This document summarizes Amendment 0004 to a solicitation seeking proposals for multiple-award indefinite delivery indefinite quantity contracts to support the installation of electric vehicle supply equipment at federal agency locations nationwide. The contracts have a one-year base period and four one-year options, with a maximum ordering limit of $500 million per geographic zone. Zone A includes the Northeast; Zone B includes the Southeast and Central South; Zone C includes the Midwest; and Zone D includes the West. The amendment extends the proposal due date to May 3, 2022, updates pricing sheets and statements of work, clarifies technical proposal page limits, and makes various other revisions. This is a 100% total small business set-aside solicitation within NAICS code 236220 for commercial and institutional building construction, with a small business size standard of $39.5 million.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. 47PL0122R0022 Amendment #0004 Attachment A Date: April 15, 2022
Project Title: GSA PBS Governmentwide Multiple-Award IDiQ Contract(s) for General Construction with Design/Build Capabilities to Support the Installation of Electric Vehicle Supply Equipment (EVSE)
AMENDMENT 0004 ATTACHMENT A
1. See attachment titled “Amendment 0004 Questions and Answers” which is hereby incorporated into the solicitation.
2. Attachment titled, “Statement of Work April 14 2022” hereby supersedes and replaces in its entirety (including all references to) attachment titled, “Statement of Work March 17 2022”. Changes are redlined for identification, which includes changes made in Amendments 0002 and 0004.
3. Attachment titled, “Revised The Solicitation DB201” hereby supersedes and replaces in its entirety (including all references to) attachment titled,“The Solicitation DB201”. Changes are redlined for identification, which includes changes made in Amendments 0001, 0002, and 0004.
4. Attachment titled, "Revised ATTACHMENT B, PRIOR EXPERIENCE WORKSHEET" hereby supersedes and replaces in its entirety (including all references to) attachment titled, "ATTACHMENT B, PRIOR EXPERIENCE WORKSHEET". The following has been updated in the attachment "Revised
ATTACHMENT B, PRIOR EXPERIENCE WORKSHEET":
● Added question 1., “Geographic Zone this form is being submitted for (A, B, C, D), select one.
● Added “the percentage of” to what is now question 10.
5. Attachment titled “Revised Supplemental SF1442 Pricing Sheet R1” hereby supersedes and replaces in its entirety (including all references to) attachment titled “Supplemental SF1442 Pricing Sheet”. The following has been updated in the attachment “Revised Supplemental SF1442 Pricing Sheet R1”:
● Line Item “Electrician” has been deleted and is no longer required.
● Line Item “Site Superintendent” has been deleted and is no longer required.
● The following asterisk located multiple times on tabs Zone A, B, C, D, now includes the word “equipment”. “* - Unit pricing for equipment shall include all material, equipment, and labor costs for a complete install [excluding travel and general conditions. The note now includes “equipment.”
● Amendment 0002 Answers# 38, 115, 116 were added to line items to provide clarity.
6. Attachment titled, “The Agreement DB101 April 14 2022” hereby supersedes and replaces in its entirety (including all references to) attachment titled,“The Agreement DB101”. Changes are redlined for identification, which includes the following change: references to FAR 52.204-14, Service Contract Reporting Requirements, are hereby deleted and replaced with FAR 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (OCT 16).
7. The following language from Attachment titled "The Solicitation DB201" Section I.B, List of Solicitation Documents, item (5), is hereby deleted “, Specifications, and Drawing Exhibits”.
8. The response to Question 62 in Amendment 0002 is hereby changed to the following, which supersedes any previous technical proposal page limitation restrictions:
“The overall page limit for the technical proposal described in “The Solicitation DB201”, Section II.B., 3.a, is hereby deleted and replaced with the following technical proposal page limitations:
"The technical proposal shall be limited to the following components and their respective page limitations:
- Cover Page – indicating which Geographic Zone(s) the offeror is requesting to be considered for (i.e., Zone A, B, C, D), not to exceed one (1) page.
- Table of Contents - Optional, not to exceed one (1) page, if provided
- Project Bonding Capacity – no page limitation
- Factor 1 – Prior Experience on Relevant Projects - for each project submitted, the completed Attachment B shall not exceed two (2) pages. If more than two (2) pages are submitted, only the first two (2) pages will be evaluated.
