TX0130 & TX0126 Work Order list
| MAXIMO W/O Number | W/O Type | W/O Sub Type | W/O Description | reportdate | reportedby | Behalf of | Location Description | Equip Number | status | statusdate | BLDG # |
| 27768183 | CM | CORRECT | TX0130 1ST FLOOR COURTROOM TEMP ADJUST | 4/30/18 7:00 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/30/18 11:28 | TX0130ZZ | |
| 27768313 | CM | CORRECT | TX01302ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/30/18 7:00 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/30/18 11:26 | TX0130ZZ | |
| 27768455 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE & ATTORNEY CONFERENCE ROOM | 4/30/18 7:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/30/18 11:25 | TX0130ZZ | |
| 27750750 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/27/18 8:30 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/27/18 15:31 | TX0130ZZ | |
| 27750756 | CM | CORRECT | TX0130 2ND FLOOR ATTORNEY CONFERENCE & KECIA'S OFFICE TEMP ADJUST | 4/27/18 8:30 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/27/18 15:29 | TX0130ZZ | |
| 27750774 | WR | SERVCALL | TX0130 AREA COLD MAKE TEMP ADJUST | 4/26/18 15:45 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/27/18 15:28 | TX0130ZZ | |
| 27678777 | CM | CORRECT | TX0130 1ST FLOOR REGULATE BUILDING TEMPS | 4/26/18 8:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/26/18 14:46 | TX0130ZZ | |
| 27695910 | CM | CORRECT | TX0130 1ST FLOOR AHU ROOM REGULATE TEMPS IN BUILDING | 4/26/18 8:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-2 | COMP | 4/26/18 14:44 | TX0130ZZ | |
| 27695918 | CM | CORRECT | TX0130 2ND FLOOR REPORTER CONFERENCE ROOM TEMP ADJUST | 4/26/18 6:30 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/26/18 14:16 | TX0130ZZ | |
| 27695924 | CM | CORRECT | TX0130 2ND FLOOR JUDGES CHAMBERS TEMP ADJUST | 4/26/18 6:30 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/26/18 14:10 | TX0130ZZ | |
| 27617497 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/25/18 7:30 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/25/18 16:14 | TX0130ZZ | |
| 27617711 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/25/18 7:30 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/25/18 16:12 | TX0130ZZ | |
| 27617789 | CM | CORRECT | TX0130 1ST FLOOR CHILLER ROOM DISABLE CHILLER | 4/25/18 7:30 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | TX0130ZZ-CHL-CW1-R07B-2 | COMP | 4/25/18 16:08 | TX0130ZZ | |
| 27617897 | CM | CORRECT | TX0130 1ST FLOOR BOILER ROOM ENABLE BOILER FOR TEMP ADJUST | 4/25/18 7:30 | RAMONASCOX | TX0130ZZ-Basement-Boiler Mechanical Room | TX0130ZZ-BLR-HW1-B02E-1 | COMP | 4/25/18 16:07 | TX0130ZZ | |
| 27611155 | CM | CORRECT | TX0130 1ST FLOOR BOILER ROOM TEMP ADJUST | 4/24/18 7:15 | RAMONASCOX | TX0130ZZ-Basement-Boiler Mechanical Room | TX0130ZZ-BLR-HW1-B02E-1 | COMP | 4/24/18 14:17 | TX0130ZZ | |
| 27611237 | CM | CORRECT | TX0130 1ST FLOOR CHILLER ROOM TEMP ADJUST | 4/24/18 7:15 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | TX0130ZZ-CHL-CW1-R07B-2 | COMP | 4/24/18 14:10 | TX0130ZZ | |
| 27611248 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/24/18 7:15 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/24/18 14:09 | TX0130ZZ | |
| 27611252 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/24/18 7:15 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/24/18 14:07 | TX0130ZZ | |
| 27610988 | CM | CORRECT | TX0130 1ST FLOOR CHILLER ROOM TEMP ADJUST | 4/23/18 7:00 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | TX0130ZZ-CHL-CW1-R07B-2 | COMP | 4/24/18 14:33 | TX0130ZZ | |
| 27610993 | CM | CORRECT | TX0130 1ST FLOOR BOILER ROOM TEMP ADJUST | 4/23/18 7:00 | RAMONASCOX | TX0130ZZ-Basement-Boiler Mechanical Room | TX0130ZZ-BLR-HW1-B02E-1 | COMP | 4/24/18 14:32 | TX0130ZZ | |
| 27611002 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/23/18 7:00 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/24/18 14:27 | TX0130ZZ | |
| 27611027 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/23/18 7:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/24/18 14:25 | TX0130ZZ | |
| 27598530 | CM | CORRECT | TX0130 1ST FLOOR TEMP ADJUST | 4/20/18 6:45 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/20/18 11:35 | TX0130ZZ | |
| 27598533 | CM | CORRECT | TX0130 BUILDING IS COLD MADE TEMP ADJUST | 4/20/18 6:45 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/20/18 11:34 | TX0130ZZ | |
| 27598536 | CM | CORRECT | TX0130 BUILDING IS COLD MADE TEMP ADJUST | 4/20/18 6:45 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/20/18 11:33 | TX0130ZZ | |
| 27598540 | CM | CORRECT | TX0130 BUILDING IS COLD MADE TEMP ADJUST | 4/20/18 6:45 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/20/18 11:28 | TX0130ZZ | |
| 27598547 | WR | SERVCALL | TX0130 DRAIN PIPE 1ST FLOOR CHILLER ROOM | 4/19/18 13:00 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | COMP | 4/20/18 10:36 | TX0130ZZ | ||
| 27576982 | CM | CORRECT | TC0130 DISABLE CHILLER FOR TEMP ADJUST | 4/19/18 7:00 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | TX0130ZZ-CHL-CW1-R07B-2 | COMP | 4/19/18 11:05 | TX0130ZZ | |
| 27576990 | CM | CORRECT | TX0130 ENABLED BOILER FOR TEMP ADJUST | 4/19/18 7:00 | RAMONASCOX | TX0130ZZ-Basement-Boiler Mechanical Room | TX0130ZZ-BLR-HW1-B02E-1 | COMP | 4/19/18 11:04 | TX0130ZZ | |
| 27576994 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/19/18 7:00 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/19/18 11:03 | TX0130ZZ | |
