A, MCB = 800A, surface mtd, interior mtd, 42-pole, 10kAIC, fully populated 40A/2P)ea1$0.00
EMT Conduit and Cable (3/4" dia, qty 4 cat-6)ft100$0.00
EMT Conduit and Cable (2" dia, THHN 6#8, 2#10G AWG)ft50$0.00
PVC Conduit (sked 80) and Cable (unpaved earth, with 24" x 24" trench and reseeding) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
PVC Conduit (sked 40) and Cable (concrete encased, with 24" x 24" trench and 4" base coat and 2" top coat asphalt restoration) (qty 1 conduit at 3/4" dia with 4 cat-6, qty 4 conduit at 2" dia with THWN 6#8, 2#10G AWG each)ft50$0.00
Concrete Pad (6" slab 3500PSI, #5 reinforcing @ 6" OC each way, 4" gravel base)cu ft3$0.00
Wheel Stop (concrete, 6' long)ea24$0.00
Bollard (6" dia, Schedule 80 galvanized stl pipe, concrete filled, yellow painted, embed 36" w/ 12" conc foundation)ea24$0.00
Total Year 5 Estimated Price$0.00

* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions]

Total Evaluated Price for Zone D (Total Estimated Price for Base Year + Option 1 + Option 2 + Option 3 + Option 4) $0.00