- Factor 2 - Past Performance on Relevant Projects - PPQs have no page limitation. A list of any other forms of performance recognition shall not exceed two (2) pages. If more than two (2) pages are submitted, only the first two (2) pages will be evaluated.
- Factor 3 - Management Plan – the entire Management Plan, excluding resumes, shall not exceed ten (10) pages. If more than ten (10) pages are submitted, only the first ten (10) pages will be evaluated. A maximum of five (5) resumes can be submitted. If more than 5 resumes are submitted, only the first five (5) will be evaluated. Each resume submitted shall not exceed two (2) pages.
If more than two (2) pages are submitted, only the first two (2) pages will be evaluated.
- Factor 4 - Small Business Socioeconomic Category Designation - The Attachment C, Small Business/Socioeconomic Category Designation Form, is excluded from the page limitation.
All pages in the technical proposal must be 8.5 inches by 11 inches and use twelve (12) point font, except that headers, footers, tables, charts and graphics would not need to meet font size 12 restrictions; however, the offeror is responsible to ensure all text is legible. Pages that differ from these page dimensions will not be evaluated."
9. The following language in “The Solicitation DB201”, Section II.D, Technical
Proposal, Factor 1 – Prior Experience on Relevant Projects, is hereby changed From: “While the Government is looking for prior experience by the prime contractor or joint venture, the Government may consider relevant experience by affiliated companies, key personnel and subcontractors, which may include subcontractors under Small Business Teaming Arrangements.”
To: “While the Government is looking for prior experience by the prime contractor or joint venture, the Government will consider relevant experience by affiliated companies, key personnel and subcontractors, which may include subcontractors under Small Business Teaming Arrangements.”
10. Attachment titled "The Solicitation DB201", section II.D, Factor 1 – Prior Experience on Relevant Projects, hereby adds the following, “Prior experience by the prime contractor or joint venture may be considered a strength.”
11. The following language in "The Solicitation DB201" section II.D, Factor 1 – Prior Experience on Relevant Projects, is hereby added to the paragraph beginning with "Note": "A "project" is not an Indefinite Delivery Indefinite Quantity (IDIQ) contract, blanket purchase agreement, or other type of master contract. However, if the “project” was performed under an IDIQ, blanket purchase agreement or other type of master contract, this should be identified."
12. The following language in “The Solicitation DB201”, VI.E, Total Evaluated Price, is hereby changed From: “Total Evaluated Price shall be calculated using the prices indicated in the Price Proposal, using the following formula:”
To: “Total Evaluated Price shall be calculated as indicated in the revised Supplemental SF1442 Pricing Sheet.”
13. The following language from the revised (per Amendment 0002) attachment titled “Statement of Work March 17 2022”, Section (8) Inclusion of EVSE and Ancillary Services Within Task Order Requirements, is hereby changed From: “Use of the FSS EVSE and Ancillary Services BPAs for supplies or ancillary services specified in the Task Order requirements is mandatory, unless the required supplies or ancillary services are not available on the BPAs. This includes, but is not limited to all types of electric vehicle charging terminals. In the event that a contractor determines that required supplies or ancillary services under a Task Order are not available through the FSS EVSE and Ancillary Services BPAs, contractors must notify the Task Order Contracting Officer as soon as practicable to request an exception from this requirement.”
To: “Use of the FSS EVSE and Ancillary Services BPAs for electric vehicle charging stations specified in the Task Order requirements is mandatory, unless the required electric vehicle charging stations are not available on the BPAs. In the event that a contractor determines that required electric vehicle charging stations under a Task Order are not available through the FSS EVSE and Ancillary Services BPAs, contractors must notify the Task Order Contracting Officer as soon as practicable to request an exception from this requirement. If necessary, the IDIQ Contracting Officer may identify other grounds for exceptions.”
14. Proposal due date is extended by 6 days from April 27, 2022 to May 3, 2022 at 2:00 pm Eastern Time.
15. This Amendment must be acknowledged as part of your submitted proposal.