| 27577000 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/19/18 7:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/19/18 11:01 | TX0130ZZ | |
| 27576963 | CM | CORRECT | TX0130 DISABLE CHILLER FOR TEMP ADJUST | 4/18/18 7:15 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | TX0130ZZ-CHL-CW1-R07B-2 | COMP | 4/19/18 11:11 | TX0130ZZ | |
| 27576967 | CM | CORRECT | TX0130 ENABLE BOILER FOR TEMP ADJUST | 4/18/18 7:15 | RAMONASCOX | TX0130ZZ-Basement-Boiler Mechanical Room | TX0130ZZ-BLR-HW1-B02E-1 | COMP | 4/19/18 11:09 | TX0130ZZ | |
| 27576973 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/18/18 7:15 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/19/18 11:08 | TX0130ZZ | |
| 27576979 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/18/18 7:15 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/19/18 11:07 | TX0130ZZ | |
| 27352610 | WR | SERVCALL | TX0130 ESCORT CITY OF MARSHALL FOR SIDE WALK | 4/17/18 10:00 | RAMONASCOX | TX0130ZZ-Exterior | COMP | 4/17/18 14:53 | TX0130ZZ | ||
| 27352781 | CM | CORRECT | TX0130 ESCORT RUDD FOR RZP INSPECTION | 4/17/18 9:00 | RAMONASCOX | TX0130ZZ-Entire Building | COMP | 4/17/18 14:51 | TX0130ZZ | ||
| 27343416 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/17/18 8:15 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/17/18 11:27 | TX0130ZZ | |
| 27343547 | CM | CORRECT | TX0130 1ST FLOOR BOILER ROOM TEMP ADJUST | 4/17/18 7:15 | RAMONASCOX | TX0130ZZ-Basement-Boiler Mechanical Room | TX0130ZZ-BLR-HW1-B02E-1 | COMP | 4/17/18 11:26 | TX0130ZZ | |
| 27343663 | CM | CORRECT | TX0130 1ST FLOOR CHILLER ROOM TEMP ADJUST | 4/17/18 7:15 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | TX0130ZZ-CHL-CW1-R07B-2 | COMP | 4/17/18 11:24 | TX0130ZZ | |
| 27343777 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/17/18 7:15 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/17/18 11:21 | TX0130ZZ | |
| 27343906 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/17/18 7:15 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/17/18 11:19 | TX0130ZZ | |
| 27249794 | CM | CORRECT | TX0130 2ND FLOOR MAIN COURTROOM TEMP ADJUST | 4/16/18 8:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/16/18 15:57 | TX0130ZZ | |
| 27249911 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS TEMP ADJUST | 4/16/18 7:00 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/16/18 15:55 | TX0130ZZ | |
| 27250002 | CM | CORRECT | TX0130 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/16/18 7:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/16/18 15:53 | TX0130ZZ | |
| 26967981 | GSAI | NORMAL | TX0130 Treat for weeds | 4/13/18 14:50 | CHRISTOPHERCJONES | RICHARDDCARLSON | TX0130ZZ-Exterior | CAN | 4/16/18 11:30 | TX0130ZZ | |
| 26967988 | OMI | INITIAL | TX0130 Mow the grass | 4/13/18 8:00 | CHRISTOPHERCJONES | TX0130ZZ-Exterior | COMP | 4/24/18 10:30 | TX0130ZZ | ||
| 27249265 | CM | CORRECT | TX0126 WINDOW WELLS AND DRAINS NEED CLEANING | 4/13/18 8:00 | RAMONASCOX | TX0126ZZ-Exterior | COMP | 4/16/18 16:02 | TX0126ZZ | ||
| 26961328 | CM | CORRECT | TX0130 1ST FLOOR CHILLER ROOM TEMP ADJUST | 4/13/18 7:30 | RAMONASCOX | TX0130ZZ-Floor 01-Chiller Mechanical Room | TX0130ZZ-CHL-CW1-R07B-2 | COMP | 4/13/18 11:36 | TX0130ZZ | |
| 26961455 | CM | CORRECT | TX0130 1ST FLOOR BOILER ROOM TEMP ADJUST | 4/13/18 7:30 | RAMONASCOX | TX0130ZZ-Basement-Boiler Mechanical Room | TX0130ZZ-BLR-HW1-B02E-1 | COMP | 4/13/18 11:35 | TX0130ZZ | |
| 26961069 | CM | CORRECT | TX0019 2ND FLOOR KECIA'S OFFICE TEMP ADJUST | 4/13/18 7:00 | RAMONASCOX | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-AHU-01-A11B-3 | COMP | 4/13/18 11:53 | TX0130ZZ | |
| 26961210 | CM | CORRECT | TX0130 2ND FLOOR JUDGE'S CHAMBERS | 4/13/18 7:00 | RAMONASCOX | TX0130ZZ-Roof | TX0130ZZ-AHU-01-A11B-1 | COMP | 4/13/18 11:39 | TX0130ZZ | |
| 26800449 | PM | PREVENT | Leave transmitter panel in normal operating condition with door locked. Inform involved personnel that testing is complete. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800444 | PM | PREVENT | Clean interior of transmitter cabinet. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800439 | PM | PREVENT | Check the operation of each transmitter in all modes of operation by actuation of devices or contacts within the related fire alarm panel. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800434 | PM | PREVENT | Check each transmitter for proper code wheel alignment, loose or burned contacts or terminals. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800432 | PM | PREVENT | Check standby batteries (if located in the panel) for signs of overcharging, heat, and leakage. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800430 | PM | PREVENT | Check battery charge current (be sure it is within manufacturer's limits). | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800428 | PM | PREVENT | Check standby battery voltage under load for a minimum of 5 minutes (if applicable). | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800426 | PM | PREVENT | Check power supply output voltage in normal and under load conditions. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800424 | PM | PREVENT | Check all fuses. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800422 | PM | PREVENT | Check all lamps/LEDS (including remote annunciators). | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800420 | PM | PREVENT | Inspect the cabinet for damage (exterior and interior) including locks, door hinges, and plastic covers. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800418 | PM | PREVENT | When work requires the actuation of building evacuation systems, the work must be performed after hours and must be coordinated through the field office manager to prevent the unnecessary evacuation of the building's occupants. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800416 | PM | PREVENT | Deficiencies must be recorded. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800414 | PM | PREVENT | The work required by this procedure may cause the activation of the building fire alarm system and/or supervisory signal to the control center. The Field Office Manager and the control center that will receive the signal must be notified prior to start | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800412 | PM | PREVENT | PM-TX0130ZZ-ALM-F15B-1, Fire Detection and Alarm System | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Basement-Electrical Equipment Room | TX0130ZZ-ALM-F15B-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800362 | PM | PREVENT | If treatment is not effective, it may require change in current methods and procedures. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800358 | PM | PREVENT | Record test results, action taken, type of chemicals, and treatment quantities used. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800354 | PM | PREVENT | If make up is excessive, determine source of leaks and correct. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800350 | PM | PREVENT | Add or adjust chemical and biological treatment dosages and water blow down as appropriate. | 4/12/18 22:45 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800346 | PM | PREVENT | Test each system for proper pH, alkalinity, total dissolved, hardness, conductivity, scale and corrosion inhibitors, and sludge conditioners. Test supply water for base conditions. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800343 | PM | PREVENT | Inspect boiler and piping system to determine effectiveness of water treatment. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800340 | PM | PREVENT | When boilers are out of service, they must be protected from corrosion either by draining the boiler and keeping surfaces thoroughly dry or by completely filling the boiler with properly tested with water. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800336 | PM | PREVENT | Follow the Recommended Rules for Care and Operation of Heating (or Power) Boilers as contained in the American Society of Mechanical Engineers. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800332 | PM | PREVENT | Maintain records and test results. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800330 | PM | PREVENT | Physical inspections of boilers and supply and return piping systems are to be made to determine water treatment effectiveness. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800327 | PM | PREVENT | Special attention must be paid to infrequently used boilers, or boilers subjected to long periods of idleness. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800323 | PM | PREVENT | Ensure chemicals are properly stored, test equipment clean, and that chemicals have not passed expiration date. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800319 | PM | PREVENT | Select water treatment methods which protect the life of equipment, maximize heat transfer, and minimize scale, corrosion, solid matter buildup, biological growth, and water usage. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800315 | PM | PREVENT | Maintenance includes chemicals, chemical feeding, maintaining proper water conditions, controlling blow down, protecting idle equipment, and records. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800313 | PM | PREVENT | Water treatment must be based on proven standard engineering practices. Treatment methods that claim mysterious magnetic or catalytic forces shall not be used. Follow treatment methods as directed by the manufacturer or water treatment company. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800311 | PM | PREVENT | Water treatment specialists must be properly trained. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800309 | PM | PREVENT | Be familiar with the Material Safety Data Sheets of any chemicals used in the water treatment program. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800307 | PM | PREVENT | Chemicals must comply with the Environmental Protection Agency (EPA) regulations and handled in accordance with occupational safety requirements. Employ personal protection against corrosive or hazardous treatment chemicals as appropriate. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800305 | PM | PREVENT | PM-TX0130ZZ-WTM-W09A-1, Water Treatment (Chemical) | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-WTM-W09A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800299 | PM | PREVENT | Check systems for cleanliness and clean if necessary. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800297 | PM | PREVENT | Operate valve in full open and close position. Loss of ability to close tightly will require inspection of valve seals and discs for wear and contaminate build- up. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800295 | PM | PREVENT | Assure that area is free of obstructions, that activation mechanisms are accessible to personnel in a distressed condition. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800292 | PM | PREVENT | Activate the unit to flush the line and verify proper operation. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800290 | PM | PREVENT | Where flow alarms have been installed, check with responding unit before activating the unit. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800284 | PM | PREVENT | Where units have been sealed, be certain seals are available to re-seal the unit after PM is accomplished. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800281 | PM | PREVENT | On non-plumbed units (units containing their own water supply), use manufacturer's instruction to perform maintenance. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800276 | PM | PREVENT | Review manufacturer's operation and maintenance instructions. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800271 | PM | PREVENT | PM-TX0130ZZ-EYE-W02A-1, Eyewash/Shower Unit | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-EYE-W02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800252 | PM | PREVENT | Clean up work area and remove trash. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800251 | PM | PREVENT | Remove tags, and restore to service. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800250 | PM | PREVENT | Install new filters. Make sure direction of airflow corresponds to the airflow shown on the filter and filters are properly sized to cover the opening. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800249 | PM | PREVENT | Inspect frame, clamps, etc. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800248 | PM | PREVENT | Vacuum filter section of air handler. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800247 | PM | PREVENT | Remove old filters. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800245 | PM | PREVENT | Filters should be replaced more often when static pressure readings indicate. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800243 | PM | PREVENT | De-energize, lock out, and tag fan electrical circuit. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800241 | PM | PREVENT | PM-TX0130ZZ-FLT-F32A-2, Filter, Air | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-FLT-F32A-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800233 | PM | PREVENT | Clean interior of cabinet. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800231 | PM | PREVENT | Clean and/or replace filters | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800229 | PM | PREVENT | Clean interior of cabinet. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800227 | PM | PREVENT | Clean and/or replace filters | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800225 | PM | PREVENT | De-energize, lock out, and tag electrical circuits. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800222 | PM | PREVENT | Obtain and review manufacturer's instructions. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800219 | PM | PREVENT | Schedule outage with operating personnel. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800215 | PM | PREVENT | De-energize, lock out, and tag electrical circuits. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800211 | PM | PREVENT | Schedule outage with operating personnel. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800208 | PM | PREVENT | PM-TX0130ZZ-VFD-X50B-2, Variable Frequency Drive | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-VFD-X50B-2 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800193 | PM | PREVENT | Check for correct time on time stamp. Reset if necessary. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800192 | PM | PREVENT | Inspect for legibility, that it is properly coded, and for punctures or markings on tape. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800191 | PM | PREVENT | Manually move ribbon to prevent ink from drying. (Papermarking type). | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800190 | PM | PREVENT | Examine alignment and tension of paper tape and supply of tape on reels. Install new tape when needed. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800189 | PM | PREVENT | Check prewound mechanisms. Rewind if necessary. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800187 | PM | PREVENT | Clean recording devices. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800185 | PM | PREVENT | This procedure is to be accomplished once weekly during the daily test and inspection required in Guide No. F-15C. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800183 | PM | PREVENT | Review manufacturer's instructions. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800180 | PM | PREVENT | PM-TX0130ZZ-ALM-F16A-1, Fire Detection and Alarm System | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Basement | TX0130ZZ-ALM-F16A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800155 | PM | PREVENT | Affix permanent record on extinguisher with year of hydrostatic test. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800153 | PM | PREVENT | Recharge extinguisher according to manufacturer's instructions. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800151 | PM | PREVENT | Weigh replacement cartridge to insure that it is full of gas. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800149 | PM | PREVENT | 150 degrees F. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800146 | PM | PREVENT | All dry chemical and dry powder extinguishers must have all traces of water removed from extinguishing agent, shell, hose and nozzle. A heated air stream is recommended with its temperature not exceeding | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800143 | PM | PREVENT | Observe shell and gauge for any distortion or leakage. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800141 | PM | PREVENT | Secure shell in protective cage and apply proper test pressure. Pressure to be applied at rate so test pressure is reached within one minute. Type of Extinguisher Hydrostatic Test Pressure Carbon dioxide 5/3 the service pressure | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800138 | PM | PREVENT | Fill with water and connect the test pump. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800136 | PM | PREVENT | Insert plug into shell opening. (External cartridge type extinguishers only). | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800135 | PM | PREVENT | Dismantle and remove all traces of extinguishing agent (dry chemical or dry powder), from inside of shell and hose assembly. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800134 | PM | PREVENT | Operate stored pressure and cartridge type extinguisher and check performance. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800133 | PM | PREVENT | Any cylinders that have been repaired by soldering or welding, damaged, corroded, burned, or had calcium chloride type of extinguishing agent used in stainless steel extinguisher shall not be hydrostatically tested but destroyed. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800132 | PM | PREVENT | Hydrostatic testing of extinguishers requires experienced personnel and suitable testing equipment. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800131 | PM | PREVENT | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | ||
| 26800130 | PM | PREVENT | Testing should be in accordance with NFPA Standard No. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800129 | PM | PREVENT | Dry chemical extinguishers, with the exception of ones with stainless steel shells (5 year) should be tested on a 1year basis. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800128 | PM | PREVENT | Soda acid, carbon dioxide, and foam extinguishers should be tested on a 5 year basis. | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800127 | PM | PREVENT | PM-TX0130ZZ-FEX-F24A-1, Fire Extinguishers | 4/12/18 22:44 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-FEX-F24A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800116 | PM | PREVENT | Clean up work area and remove trash. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800114 | PM | PREVENT | Remove tags, and restore to service. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800112 | PM | PREVENT | Install new filters. Make sure direction of airflow corresponds to the airflow shown on the filter and filters are properly sized to cover the opening. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800110 | PM | PREVENT | Inspect frame, clamps, etc. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800108 | PM | PREVENT | Vacuum filter section of air handler. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800106 | PM | PREVENT | Remove old filters. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800104 | PM | PREVENT | Filters should be replaced more often when static pressure readings indicate. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800102 | PM | PREVENT | De-energize, lock out, and tag fan electrical circuit. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800100 | PM | PREVENT | PM-TX0130ZZ-FLT-F32A-1, Filter, Air | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Floor 01-Air Handing Room | TX0130ZZ-FLT-F32A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800074 | PM | PREVENT | Clean up work area and remove trash. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800072 | PM | PREVENT | Remove tags, and restore to service. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800069 | PM | PREVENT | Install new filters. Make sure direction of airflow corresponds to the airflow shown on the filter and filters are properly sized to cover the opening. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800065 | PM | PREVENT | Inspect frame, clamps, etc. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800061 | PM | PREVENT | Vacuum filter section of air handler. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800057 | PM | PREVENT | Remove old filters. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800054 | PM | PREVENT | Filters should be replaced more often when static pressure readings indicate. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800048 | PM | PREVENT | De-energize, lock out, and tag fan electrical circuit. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800044 | PM | PREVENT | PM-TX0130ZZ-FLT-F32A-3, Filter, Air | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Roof | TX0130ZZ-FLT-F32A-3 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800004 | PM | PREVENT | Report any deficiencies on GSA Form 28 | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26800001 | PM | PREVENT | Restore flag pole special wrench in storage rack. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799997 | PM | PREVENT | Leave in the raised position and install locking pin. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799994 | PM | PREVENT | Raise and lower several times and check for proper operation. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799990 | PM | PREVENT | Check rope for deterioration. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799987 | PM | PREVENT | Grease pivot pin. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799984 | PM | PREVENT | Grease rack and gear assembly. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799979 | PM | PREVENT | Check for worn or damaged rack and gear and pivot pins in flag pole. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799975 | PM | PREVENT | Clean the rack and gear assembly. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799973 | PM | PREVENT | Using special wrench, lower the flag pole. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799971 | PM | PREVENT | Remove the locking pin. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799966 | PM | PREVENT | Accomplish this PM when the flag is not being flown or can be lowered. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799961 | PM | PREVENT | Do not accomplish this PM during adverse weather conditions. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799958 | PM | PREVENT | PM-TX0130ZZ-EFP-P21A-1, Flagpole, Electric | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Exterior-Outside | TX0130ZZ-EFP-P21A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799935 | PM | PREVENT | Clean off any corrosion or rust on damper frame and or damper blades, coat with proper type and color paint. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799933 | PM | PREVENT | Lubricate actuator linkage sparingly. Wipe off excess lubricant. DO NOT LUBRICATE actuator/drive stem. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799931 | PM | PREVENT | Check for air leaks around actuator and in air line between controller and actuator. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799929 | PM | PREVENT | Check actuator for proper operation. If it does not stroke properly, check for binding drive stem. If actuator still does not operate properly, replace the diaphragm (pneumatic actuators). | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799927 | PM | PREVENT | Lubricate mechanical connections sparingly. Wipe off excess. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799925 | PM | PREVENT | Check actuator/damper linkage for proper operation. Adjust if needed. Tighten operator arm set screws. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799922 | PM | PREVENT | Check damper surfaces for wear and clean vanes. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799919 | PM | PREVENT | Observe damper operation through full operating range, by activating controller. Adjust linkage on vanes if out of alignment. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799916 | PM | PREVENT | Check damper for freedom of movement and proper operation. | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26799913 | PM | PREVENT | PM-TX0130ZZ-DPP-C02A-1, Damper, Powered | 4/12/18 22:43 | PMADMIN07 | TX0130ZZ-Entire Building | TX0130ZZ-DPP-C02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798926 | PM | PREVENT | Lubricate the stem and lever pivot. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798923 | PM | PREVENT | Clean the valve body. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798921 | PM | PREVENT | Check that the discharge piping support is tight and not causing stress on the valve. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798918 | PM | PREVENT | Inspect support brackets and tighten as required. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798916 | PM | PREVENT | Inspect and hand lift the manual lifting lever, checking for binding of the stem or seat. Note that valve returns to proper position when the lever is released. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798913 | PM | PREVENT | Inspect condition of spring, flanges, and threaded connections. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798911 | PM | PREVENT | Check with foreman and operating personnel before performing this test. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798909 | PM | PREVENT | The safety relief valves are designed to be operated by system pressure and should only be tested when sufficient pressure exists to clear the seating area of any debris. | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798907 | PM | PREVENT | PM-TX0130ZZ-VLV-V02A-1, Valves | 4/12/18 22:39 | PMADMIN07 | TX0130ZZ-Floor 01 | TX0130ZZ-VLV-V02A-1 | APPR | 4/30/18 14:49 | TX0130ZZ | |
| 26798601 | PM | PREVENT | Leave transmitter panel in normal operating condition with door locked. Inform involved personnel that testing is complete. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798600 | PM | PREVENT | Clean interior of transmitter cabinet. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798599 | PM | PREVENT | Check the operation of each transmitter in all modes of operation by actuation of devices or contacts within the related fire alarm panel. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798598 | PM | PREVENT | Check each transmitter for proper code wheel alignment, loose or burned contacts or terminals. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798597 | PM | PREVENT | Check standby batteries (if located in the panel) for signs of overcharging, heat, and leakage. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798596 | PM | PREVENT | Check battery charge current (be sure it is within manufacturer's limits). | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798595 | PM | PREVENT | Check standby battery voltage under load for a minimum of 5 minutes (if applicable). | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798594 | PM | PREVENT | Check power supply output voltage in normal and under load conditions. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798593 | PM | PREVENT | Check all fuses. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798592 | PM | PREVENT | Check all lamps/LEDS (including remote annunciators). | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798591 | PM | PREVENT | Inspect the cabinet for damage (exterior and interior) including locks, door hinges, and plastic covers. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798590 | PM | PREVENT | When work requires the actuation of building evacuation systems, the work must be performed after hours and must be coordinated through the field office manager to prevent the unnecessary evacuation of the building's occupants. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798589 | PM | PREVENT | Deficiencies must be recorded. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798587 | PM | PREVENT | The work required by this procedure may cause the activation of the building fire alarm system and/or supervisory signal to the control center. The Field Office Manager and the control center that will receive the signal must be notified prior to start | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798584 | PM | PREVENT | PM-TX0126ZZ-ALM-F15B-1, Fire Detection and Alarm System | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01 | TX0126ZZ-ALM-F15B-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798560 | PM | PREVENT | Lubricate the stem and lever pivot. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798558 | PM | PREVENT | Clean the valve body. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798556 | PM | PREVENT | Check that the discharge piping support is tight and not causing stress on the valve. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798554 | PM | PREVENT | Inspect support brackets and tighten as required. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798552 | PM | PREVENT | Inspect and hand lift the manual lifting lever, checking for binding of the stem or seat. Note that valve returns to proper position when the lever is released. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798550 | PM | PREVENT | Inspect condition of spring, flanges, and threaded connections. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798548 | PM | PREVENT | Check with foreman and operating personnel before performing this test. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798546 | PM | PREVENT | The safety relief valves are designed to be operated by system pressure and should only be tested when sufficient pressure exists to clear the seating area of any debris. | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798545 | PM | PREVENT | PM-TX0126ZZ-VLV-V02A-1, Valves | 4/12/18 22:38 | PMADMIN07 | TX0126ZZ-Floor 01-Boiler Mechanical Room | TX0126ZZ-VLV-V02A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798538 | PM | PREVENT | Affix permanent record on extinguisher with year of hydrostatic test. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798536 | PM | PREVENT | Recharge extinguisher according to manufacturer's instructions. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798534 | PM | PREVENT | Weigh replacement cartridge to insure that it is full of gas. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798532 | PM | PREVENT | 150 degrees F. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798530 | PM | PREVENT | All dry chemical and dry powder extinguishers must have all traces of water removed from extinguishing agent, shell, hose and nozzle. A heated air stream is recommended with its temperature not exceeding | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798527 | PM | PREVENT | Observe shell and gauge for any distortion or leakage. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798524 | PM | PREVENT | Secure shell in protective cage and apply proper test pressure. Pressure to be applied at rate so test pressure is reached within one minute. Type of Extinguisher Hydrostatic Test Pressure Carbon dioxide 5/3 the service pressure | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798522 | PM | PREVENT | Fill with water and connect the test pump. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798519 | PM | PREVENT | Insert plug into shell opening. (External cartridge type extinguishers only). | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798516 | PM | PREVENT | Dismantle and remove all traces of extinguishing agent (dry chemical or dry powder), from inside of shell and hose assembly. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798513 | PM | PREVENT | Operate stored pressure and cartridge type extinguisher and check performance. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798511 | PM | PREVENT | Any cylinders that have been repaired by soldering or welding, damaged, corroded, burned, or had calcium chloride type of extinguishing agent used in stainless steel extinguisher shall not be hydrostatically tested but destroyed. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798507 | PM | PREVENT | Hydrostatic testing of extinguishers requires experienced personnel and suitable testing equipment. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798503 | PM | PREVENT | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | ||
| 26798500 | PM | PREVENT | Testing should be in accordance with NFPA Standard No. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798496 | PM | PREVENT | Dry chemical extinguishers, with the exception of ones with stainless steel shells (5 year) should be tested on a 1year basis. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798493 | PM | PREVENT | Soda acid, carbon dioxide, and foam extinguishers should be tested on a 5 year basis. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798490 | PM | PREVENT | PM-TX0126ZZ-FEX-F24A-1, Fire Extinguishers | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Entire Building | TX0126ZZ-FEX-F24A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798473 | PM | PREVENT | If treatment is not effective, it may require change in current methods and procedures. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798471 | PM | PREVENT | Record test results, action taken, type of chemicals, and treatment quantities used. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798468 | PM | PREVENT | If make up is excessive, determine source of leaks and correct. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798464 | PM | PREVENT | Add or adjust chemical and biological treatment dosages and water blow down as appropriate. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798461 | PM | PREVENT | Test each system for proper pH, alkalinity, total dissolved, hardness, conductivity, scale and corrosion inhibitors, and sludge conditioners. Test supply water for base conditions. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798459 | PM | PREVENT | Inspect boiler and piping system to determine effectiveness of water treatment. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798457 | PM | PREVENT | When boilers are out of service, they must be protected from corrosion either by draining the boiler and keeping surfaces thoroughly dry or by completely filling the boiler with properly tested with water. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798455 | PM | PREVENT | Follow the Recommended Rules for Care and Operation of Heating (or Power) Boilers as contained in the American Society of Mechanical Engineers. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798453 | PM | PREVENT | Maintain records and test results. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798451 | PM | PREVENT | Physical inspections of boilers and supply and return piping systems are to be made to determine water treatment effectiveness. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798449 | PM | PREVENT | Special attention must be paid to infrequently used boilers, or boilers subjected to long periods of idleness. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798447 | PM | PREVENT | Ensure chemicals are properly stored, test equipment clean, and that chemicals have not passed expiration date. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798445 | PM | PREVENT | Select water treatment methods which protect the life of equipment, maximize heat transfer, and minimize scale, corrosion, solid matter buildup, biological growth, and water usage. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798443 | PM | PREVENT | Maintenance includes chemicals, chemical feeding, maintaining proper water conditions, controlling blow down, protecting idle equipment, and records. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798439 | PM | PREVENT | Water treatment must be based on proven standard engineering practices. Treatment methods that claim mysterious magnetic or catalytic forces shall not be used. Follow treatment methods as directed by the manufacturer or water treatment company. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798436 | PM | PREVENT | Water treatment specialists must be properly trained. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798434 | PM | PREVENT | Be familiar with the Material Safety Data Sheets of any chemicals used in the water treatment program. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798432 | PM | PREVENT | Chemicals must comply with the Environmental Protection Agency (EPA) regulations and handled in accordance with occupational safety requirements. Employ personal protection against corrosive or hazardous treatment chemicals as appropriate. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798428 | PM | PREVENT | PM-TX0126ZZ-WTM-W-09A-1, Water Treatment (Chemical) | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Floor 01-Pump Room | TX0126ZZ-WTM-W-09A-1 | APPR | 4/30/18 14:47 | TX0126ZZ | |
| 26798400 | PM | PREVENT | Operate lift through it's full range of travel, in both directions, using a load if possible. Note operation of controls, safety devices, leveling, and other devices or features. | 4/12/18 22:37 | PMADMIN07 | TX0126ZZ-Exterior-Outside | TX0126ZZ-WLF-W07A-1 | APPR | 4/30/18 14:47 | TX0126ZZ |